Traffic Chaos at Cotton Market Sq To Persist For At Least Four Months
2
Nagpur: Commuters passing through the busy Cotton Market Square will have to endure traffic snarls for at least four to five months more, as two major infrastructure projects continue to disrupt the area.
For the last three months, the area has been witnessing traffic snarls because of the simultaneous infrastructure projects, leaving commuters frustrated.
The Railways shut down the crucial underpass that connects Sitabuldi to Cotton Market for the extension of the fifth and sixth railway lines since the end of April. Simultaneously, MahaMetro barricaded large portions of the main square and installed temporary pillars as part of its ongoing Skywalk construction.
These simultaneous projects have created a major bottleneck, forcing motorists to take long detours and worsening congestion in the area.
With the underpass closed, motorists traveling from Gandhi Sagar towards Sitabuldi currently have to use the other underpass near Anand Talkies. However, at the entrance of this stretch, MahaMetro erected a temporary platform, which is affecting traffic movement.
Similarly, one of the major issues is the movement of heavy vehicles from the railway station side, which passes through the currently opened new underpass.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
New Container Houses Indonesia (Prices May Surprise You)
Container House | Search Ads
Search Now
Undo
The underpass regularly witnesses traffic jams, and the road has become narrow because of the work on the old underpass.
"The underpass at Cotton Market Square is an important link for both sides of the railway line. Since it was closed, the detour route is witnessing heavy traffic jams. Similarly, the square is also in bad condition due to MahaMetro's work, which has reduced the width of the road. The authorities should not have given permission for simultaneous works," said Vishrut Kale, a regular commuter.
In charge of the Cotton Market traffic zone, Pramod Pore said that the underpass is likely to remain closed for more than four to five months. "We gave permission to railways for six months. Currently, three months are completed, but the work could take another four to five months as they are laying the fifth and sixth railway lines. Similarly, MahaMetro's work will take at least three to four months to complete," said Pore, adding that they are regularly deploying traffic cops at the spot during peak hours to regulate traffic.
This means that the area will continue to witness crippled traffic for at least four to five months.
A senior MahaMetro official said that the skywalk work would be completed by the end of October, after which all the temporary structures would be removed.
Get the latest lifestyle updates on Times of India, along with
Friendship Day wishes
,
messages
and
quotes
!

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
37 minutes ago
- Time of India
Union proposes to convert old CNG autos to electric
Mumbai: The Mumbai Rickshawmen's Union has prepared a roadmap to convert existing old CNG autos in the city to electric autos by retrofitting. It has proposed to the MMRTA to allow drivers/permit holders to convert autos to electric once they reach the lifespan of 16 years in MMR. Such autos can switch to electric and ply on roads with zero permit and no pollution for another 5-10 years, union leader Thampy Kurien said. The union has been called to the transport commissioner's office for discussions on this issue on Thursday. Also, the cost of retrofitting is around Rs 1.6 lakh, which is less than the cost of a normal auto (Rs 2.8 lakh) and an e-auto (Rs 3.8 lakh). A proposed model of a retrofitted e-auto has been approved by RTO and registered in Pimpri Chinchwad, Pune. "The union will bring this auto to Mumbai for a demo and test drive on city roads. We will ask drivers to take multiple rides on all kinds of roads—narrow lanes or the arterial road. After getting good feedback, we plan to introduce these kinds of autos in Mumbai," Kurien said. The union has also petitioned the govt to set up more charging stations and will also push for battery swapping stations in the suburbs. Battery swapping can save significant time compared to charging an electric vehicle, particularly for electric three-wheelers. Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Treatment That Might Help You Against Knee Pain Knee pain| search ads Find Now Undo by Taboola by Taboola While charging can take hours, battery swapping can be completed in just a few minutes. You Can Also Check: Mumbai AQI | Weather in Mumbai | Bank Holidays in Mumbai | Public Holidays in Mumbai The city has nearly 3 lakh autos in the suburbs, with many of them nearing the lifespan of 16 years, after which they have to be phased out from the roads. "We are asking MMRTA to allow the autos to continue in electric mode so that the owners/drivers can continue to earn a livelihood," Kurien added. A source from the auto trade said: "There is one problem with having autos running on battery. There is no need for a permit in such vehicles, although they are registered with green number plates. So, these vehicles can ply in MMRTA as well as go to the far-off villages and operate."


Time of India
37 minutes ago
- Time of India
Govt gears up to issue e-khatas for 97 lakh rural properties
Bengaluru: In light of the govt planning to make e-khatas mandatory for property registrations from Oct, the rural development and panchayat raj (RDPR) department is gearing up to issue over 97 lakh e-khatas under a large-scale campaign titled 'Eswathu to doorsteps'. Unlike urban areas where digital literacy is relatively high and khata services are often accessed online, the move highlights the challenge of bridging the digital divide in rural regions. RDPR officials say the department manages about 1.5 crore property records — most of it still maintained manually in gram panchayat (GP) registers. Of these, over 97 lakh have been digitised and stored on the department's Panchatantra 2.0 platform. These records will now be used to issue e-khatas across Karnataka's villages, making it one of the largest rural documentation drives in recent times. You Can Also Check: Bengaluru AQI | Weather in Bengaluru | Bank Holidays in Bengaluru | Public Holidays in Bengaluru However, the department is aware of the steep learning curve that rural citizens and field-level staff may face when shifting to a fully online process. To ease the transition and ensure smooth implementation, the department will set up a dedicated eSwathu citizen helpdesk — essentially a professional call centre — to assist applicants, resolve queries, and handle grievances. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like One plan. Total peace of mind. ICICI Pru Life Insurance Plan Get Quote Undo "The proposed call centre will provide seamless support to citizens and enhance system accountability," an official said. "Each call will be recorded to improve service quality, and citizens can also lodge complaints if someone demands a bribe to issue an e-khata." The department says it is committed to penalising officials if allegations are supported by call records or related evidence. To avoid technical roadblocks, RDPR minister Priyank Kharge held meetings earlier this week with officials from National Informatics Centre (NIC), the department's data centre, and IT teams. He reviewed operational readiness and directed teams to fix technical issues before launch. "The department is in the process of making the Karnataka Gram Swaraj and Panchayat Raj (Gram Panchayat Taxes, Rates, and Fees) Rules, 2025 accessible to the public," Priyank said. "These rules will facilitate online issuance of e-khatas for over 97 lakh digitised properties available on the Panchatantra 2.0 platform. It will eliminate the need for citizens to visit GP offices for khata-related services." Rural citizens can begin the process by visiting the website where they can view their draft e-khata. They must submit basic details online, including Aadhaar number of the property owner, sale deed number (auto-fetched from the KAVERI system), BESCOM account ID (optional for vacant plots), and a photograph of the property. If the inputs match RDPR's digitised records, the final e-khata will be generated instantly. Discrepancies, if any, will be sent to the local GP official for verification.


Time of India
an hour ago
- Time of India
Govt engages Tata Tech to upgrade state polytechnics
Lucknow: The UP govt in collaboration with Tata Technology Limited (TTL) would set up Tata Technology Excellence Centres in 121 govt polytechnics across the state to help these technical educational institutes meet industry requirements. In a govt order (GO), additional chief secretary, technical education, Narendra Bhooshan said the decision was taken to bridge the industry-academia gap prevalent in the diploma sector of technical education. "In polytechnics, some topics have become irrelevant or are not in accordance with industry requirements. These centres will upgrade them and bridged the industry-academia gap," Bhooshan said. For this, Rs 57.3 crore will be spent on installation of machines and equipment in each of the 121 polytechnics. Of the total Rs 6935.8 crore, 87%, that is, Rs 6034.2 crore, will be borne by TTL, and the remaining 13% (Rs 1063.9 crore) by the govt. Also, the state govt will spend an additional Rs 858 crore – Rs 709.2 lakh per institution – towards civil infrastructure and other basic facilities. In the first phase, 45 polytechnic institutions will be upgraded. The project is aimed at providing quality technical education to students studying in the diploma sector of the state, thereby enhancing employment. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like How Retirees Can Potentially Minimize RMD Taxes SmartAsset Learn More Undo It will also help students acquire essential skills like soft skills and personality development as per industry requirements. As per the GO, TTL will involve global partner companies and institutions in upgrading the polytechnics. TTL will also prepare the project document related to the execution of the upgradation work and determine short, medium, and long-term strategies in it. In addition, they will prepare a baseline study report related to the status of the polytechnic institutions before the implementation of the project. TTL will also make available two trainers for the first two years and one trainer for the third year in each selected institute from its own sources. Besides, it will ensure the availability of training material, an online platform for training, and experts from industries as per demand in all 121 institutes and organise dialogue programmes at regular intervals.