Solar farms forced to switch off as poles and wire delays hamper renewable transition
The Australian government has set a target of 82 per cent renewable energy by 2030 — from 35 per cent in 2023 — and a 43 per cent reduction in carbon emissions.
The Australian Energy Market Operator (AEMO) has previously laid out a $122 billion blueprint, known as the Integrated System Plan (ISP), for the country's electricity grid to achieve that goal without major disruption as ageing coal-fired generators are taken offline.
NSW's Eraring coal plant will cease operations in 2027, followed by Victoria Yallourn coal plant in 2028.
But AEMO has warned that delays and cost blowouts for a number of major transmission projects, particularly in Victoria, will severely curtail the amount of energy generated by renewable energy projects over the next two years.
'While some locations have not seen heavy congestion historically, they are nearing their current network limits and additional capacity may result in new areas of congestion,' AEMO's 2025 Enhanced Locational Information report published on Wednesday said.
Major transmission projects facing delays include the $3.3 billion VNI West, a 500 kV double circuit transmission line connecting the NSW and Victorian energy grids, the 700 kilometre EnergyConnect line between South Australia and NSW, and the 190 kilometre Western Renewables Link from western Victoria to Melbourne.
AEMO's analysis found no major solar farms in Victoria or South Australia were forecast to have a shut-off rate of less than 35 per cent by 2027, with that figure as high as 65 per cent for some projects.
'This is more pronounced in the near-term horizon, while improvements are seen in the medium term based on new actionable ISP projects being delivered, and as investment is made to meet required system security services which would begin to relax system security constraints,' the report said.
'Projected curtailment is particularly high in South Australia and Victoria in the near term, as these regions are further progressed in the renewable transition, and each further increase in capacity is more heavily curtailed by minimum security and export limitations.'
AEMO noted that there were approximately 20 gigawatts (GW) of projects currently at the application to connect stage, as well as the 300 GW of proposed future projects under consideration by developers using a range of technical and economic considerations to identify the most viable project locations.
'Opportunities exist in all National Electricity Market (NEM) regions for renewable and firming projects to deliver energy, capacity, and network support services,' AEMO executive general manager of system design Merryn York said in a statement.
'This report presents key locational data to help investors understand where their projects are most likely to succeed, and where challenges, such as network congestion, curtailment, or energy losses, may arise. Not all locations are equal, and geographic network conditions must be a critical part of investment decisions.'
AEMO's report warned some locations were already reaching 'significant levels' of congestion and curtailment.
In 2024, over half of all grid-scale wind and solar generation experienced network-driven curtailment of less than 1 per cent. Wind farms averaged 1.1 per cent network curtailment, but this was as high as 4.8 per cent for some units.
However for solar farms, curtailment averaged 4.5 per cent with several experiencing 'very high levels' of curtailment above 25 per cent.
'High curtailment was mainly concentrated in specific areas (particularly western New South Wales and north west Victoria), and illustrates that most transmission lines did not experience significant congestion,' AEMO said.
'The most severe network congestion arose in areas with high levels of generation connected in locations that were originally designed to service demand rather than supply. These high network congestion areas broadly overlap with the areas experiencing high levels of generation curtailment.'
The Clean Energy Council, which represents a number of solar investors impacted by the forecast curtailment, told The Australian Financial Review the slow rollout of transmission was affecting investment decisions.
'As the coal fleet exits, we need new capacity in the right places and quickly,' CEC spokesman Chris O'Keefe told the newspaper.
'Large-scale solar is fast and cost-effective to build, but it's also the most exposed to curtailment, especially when system security limits or negative prices hit in the middle of a sunny day.
'In the longer term, the only durable solution is new transmission. These transmission projects are absolutely essential to unlocking new generation and maintaining momentum in the transition.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

News.com.au
38 minutes ago
- News.com.au
Cyber City's owner Andrew Knox is laughing all the way to the bank with $15,000 collect for $200 bet
Cyber City's owner Andrew Knox is laughing all the way to the bank after he collected more than $15,000 for a $200 outlay when his roughie caused a huge upset at Doomben on Saturday. The David Murphy -trained gelding paid $51 when he crossed the finishing post a whopping seven lengths ahead of the fourth-placed $3 favourite Idyllic Affair in a 3YO Handicap over 1350m. 'The (2.1) multiplier on the Queensland TAB app gave me odds of 102/1 for a $100 bet,' a cashed-up Knox said on Sunday. 'Then I had $100 on at Ladbrokes for $51. Ladbrokes offered me an owner's bet – for up to $2000 you get your money back if the horse runs second or third. 'The night before when it came through on my phone it was $61 so I was kicking myself I didn't get on at that price. 'I picked up $15,000 for $200. I went and bought a carton of beer, I've got it in the fridge now. 'When he turned into the corner, I knew he had them because I was watching all the horses behind him and they just weren't progressing forward. 'I thought 'we've got this' and then when he started to kick around the 200m mark I thought 'this is over'.' 🗣ï¸� | "Cyber City by 5..." ðŸ�‡ CYBER CITY (3g) puts 5Ls on his rivals to win today's metro QTIS 3YO Handicap at Doomben over 1350m for trainer David Murphy. Raced and bred by Mr A Knox, the gelding is by Telemon Thoroughbreds SUN CITY. More â'¹ï¸� — Thoroughbred Breeders Queensland (@QldBreeders) August 16, 2025 Knox said he wasn't surprised at Cyber City's victory, believing the gelding should have won his previous race after being caught wide in a Maiden Plate (1100m) at Ipswich on July 31. Before that, Cyber City finished sixth to the Paul Shailer -trained filly Ha'penny Hatch, who went on to run in the $1m Group 2 BRC Sires Produce Stakes (1400m) at Eagle Farm in late May. 'If you go back and watch the replay, my horse could've beaten him that day or at least it would've been a fight at the end,' the 61-year-old Knox said. 'Cyber City got caught in a bunch of horses and got boxed in. He pulled up a little bit sore after the race so we put him in the paddock. 'He comes from a really good family. I've had the mare (Star Council) since about 2003 – I bought her as a yearling from the Brisbane Bloodstock sales.' • Concussed jockey 'should never have been allowed to go home' After saluting at Doomben on Saturday at 52kg, jockey Taylor Marshall said Cyber City had 'plenty of potential, he's very untapped and raw'. Murphy was worried that the 'aggressive' galloper would go too hard early but Marshall did well to get him into a nice rhythm. 'Once he gets a bit of experience then he'll settle down because he's like a bull at a gate at the moment,' said Knox, who was born and raised in Longreach and now flies between Brisbane and Western Australia as a FIFO mines worker driving road-trains. 'I know he'll get to a mile because the whole family have been really good milers. ' Longshoreman (whose dam was Star Council) was a very good horse over a mile, he won a Balaklava Cup (in 2014). 'Next year he'll be a really good winter carnival horse, that's what David's opinion was.'

News.com.au
39 minutes ago
- News.com.au
Thornbury auction: Bids increase by $215k in just 90 seconds
A first-home buyer couple gazumped their competition with a bid $50,000 more than a Thornbury villa's reserve price at an auction on Saturday. The property's lightning-fast sale unexpectedly came in at seven figures, instead of six. McGrath Northcote's Luke Brizzi said the young purchasers 'came in hard and fast' when the two-bedroom home at 1/79 Fyffe St went under the hammer. Near-knockdown home gets its entire back half cut off in incredible Thornbury renovation The couple were the second to bid, following an opening $825,000 bid from another buyer. Mr Brizzi described the $930,000 second bid as a bit of a surprise, as three buyers competed for the villa's keys. The renovated residence was listed with a $840,000-$880,000 range but ended up selling for $1.04m, 'Between the $825,000 and the $1.04m point, it was extremely fast – I reckon the time taken to get to the last bid would have been less than 90 seconds,' Mr Brizzi said. 'The auction would have been over in three minutes.' He said the buyers were excited and relieved to have secured a home. 'It was really nicely renovated,' he said. 'They said when they came to look at it, that it had a great feel, it wasn't too big or too small.' Almost 100 buyer groups inspected the villa during the sales campaign. The owner, who purchased the residence about three years ago and did the renovations, was all smiles following the auction. 'She was absolutely ecstatic,' Mr Brizzi said, adding the owner was moving as she and her growing family needed a bigger home. Mr Brizzi said there was a shortage of homes for sale at the moment, mostly due to the colder winter weather and owners waiting to see what the market would do in coming months. But he said the Reserve Bank decision to cut Australia's official cash rate by 0.25 percentage points last week was likely to give homeowners more confidence to list during spring. Another Saturday auction in Melbourne's southeastern suburbs saw a Cheltenham two-bedroom apartment with a courtyard sell for $551,000. The sum was $91,000 above the $460,000 reserve. Ray White Bayside Group's Angela Limanis said five bidders participated in the auction. 'It started off with a bang and we got to the reserve price in literally seconds,' Ms Limanis said. The new owner is a first-home buyer who had previously been renting in the inner city. Ms Limanis added that the RBA interest rate cut was causing buyers 'to give it everything they've got, because they might have to pay more for the same property in the future'.

News.com.au
39 minutes ago
- News.com.au
Inside new Mickleham home built to fight children's cancer
A brand-new house in Melbourne's north will be auctioned next month to raise funds for the My Room Children's Cancer Charity. The five-bedroom home at 36 Pasilla Circuit, Mickleham, was built by Henley Homes on a 412sq m land block donated by the Satterley Property Group. The 2025 Home for a Cure has been listed with $950,000-$1m price expectations. All proceeds from its sale will go towards My Room's efforts to help fund critical clinical care, family support services and research into rare and aggressive childhood cancers. The double-storey house features a kitchen fitted with 900mm stainless steel appliances, stone benchtops and a butler's pantry. A double-height void lets plenty of natural light in to the open-plan dining and living areas where sliding doors open to a covered outdoor space and large backyard. Upstairs, the main bedroom is equipped with a walk-in wardrobe and ensuite with a double vanity and separate toilet. Downstairs, three other bedrooms each have their own ensuite while the guest suite comes with a walk-in wardrobe and private ensuite. The house, modelled on a design from Henley's Mainvue Collection, boasts a 7-star energy rating thanks to its double-glazed windows and energy-efficient appliances. The abode is located in Satterley's Botanical estate where more than 30ha of open spaces, a shopping village and sports oval are planned to be built in the future. The Mickleham house is the third time Henley Homes and Satterley have collaborated for the Home for a Cure campaign. Satterley Property Group has partnered with Home For A Cure since 2018, donating eight land lots for homes to be built upon. My Room's chief executive Margaret Zita said no. 36 Pasilla Circuit 'represents the power of community to make a real difference'. 'Every dollar raised from its auction will help us provide essential support to families facing the unimaginable,' Ms Zita said. 'That includes emotional counselling, financial relief, clinical care roles and world-leading research.' Henley Homes's general manager of completed homes Ben Griffiths said the Home for a Cure was one of the most meaningful projects the company was involved in. 'From the entire Henley team, we give a huge shout out to the volunteer trades and suppliers who have donated their time and resources in making this amazing build a reality,' he added. Satterley's Victoria and Queensland general manager Jack Hoffman said the Home for a Cure initiative brought out the best in the industry. 'We are incredibly proud to contribute land for such an important cause and look forward to seeing strong interest at the open for inspections,' Mr Hoffman said. The house will be auctioned at 11am on September 6. Barry Plant Craigieburn's Romi Sleiman is managing the sales campaign.