Robex Kiniero Project on Track for First Gold in Q4

Robex Kiniero Project on Track for First Gold in Q4

Ottawa Citizen14-05-2025
Article content
HIGHLIGHTS:
Article content
Article content
Construction at Robex's Kiniero Gold Project, Guinea, remains on schedule and budget – first gold pour on track for Q4 CY25.
Project remains LTI free (lost time injury).
Phase 1 grade control drilling at Mansounia commenced on 18 March 2025 with 24,287m drilled as of 30 April.
SMP (Structural, Mechanical & Piping) Contract for process plant construction awarded and mobilisation commenced.
First four power station engines and generators completed and successfully tested for shipping in early June. Four remaining power station engines are scheduled for testing mid-June.
Mechanical and electrical equipment, piping and electrical materials on track for delivery within the working schedule.
ROM pad backfilling nearing completion.
Reclaim chamber suspended slab scheduled for late May as final major concrete pour. Process plant concrete 93% complete.
Structural steel and platework fabrication at 74% and 83% respectively progressed, with seven shipments of structural steel and two shipments of platework in transit to Kiniero; Field tank structures 56% progressed.
Preparation of Phase 1A of tailing storage facility (TSF) base is nearing completion with 450,000m2 of 800,000m2 liner placed. Construction of the main embankment has commenced and progressing well.
Fuel supply contract was awarded, and construction of the fuel storage facility has commenced.
Mill installation contract awarded with onsite works to commence in early June.
Contracts for mining and drill and blast being finalised, with mobilisation commenced. Full mobilisation in Q3 CY2025.
MoU signed with Vivo Energy to design Kiniero solar farm.
Article content
QUEBEC CITY, May 14, 2025 (GLOBE NEWSWIRE) — West African gold producer and developer Robex Resources Inc (' Robex ' or the ' Company ') (TSX-V: RBX) is pleased to provide a May 2025 project construction update for its Kiniero Gold Project in Guinea, West Africa. Robex is on track to deliver first gold at Kiniero in Q4 CY25. Robex expects to produce 155,000oz gold at Kiniero in 2026.
Article content
Article content
Article content
Article content
Article content
Article content
Article content
Figure 3: Tailings storage facility showing the extent of lining and main embankment construction (9 May 2025).
Article content
Robex's Managing Director and Chief Executive Officer Matthew Wilcox said: ' Our progress at Kiniero continues on budget and schedule, with some aspects of construction very near to completion, such as process plant construction, which is nearly done, and structural steel and platework fabrication also advanced. It continues to be very busy on site, but our teams are maintaining rigorous safety protocols, and we remain LTI free, which is pleasing. Contracts for mining as well as drill and blast services are being finalised with teams from our selected contractors mobilising to site to ensure this work commences on schedule. Grade control drilling at Mansounia has progressed well since commencing in March.
Article content
Article content
Having progressed our Initial Public Offer to raise $120 million before costs and list on the ASX in June in parallel with our busy construction schedule, I am grateful to both our construction and corporate teams for their hard work and dedication. We look forward to finalising remaining details over the next few months to ensure we achieve our goal of first gold in Q4.'
Article content
The SMP contract has commenced mobilisation and site establishment and will commence structural steel erection of the first process plant steelwork in early June. The milling installation contract has been awarded with key mill deliveries arriving to site and work for the mill installation will commence in early June. The tailings dam construction is progressing well, with more than 50% of the phase 1A lining completed.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Windsor getting $271K to help alleviate flooding
Windsor getting $271K to help alleviate flooding

CTV News

time3 hours ago

  • CTV News

Windsor getting $271K to help alleviate flooding

The Ontario government is investing $271,000 to support the implementation of the Sewer and Coastal Flood Protection Master Plan (SMP) in Windsor. This investment supports an immediate priority project identified in the SMP: sealing sanitary maintenance hole covers (MH Sealing) through the installation of rain catchers. The city is contributing approximately $96,000 toward this project. 'Windsor was hard hit by severe flooding events in 2016 and 2017, and we've put in the work to understand the causes, evaluate the short-term and long-term solutions, and get to work to make a difference,' said Ward 6 councillor Jo-Anne Gignac. 'Certainly, we cannot do this alone, and we are grateful for this investment from the province that supports work in areas of the city that are most vulnerable to the impacts of stormwater.' Funding for this project is part of Ontario's $7.3 million initiative to support local organizations across the province with projects that help strengthen the health and resilience of the Great Lakes and their connecting waterways. 'Flooding has been a real concern for families and homeowners in Windsor,' said Andrew Dowie, Member of Provincial Parliament for Windsor–Tecumseh. 'This funding will help the City take practical steps to reduce the risk of basement flooding and protect our neighbourhoods.' Rain catchers are designed to reduce the amount of rainwater entering maintenance holes, helping to lower the risk of basement flooding, particularly as the region experiences more frequent and severe weather events. This work is part of the City of Windsor's broader Sewer Master Plan (SMP), a 50+ year roadmap recommending about $5 billion in improvements. So far, the city has committed $419 million, with nearly $100 million already invested. 'The City of Windsor is committed to ending basement flooding, and we are working deliberately and strategically to realize that goal through key projects and initiatives identified in the Sewer and Coastal Flood Protection Master Plan,' said Windsor Mayor Drew Dilkens. As part of the MH Sealing project, around 1,000 rain catchers will be installed in low-lying, high-risk areas. These devices aim to prevent stormwater from entering the sanitary sewer system, reducing the likelihood of flooding, sewer overflows, and treatment plant bypasses. Installations will be tracked using GIS-based mapping for real-time monitoring and future infrastructure planning. The project supports climate resilience, system efficiency, and better flood protection for the community. Local Great Lakes initiatives are funded by two provincial programs, the Great Lakes Program and the Great Lakes Local Action Fund.

Tech stocks help lift S&P/TSX composite higher, U.S. stock markets mixed
Tech stocks help lift S&P/TSX composite higher, U.S. stock markets mixed

Winnipeg Free Press

time5 hours ago

  • Winnipeg Free Press

Tech stocks help lift S&P/TSX composite higher, U.S. stock markets mixed

TORONTO – Strength in technology stocks helped lift Canada's main stock index in late-morning trading, while U.S. markets were mixed. The S&P/TSX composite index was up 35.34 points at 27,794.02. In New York, the Dow Jones industrial average was down 143.06 points at 44,032.55. The S&P 500 index was down 0.09 points at 6,389.36, while the Nasdaq composite was up 35.81 points at 21,485.83. The Canadian dollar traded for 72.51 cents US compared with 72.72 cents US on Friday. The September crude oil contract was down nine cents US at US$63.79 per barrel. The December gold contract was down US$87.00 at US$3,404.30 an ounce. Monday Mornings The latest local business news and a lookahead to the coming week. This report by The Canadian Press was first published Aug. 11, 2025. Companies in this story: (TSX:GSPTSE, TSX:CADUSD)

Callinex to Change Name to Visionary Copper and Gold Mines Inc.
Callinex to Change Name to Visionary Copper and Gold Mines Inc.

Montreal Gazette

time5 hours ago

  • Montreal Gazette

Callinex to Change Name to Visionary Copper and Gold Mines Inc.

VANCOUVER, British Columbia, Aug. 11, 2025 (GLOBE NEWSWIRE) -- Callinex Mines Inc. (the 'Company' or 'Callinex') (TSX-V: CNX; OTCQX: CLLXF) is pleased to announce that it plans to change its name to 'Visionary Copper and Gold Mines Inc.' (the 'Name Change'). The Name Change better reflects the Company's forward-looking commitment to creating value through the discovery and development of sustainable copper and gold mines across Canada. The name Callinex has been a cornerstone of our identity, deeply rooted in our proud history in Manitoba. It has provided a strong foundation, guiding us through years of growth and many of our greatest achievements. As we move forward, the new name, Visionary Copper and Gold Mines Inc., embodies our long-term vision to lead in sustainable mining, delivering lasting value to our stakeholders and communities through the discovery and development of critical and precious metals deposits within established mining jurisdictions. The Company anticipates its new stock symbol will be "VCG" and that it will occur in early September 2025. Shareholders of the Company will not be required to exchange their existing share certificates for new certificates bearing the Company's new name. The name change does not affect the Company's share structure or the rights of the Company's shareholders, and no further action is required by existing shareholders of the Company. The Name Change remains subject to the acceptance by the TSX Venture Exchange. About Callinex Mines Inc. Callinex Mines Inc. (TSXV: CNX) (OTCQX: CLLXF) is advancing its portfolio of base and precious metals rich deposits located in established Canadian mining jurisdictions. The focus of the portfolio is highlighted by the 100% owned Point Leamington Deposit in Newfoundland, located in one of the richest VMS and Gold Districts in Canada. Callinex prepared a pit constrained Indicated Mineral Resource of 5.0 Mt grading 2.5 g/t AuEq for 402 koz AuEq (145.7 koz gold, 60.0 Mlb copper, 153.5 Mlb zinc, 2.0 Moz silver, 1.5 Mlb lead), a pit constrained Inferred Mineral Resource of 13.7 Mt grading 2.24 g/t AuEq for 986.5 koz AuEq (354.8 koz gold, 110.2 Mlb copper, 527.3 Mlb zinc, 6.2 Moz silver, 7.0 Mlb lead) and an out-of-pit Inferred Mineral Resource of 1.7 Mt grading 3.06 g/t AuEq for 168.5 koz AuEq (65.4 koz gold, 13.3 Mlb copper, 102.9 Mlb zinc, 1.4 Moz Ag, 2.6 Mlb lead) (see news release dated October 25, 2021). Additionally the Company is permitting the Rainbow deposit at its rich VMS Pine Bay Project located near existing infrastructure in the Flin Flon Mining District. Callinex prepared an indicated mineral resource on the Rainbow deposit of 3.44 Mt grading 3.59% CuEq for 272.4 Mlb CuEq (238.3 Mlb Cu, 56.9 Mlb Zn, 37.6 koz Au, 692.8 koz Ag, 2.3 Mlb Pb), an inferred mineral resource on the Rainbow deposit of 1.28 Mt grading 2.95% CuEq containing 83.4 Mlb CuEq (72.1 Mlb Cu, 19.5 Mlb Zn, 11.1 koz Au, 222.2 Koz Ag, 0.8 Mlb Pb) and an inferred mineral resource at the Pine Bay deposit of 1.0 Mt grading 2.62% Cu containing 58.1 Mlb Cu (see news release dated July 10, 2023). Additionally, the portfolio includes the Nash Creek Project located in the VMS rich Bathurst Mining District of New Brunswick. A 2018 PEA generates a strong economic return with a pre-tax IRR of 34.1% (25.2% post-tax) and NPV8% of $230 million ($128 million post-tax) at $1.25 Zinc (see news release dated May 14, 2018). For additional information, please contact: Callinex Mines Inc. Max Porterfield, President and Chief Executive Officer Phone: (604) 605-0885 E-mail: info@ Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. Some statements in this news release contain forward-looking information. These statements include, but are not limited to, statements with respect to future expenditures. These statements address future events and conditions and, as such, involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the statements. Such factors include, among others, the ability to complete the proposed drill program and the timing and amount of expenditures. Except as required under applicable securities laws, Callinex does not assume the obligation to update any forward-looking statement.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store