
Express RTI: Uttarakhand finance dept questioned Beatles ashram revamp by Bimal Patel firm, state govt gave go-ahead
The documents, reviewed by The Indian Express, show that the Tourism department justified the selection of HCP through single-source procurement by pointing to the complexity of the heritage cum eco-tourism project, and the expertise of the 'world-class' company, which had executed major projects such as the Kashi Vishwanath Corridor and the Central Vista redevelopment near Parliament.
While the Finance department did come around to clearing the project, it recommended obtaining a priori the approval of the Forest department, and asked the Tourism department to ensure the rate reasonableness and the fees paid to the company, the documents showed.
Following rounds of discussion, the Uttarakhand Cabinet approved hiring HCP as the consultant on August 3, 2023. The Beatles ashram is situated inside the Rajaji National Park in Rishikesh and was visited by the British band in 1968.
While the cost of the consultancy is Rs 1.9 crore for the master plan lump sum and a fee of 4.75 per cent of the actual cost of the project for supervision support, Rs 15 lakh was levied for a one-day workshop, site visit, and broad design framework report. This was borne by the Tourism department, while the cost for the actual project will be borne by the Forest department.
The complex has nearly 25 buildings, of which 12 will be revamped in the upcoming project. The actual project cost is over Rs 98 crore. The project will primarily involve the retrofitting of structures by strengthening the reinforced concrete beams and slabs.
When contacted, Anand Patel, who helms the project at HCP, said that they received a request from the Tourism department in late 2021. 'We declined it then because the architectural intent was unclear. We visited the site twice or thrice, and in 2023 again, they requested and we submitted a proposal,' Patel said.
On the conditions set by the Finance department, Patel said he was unaware. 'The conditions by the Forest department were factored in, and our agenda is to make the buildings safe and improve awareness on yoga, art, forest, and wildlife of the area,' he said.
The bone of contention between the Finance and Tourism departments was over Rule 59 of Chapter 4 of the Uttarakhand Procurement Rules, 2017. This rule states that services from a single-source consultant can be obtained only after due justification is recorded and approval is obtained from the competent authority. For projects exceeding Rs 25 lakh, approvals from the administrative department and the finance department are mandatory.
In giving the approval, then finance secretary, Dilip Jawalkar, said in his June 20, 2023, letter that the consultancy fees should be justified on the basis of the firm's agreements with other governments, wherein the same firm has secured the work through a competitive process. He also said that the department should justify the rate reasonableness based on a market survey and after comparison with the rates discovered through a bidding process for similar or comparable assignments for the Uttarakhand government.
'The department should get a formal consent from the Forest department before taking the proposal before the Cabinet, since the general impression is that the Forest department keeps changing its decisions and fails to honour its commitments,' he said.
One of the officers in charge of the consultancy process, Satish Bahuguna, said that the Uttarakhand Tourism Development Board was not aware of the 'opinion' of the finance department on the matter, and whether the market survey suggested was conducted. 'This is the opinion of the department. If it goes to the cabinet and approval is given, the decision stands over any suggestions,' he said.
Jawalkar told The Indian Express that their responsibility is to 'give advice on the file of the department'. 'What department does subsequently is not in our purview,' he said.
The then tourism secretary, Sachin Kurve, did not respond to calls and messages seeking a comment.
Aiswarya Raj is a correspondent with The Indian Express who covers South Haryana. An alumna of Asian College of Journalism and the University of Kerala, she started her career at The Indian Express as a sub-editor in the Delhi city team. In her current position, she reports from Gurgaon and covers the neighbouring districts. She likes to tell stories of people and hopes to find moorings in narrative journalism. ... Read More

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Indian Express
34 minutes ago
- Indian Express
Jal Jeevan tender premium stopped, says Patil, flags ‘needless waste'
Amid concerns in sections of the government that work contracts have been inflated in some states under the Jal Jeevan Mission (JJM), Jal Shakti Minister C R Patil has said that the Centre has stopped the payment of tender premium under the rural tap water scheme — tender premium refers to the additional amount a bidder quotes, higher than the government's approved cost. Responding to a question at the Idea Exchange programme of The Indian Express (a detailed transcript of the interaction will be published next week), Patil said, 'Tender premium ka bhugtan humne rok diya hai. Jo thha, jo gaya hoga woh alag baat hai, magar jo naya hai usse poori tarah hamne rok diya hai. (We have stopped the payment of tender premium. What was there, what has gone is a different matter, but what is new has been completely stopped).' He said once the tender process is over, there should not be any facility like tender premium thereafter. 'We feel money is unnecessarily wasted,' he said. Patil said there will not be a provision for payment of tender premium in the new JJM guidelines to be announced for the next phase of the programme — the government has announced extension of the JJM until 2028. His remarks come at a time when sections of the government have expressed concern that JJM work contracts were inflated in some states. Earlier this year, an Expenditure Secretary-led panel recommended a 46 per cent cut in the Jal Shakti Ministry's proposal seeking Rs 2.79 lakh crore for completing the mission over four years ending December 2028. The payment of tender premium was prohibited in the original JJM guidelines. The 'Operational Guidelines for the Implementation of Jal Jeevan Mission: Har Ghar Jal', issued in December 2019, clearly stated that all schemes sanctioned under JJM would be implemented without cost and time overrun. 'In case of any cost escalation beyond the approved cost, it will have to be borne by the State and UTs with legislature concerned and no additional expenditure out of Central share will be permitted,' the guidelines stated. The 2019 guidelines also listed the tender premium in the 'Suggestive list of inadmissible expenses'. But in June 2022, the Ministry, with the approval of 'competent authority', made a crucial change in these guidelines. The Ministry defined the 'approved cost' and deleted 'tender premium' from the suggestive list of inadmissible expenses. 'The 'approved cost' for this purpose shall be the cost as discovered through an open, transparent and competitive bidding process as per prevailing Rules,' stated the amended guidelines circulated to the states on June 21, 2022. The new guidelines also stated that wherever such 'approved cost' was 10% to 25% more than the estimated cost at which the tender for a project/scheme was invited, approval by the Head of the State Level Scheme Sanctioning Committee (SLSSC) would have to be taken before award of work. Wherever such 'approved cost' was over 25% more than the estimated cost at which the tender for a project/scheme was invited, approval by the Head of the Apex Committee of the state Water and Sanitation Mission would have to be taken before award of the work, the guidelines stated. On May 21 this year, The Indian Express reported that an investigation of the data uploaded by states and UTs on the Jal Jeevan Mission dashboard showed that these crucial changes in the JJM guidelines three years ago lifted the check on expenditure, and led to cost escalations. This resulted in additional costs totalling Rs 16,839 crore for 14,586 schemes, an increase of 14.58 per cent from their estimated cost. Since the launch of the JJM in 2019, 6.4 lakh water supply schemes with total estimated cost of Rs 8.29 lakh crore – more than double of the scheme's original outlay of Rs 3.60 lakh crore (Centre: Rs 2.08 lakh crore, States:1.52 lakh crore) – have been approved by the states. To meet the additional requirement of funds, the Ministry had approached the Expenditure Finance Committee, headed by the Expenditure Secretary, to approve Rs 2.79 lakh crore additional Central funding over and above Rs 2.08 lakh crore. But the EFC recommended only Rs 1.51 lakh crore as the Central share, 46 per cent lower than what was sought by the Ministry. Harikishan Sharma, Senior Assistant Editor at The Indian Express' National Bureau, specializes in reporting on governance, policy, and data. He covers the Prime Minister's Office and pivotal central ministries, such as the Ministry of Agriculture & Farmers' Welfare, Ministry of Cooperation, Ministry of Consumer Affairs, Food and Public Distribution, Ministry of Rural Development, and Ministry of Jal Shakti. His work primarily revolves around reporting and policy analysis. In addition to this, he authors a weekly column titled "STATE-ISTICALLY SPEAKING," which is prominently featured on The Indian Express website. In this column, he immerses readers in narratives deeply rooted in socio-economic, political, and electoral data, providing insightful perspectives on these critical aspects of governance and society. ... Read More


India Today
an hour ago
- India Today
Families say Air India forced financial disclosures for Ahmedabad crash claims
Air India is facing serious allegations from families of the AI 171 crash victims, who claim the airline forced them to disclose financial dependency to get compensation. Over 40 families represented by the UK-based Stewarts Law have accused the airline of coercion and intimidation as they pursue claims related to the Ahmedabad crash in which over 250 people were to Stewarts, Air India allegedly pressured grieving families into disclosing sensitive financial details, including the extent of their financial dependence on the deceased, as a condition for receiving law firm claims the airline forced victims' families to sign forms under the threat that they would otherwise forfeit their right to any settlement or see the compensation amount reduced significantly. Stewarts also raised concerns over a questionnaire circulated by the airline, alleging that it was designed to lower potential compensation payouts by framing dependency in a way that could weaken the families' claims."This tactic has deeply distressed families already dealing with an immense loss," the firm India, in response to the accusations, has denied any wrongdoing. In an exclusive statement to India Today, the airline said the compensation process is being handled with 'flexibility and support".It added that dedicated support staff have been assigned to help families of the crash airline also stated that interim compensation has already been paid to 47 families, with more settlements currently in process. Air India reiterated its commitment to ensuring a fair and sensitive approach in dealing with all claims related to the AI 171 crash.- EndsTune InMust Watch


Time of India
an hour ago
- Time of India
Tajbagh beautification: Phase 1 completed, NMRDA awaits Rs 95.87 crore for phase 2
1 2 Nagpur: The Nagpur Metropolitan Region Development Authority (NMRDA) has almost completed the Rs 132.49 crore phase 1 of the Tajbagh renovation and beautification project and is now awaiting Rs 95.87 crore to start phase 2 of the project. Under the first phase, NMRDA strengthened and beautified the main dargah, constructed a shopping complex, a choti dargah, shops, and other structures, including marble flooring. According to NMRDA sources, Phase 1 of the project received Rs 132.49 crore administrative approval, out of which the agency received Rs 128.95 crore, while Rs 3.54 crore is pending. Out of the received funds, NIT spent Rs 127.50 crore and almost completed the works, with some work on the shopping complex and sandal room still pending. "Excluding the works on the encroached land, all other development works have been completed and handed over to the Hazrat Baba Tajuddin Trust. The inauguration of the project took place in November 2022. Subsequently, encroachment on the project land was removed, and the Hazrat Baba Tajuddin Trust made the land available. Accordingly, a tender for the remaining work was floated, and a work order for Rs 5.49 crore was issued to the contractor in October 2023. The deadline for completion of the work is set for March 2025, but it is still under way," said NMRDA sources. The proposal for the approval of the Detailed Project Report (DPR) Phase 2, worth Rs 224 crore, was submitted to the planning department in December 2022. NIT sources said that the proposal was approved in the district-level committee meeting held in March 2024. It was then forwarded to the govt for a final approval. The high-powered committee, in its meeting in March 2025, approved the revised proposal amounting to Rs 95.18 crore, which includes 18% Goods and Services Tax (GST) on the Rs 66.58 crore plan, along with 25% for other related components. NIT sources said that several components from the earlier proposal were dropped, including the entry gate on Umred Road, shopping complex, auditorium, e-library, housing scheme, and others. "Some of the important works approved included a boundary wall around the trust's 84-acre land, toilets, and decoration of the wall near the main Dargah, which will be done in the second phase after receiving funds from the govt," said sources.