Kolkata: KMRC has started sealing the last openings to the twin East-West Metro tunnels. The 98-feet deep shafts at the Esplanade metro station were built to launch the giant tunnel borers, Chundi and Urvi, in Jan-Feb 2019.
A shaft is a vertical pathway that provides access to underground tunnels. Normally, metro shafts are closed months before the third rail (carrying electricity) is laid to prevent electrocution. Contractors ITD-ITD Cementation, which has built the last 2.6 km Esplanade-Sealdah leg of East-West Metro, took enormous risks to accommodate the drastic change in work sequence, allowing civil construction (tracks, pipelines, electric cabling, signalling work, etc) and train trials to proceed simultaneously and prevent further delay of the project.
On Thursday, TOI sneaked a peek behind the cardboard partition that hides the 30m deep shafts from the East-West Metro's Esplanade station's functional area. The work will be over by July, said officials of KMRC, the implementing agency of East-West Metro, which is now veering toward its full 16.6 km run from Sector V to Howrah Maidan. The Esplanade-Sealdah section — the missing link between Sector V-Sealdah and Esplanade-Howrah Maidan — is finally ready for revenue operations.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Giao dịch CFD với công nghệ và tốc độ tốt hơn
IC Markets
Đăng ký
Undo
Ever since PM Modi inaugurated the 4.8km Esplanade-Howrah Maidan section (India's first under-river Metro), in March last year, the two shafts, one measuring 5.6mX4m to allow access to the west-bound or Howrah-bound tunnel, and another 3.1m-square opening for the eastbound or Sector V-bound tunnel, have been taking workers to the unfinished Esplanade-Sealdah section. The west-bound shaft was reduced from 10.5mX10.5m to its current size to make the subway linking East-West and North-South lines at Esplanade station more spacious.
The shaft closure involves construction of four slabs to cover each of the twin tunnels. The east-bound shaft has two are hatch covers (steel structures through which tunnels can be accessed during emergencies) and two concrete covers. The west-bound shaft will have one hatch cover and three concrete slab covers.
Get the latest lifestyle updates on Times of India, along with
Eid wishes
,
messages
, and
quotes
!

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Horti dept offers 50% subsidy on solar pumps for Mysuru, Chamarajanagar farmers
Horti dept offers 50% subsidy on solar pumps for Mysuru, Chamarajanagar farmers

Time of India

time41 minutes ago

  • Time of India

Horti dept offers 50% subsidy on solar pumps for Mysuru, Chamarajanagar farmers

Mysuru: The horticulture department has introduced a 50% subsidy on solar-powered irrigation pumps for growers in Mysuru and Chamarajanagar. Under the scheme, Rs 1 lakh will be provided for a 3 HP solar pump and Rs 3 lakh for a 5 HP pump. The initiative not only reduces operational costs, but also promotes sustainable irrigation over diesel or grid-powered systems. Farmers cultivating horticulture crops in their fields can apply for the scheme without the condition of having drip irrigation and sprinkler systems installed to avail themselves of the benefit. The department has given preference to small and marginal farmers in the first phase and plans to extend the scheme to others later. To obtain this benefit for the installation of solar pumps from the horticulture department, farmers must submit a written affidavit certified by Karnataka Renewable Energy Development Limited, stating that they did not benefit from KREDL and did not avail themselves of the benefit from the PM KUSUM scheme. Both Chamarajanagar and Mysuru districts have set a target of distribution for 213 farmers in the twin districts after identifying the beneficiaries taluk-wise in the 2025-26 financial year. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với sàn môi giới tin cậy IC Markets Tìm hiểu thêm Undo To avail themselves of the subsidy benefit from the horticulture department for the installation of solar pumps, farmers must obtain prior work order permission from the office of the deputy director of horticulture after submitting an application with their taluk assistant director of horticulture, Chamarajanagar deputy director of horticulture Shivarprasad told TOI. Farmers must install solar pumps after purchasing them from a certified company from the state energy department at their own cost, then claim the subsidy amount after full installation from the department, he said. He mentioned that apart from providing a 50% subsidy for the installation of solar pumps, his department has also provided a 75% subsidy to encourage honeybee farming for general category farmers and a 90% subsidy for SC/ST farmers. Speaking to TOI, deputy director of horticulture of Mysuru district, Manjunath Angadi said that the department has already given instructions to all taluk assistant directors of horticulture to start identifying the beneficiaries to avail themselves of the subsidy benefit for the installation of solar pumps in their horticulture fields and start distributing subsidies after the completion of installation. The department has decided to encourage farmers to adopt such renewable energy solutions by installing solar pumps. This scheme is entirely different from the PM Kusum scheme, he said.

Leo Daily Horoscope Today, June 08, 2025: Focus on progress, not perfection
Leo Daily Horoscope Today, June 08, 2025: Focus on progress, not perfection

Time of India

timean hour ago

  • Time of India

Leo Daily Horoscope Today, June 08, 2025: Focus on progress, not perfection

This day holds the energy of effort turning into something meaningful. What you do now, even if it feels small or ordinary, will create results that echo into the future. It is a powerful time for focused action. The universe is watching your intention more than your speed. Whether you take one step or ten, do it with your whole heart. Your actions today will not go unnoticed. Keep your attention on progress, not perfection. You are building something lasting. Leo Love Horoscope Today In love, small gestures made with sincerity will have a big emotional impact. If you're in a relationship, even one kind word or thoughtful act can strengthen the bond deeply. You don't need grand romance—real connection grows through everyday care. If single, don't underestimate the power of showing interest or expressing how you feel. One honest effort in love today may lead to a connection that stays. What you give from the heart today returns in beautiful ways later. Leo Career Horoscope Today Work brings opportunities to set a strong foundation. You may feel slightly overworked or stretched, but your efforts are not wasted. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Top Urologists: Frequent Urination & Weak Stream? Do this Before Bed Mens Health Learn More Undo Whether you are leading or supporting, give your best. Your consistency is being noticed, even if no one says it openly. This is a good day to finish pending tasks and show initiative. Don't doubt your abilities. What you do now will open doors in the near future. Keep your focus steady and your pace honest. Leo Money Horoscope Today Financially, this is the day to act with discipline and clarity. Spending should be limited to what is truly necessary. If you have been thinking of organizing your budget or starting a savings goal, begin now. A small financial decision today may grow into something stable tomorrow. Avoid impulsive purchases, and think long-term. Your money will respond well to thoughtful attention. Any effort made to manage finances today will help create security and peace in the days to come. Leo Health Horoscope Today Health may need attention to balance. You might feel slightly tired or mentally overactive due to ongoing stress. Don't ignore small signals from the body. Today is perfect for setting a health habit, even if it is just sleeping early or drinking more water. Take action now, even if it's a simple walk or warm meal. Your physical well-being needs daily commitment. Effort given to your health today will improve your strength tomorrow. Be kind to your body and it will support you fully. Discover everything about astrology at the Times of India , including daily horoscopes for Aries , Taurus , Gemini , Cancer , Leo , Virgo , Libra , Scorpio , Sagittarius , Capricorn , Aquarius , and Pisces .

Delhi considers building elevated road over ring road to ease chronic congestion
Delhi considers building elevated road over ring road to ease chronic congestion

Time of India

timean hour ago

  • Time of India

Delhi considers building elevated road over ring road to ease chronic congestion

N ew Delhi: With the city's Ring Road catering to heavier traffic than its capacity, Delhi govt is toying with the idea of building an elevated road over the existing 55-km stretch. PWD minister Parvesh Verma said he had already asked for a feasibility of such a project, with the proposed road to be built on pillars and connected with other arterial roads through ramps. Verma said he had discussed the plan with Union minister for road, transport and highways Nitin Gadkari and received a go-ahead from him. "This will be one of the biggest projects of this govt and will be completed within its term," Verma told TOI. The minister said that Delhi's two ring roads bear the maximum load of traffic and remain clogged during peak hours. Adding to the capacity of the existing road would help ease traffic on the existing one while also decongesting other roads that connect with Ring Road. "Since the new road will be entirely elevated, it can be built on pillars along the central verge of the existing road. The project will not require any acquisition of land and so can be completed within a given timeframe," Verma said. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Thousands Are Saving Money Using This Wall Plug elecTrick - Save upto 80% on Power Bill Click Here Undo Since a large volume of traffic using the Ring Road disperses on other important arterial roads such as Mathura Road, Aurobindo Marg, DND Flyway or head to the airport, Gurgaon, Rohtak Road and other highways, Verma said traffic movement would become obstruction-free with the construction of the new elevated road. "The cost of the construction of an elevated road comes to about Rs 100 crore per kilometre. This project can easily be completed at a cost of Rs 5,500-6,000 crore," the PWD minister said. Once a relatively efficient arterial corridor designed to decongest central areas and facilitate cross-city travel, Ring Road is now facing chronic congestion. Unlike the newer Outer Ring Road, developed later to redirect peripheral traffic, the inner Ring Road is buckling under mounting pressures. From urban sprawl and flawed planning to infrastructure saturation and enforcement gaps, a confluence of factors has brought the once-speedy corridor to a glacial pace. When Ring Road was originally planned in the 1950s and completed in the following decades, it was meant to serve a very different city — both in population and traffic volume. At the time, Delhi had fewer than three million residents. Today, the metro region is home to over 30 million. The road, however, has not expanded proportionately to accommodate this growth. What was once designed as a bypass route now functions as a semi-central road. As the city grew outward, neighbourhoods like South Extension, Punjabi Bagh, Lajpat Nagar and Ashram became dense mid-city urban hubs. Ring Road now cuts through commercial, institutional and residential areas. The corridor is used not just by through traffic but also by local traffic to access shops, markets, schools and hospitals — all of which generate frequent stops and lane intrusions. Intersections like AIIMS, Moolchand, Dhaula Kuan, Ashram and ITO are choke points where arterial routes intersect with heavy local traffic. While flyovers and underpasses have been built at some locations, they often only shift the congestion rather than resolve it. Delhi Traffic Police conducted a survey in 2024 and found that of 134 congestion hotspots, at least 12 were located on Ring Road and Outer Ring Road.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store