Incomplete structures in Kilmore Road development facing demolition

Incomplete structures in Kilmore Road development facing demolition

Irish Examiner4 days ago
Cork City Council spent almost €2.5m on a controversial and unfinished 24-house development on the city's northside, but it is unclear how many of the incomplete structures are now being demolished.
In March 2020, a private contractor began work on 24 houses on Kilmore Rd in Knocknaheeny before work ground to a halt a few months later in what Cork City Council described as 'a complex contractual dispute'.
The houses were being built under phase 2c of the Cork Northwest Quarter Regeneration (CNWQR) project, a huge multi-annual, phased regeneration project which began in the Knocknaheeny and Hollyhill area more than a decade ago.
The CNWQR, adopted by the council in November 2011, involves the demolition of 450 houses and the design and construction of more than 600 new homes.
Last year, the council resolved its dispute with the Phase 2c contractors, and reissued the tender for the project, costed at an estimated €5m. Works eventually began this summer under a new contractor.
At a recent council meeting, Sinn Féin's Kenneth Collins asked the total sum paid to the original contractor and 'the percentage amount of work complete that will require demolition and the cost of this demolition'.
He was told the original contractor had been paid €2,452,317, ex Vat, in May 2024, and '0% of the works complete will require demolition'.
Rectification and completion works
Asked by the Irish Examiner how this claim squared with photographic evidence of current demolition work, a council spokesperson clarified that the council had engaged a contractor to undertake 'rectification and completion works on the 24-unit housing development at Kilmore Road Lower".
'These works include the demolition and taking down of incomplete works.
'Works that have been certified as complete which were undertaken by the initial contractor do not require demolition,' they said.
When asked how much of the development was not certified as complete, a spokesperson admitted that, in fact, none of the 24 homes had been completed by the original contractor.
'Zero homes are certified as complete,' the spokesperson said.
'We are still within a construction contract and practical completion of the contract has not been reached.'
In a subsequent email, they said not all of the initial works were being demolished but they did not immediately respond when asked how many of the buildings were being retained.
Almost two weeks after his initial question, Mr Collins said he was again asking how much of the original work was being demolished.
'I can't understand why we can't get a straight answer, but first we're told 0% required demolition, then they say it's 0% of completed buildings and now they say none of the buildings were completed, but some aren't being demolished,' he said.
So how many of the buildings are being demolished? Why can't the council answer a simple question?
'This is a long running saga. The people of Knocknaheeny want these homes built.
'They've lived opposite and beside a building site for years on end. The council have broken commitment after commitment when it came to this site.
In its most recent statement, a council spokesperson said: 'Works undertaken by the initial contractor would have constituted approximately 55% of the project.
'The new contractor is now at approximately 60% (plus c5% on the initial signed off works) completion overall as they have recently commenced.
'As per previous all works signed off in that approximately 55% are to be retained. A minor percentage of works not signed off were not retained.'
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Deep pride in Cork as Michael Collins' diary from 1919 goes on display in Clonakilty for August
Deep pride in Cork as Michael Collins' diary from 1919 goes on display in Clonakilty for August

Irish Independent

time4 hours ago

  • Irish Independent

Deep pride in Cork as Michael Collins' diary from 1919 goes on display in Clonakilty for August

For the fourth year in a row, the National Archives, in partnership with Cork County Council, has sent one of Irish independence leader Michael Collins' working diaries to be displayed in the museum dedicated to him in his hometown of Clonakilty. This year's diary is the 1919 edition and highlights a lesser-known aspect of Collins' work – his international connections. Alongside the diary, visitors to the Michael Collins House Museum can peruse a selection of letters exchanged between Collins and Donal Hales, a fellow Cork man who was an Irish diplomat based in Italy from 1919 to 1922. Hales, a brother of West Cork IRA leaders Tom and Sean, sought to gain diplomatic recognition for the nascent Irish republic from both the Italian government and the papacy. He also tried, unsuccessfully, to organise arms shipments from Italy to Ireland. The Cork man regularly sent Collins Italian newspaper clippings and reports on European sentiment toward Ireland's independence movement. In return, Collins shared candid updates on the escalating conflict, political developments, and the challenges of building a new state. The diaries, which cover the period from 1918 to 1922, have been officially loaned to the National Archives by the Collins family. They have now been digitised and can be explored on a touchscreen at the Michael Collins House Museum and the National Archives in Dublin. The pocket-sized books are terse records of the daily meetings, appointments and tasks of a busy man trying to run a guerilla war and organise a national loan for a new state while avoiding capture by the British administration in Ireland. 'They're operational diaries, essentially that's what they are. They give a good insight into the internal workings of Collins' mind. When you look at the diaries, you can see Collins was very good at his to-do lists,' the museum's general manager Jamie Murphy told the Irish Independent. The diary will be on display until August 31. The Michael Collins House Museum, which is funded by Cork County Council, is located at 7 Emmet Square in Clonakilty. Opening hours are Tuesday to Sunday 9am – 6pm and admission is free. Funded by the Local Democracy Reporting Scheme.

MSD won't close Irish sites as part of $3bn cutbacks
MSD won't close Irish sites as part of $3bn cutbacks

Irish Examiner

time2 days ago

  • Irish Examiner

MSD won't close Irish sites as part of $3bn cutbacks

Pharmaceutical giant MSD is slashing $3bn (€2.59bn) from its annual spending as part of global job cut but said it will not be closing any of its Irish sites. MSD yesterday announced a global cost-cutting exercise as it prepares for generic competition to its Irish-manufactured cancer drug Keytruda, the world's best-selling medicine, which is predominantly made in Ireland. The company will cut administrative, sales and research jobs, with increased focus on the US market. It has not said where the roles will be lost or if any Irish workers will be among those affected. However, a spokesperson told the Irish Examiner: "The restructuring announced today does not include site closures in Ireland." MSD employs more than 3,000 people at eight locations in Ireland. These include MSD Brinny in Co Cork specialising in development and manufacture of innovative novel vaccines and testing of immuno-oncology medicines; three facilities in Dublin (MSD Biotech, MSD Blackrock, and MSD Red Oak North); MSD Carlow; MSD Dunboyne in Co Meath; MSD Ballydine in Co Tipperary, the company's first Irish site; and MSD Dundalk, the former WuXi Vaccines sites acquired in January. The cost cuts will include $1.7bn (€1.47bn) in annual savings from the elimination of certain administrative, sales and R&D positions, MSD said. The company expects the restructuring to be completed by the end of 2027, the year before Keytruda's key patents expire and the drug faces US government price cuts. The company said it plans to reinvest the savings into developing new drugs and launching new products. EU-branded medicines will face 15% import tariffs under the new transatlantic trade deal agreed between the European bloc and the US at the weekend. Like many other pharmaceutical firms based in Ireland, MSD had stockpiled doses of Keytruda manufactured in Ireland, to protect itself from tariffs imposed in 2025. MSD previously disclosed plans to invest more than $9bn (€7.78bn) in US manufacturing over the next four years, part of an effort to make more of its medicines in the US. The company reiterated that it expects to spend $200m (€172m) on tariffs in 2025, a number that reflects levies already in place and doesn't account for future tariffs on pharmaceuticals.

Incomplete structures in Kilmore Road development facing demolition
Incomplete structures in Kilmore Road development facing demolition

Irish Examiner

time4 days ago

  • Irish Examiner

Incomplete structures in Kilmore Road development facing demolition

Cork City Council spent almost €2.5m on a controversial and unfinished 24-house development on the city's northside, but it is unclear how many of the incomplete structures are now being demolished. In March 2020, a private contractor began work on 24 houses on Kilmore Rd in Knocknaheeny before work ground to a halt a few months later in what Cork City Council described as 'a complex contractual dispute'. The houses were being built under phase 2c of the Cork Northwest Quarter Regeneration (CNWQR) project, a huge multi-annual, phased regeneration project which began in the Knocknaheeny and Hollyhill area more than a decade ago. The CNWQR, adopted by the council in November 2011, involves the demolition of 450 houses and the design and construction of more than 600 new homes. Last year, the council resolved its dispute with the Phase 2c contractors, and reissued the tender for the project, costed at an estimated €5m. Works eventually began this summer under a new contractor. At a recent council meeting, Sinn Féin's Kenneth Collins asked the total sum paid to the original contractor and 'the percentage amount of work complete that will require demolition and the cost of this demolition'. He was told the original contractor had been paid €2,452,317, ex Vat, in May 2024, and '0% of the works complete will require demolition'. Rectification and completion works Asked by the Irish Examiner how this claim squared with photographic evidence of current demolition work, a council spokesperson clarified that the council had engaged a contractor to undertake 'rectification and completion works on the 24-unit housing development at Kilmore Road Lower". 'These works include the demolition and taking down of incomplete works. 'Works that have been certified as complete which were undertaken by the initial contractor do not require demolition,' they said. When asked how much of the development was not certified as complete, a spokesperson admitted that, in fact, none of the 24 homes had been completed by the original contractor. 'Zero homes are certified as complete,' the spokesperson said. 'We are still within a construction contract and practical completion of the contract has not been reached.' In a subsequent email, they said not all of the initial works were being demolished but they did not immediately respond when asked how many of the buildings were being retained. Almost two weeks after his initial question, Mr Collins said he was again asking how much of the original work was being demolished. 'I can't understand why we can't get a straight answer, but first we're told 0% required demolition, then they say it's 0% of completed buildings and now they say none of the buildings were completed, but some aren't being demolished,' he said. So how many of the buildings are being demolished? Why can't the council answer a simple question? 'This is a long running saga. The people of Knocknaheeny want these homes built. 'They've lived opposite and beside a building site for years on end. The council have broken commitment after commitment when it came to this site. In its most recent statement, a council spokesperson said: 'Works undertaken by the initial contractor would have constituted approximately 55% of the project. 'The new contractor is now at approximately 60% (plus c5% on the initial signed off works) completion overall as they have recently commenced. 'As per previous all works signed off in that approximately 55% are to be retained. A minor percentage of works not signed off were not retained.'

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store