Robex Progresses Kiniero Toward First Gold in Q4 2025
Construction at Robex's Kiniero Gold Project, Guinea, remains on schedule and budget - first gold pour on track for Q4 CY25.
Project remains LTI free (lost time injury).
Grade control drilling phase 1 contract awarded; drilling has commenced.
SMP (Structural, Mechanical & Piping) contract for process plant construction awarded; contractor to mobilise in May 2025.
Process plant engineering and detailed design are complete.
The first four power station engines and generators are nearing completion, with testing scheduled for mid-April at Hyundai's factory.
Purchase orders raised for key mechanical and electrical equipment including Train B CIL agitators, pebble crusher and conveyor drives.
Primary crusher ROM wall completed, and ROM pad backfilling has commenced.
SAG and Ball mill concrete foundations are 100% complete.
Structural steel and platework fabrication at 55% complete, with four shipments of structural steel collected and in transit to Kiniero. Platework deliveries will commence next month.
Concrete work for the process plant is progressing on schedule, with 85% (7,065m3) of concrete poured to date. Concrete work for the power station and fuel storage has commenced.
Tank structures are 42% complete, with all six tanks for the CIL Train A circuit at full height.
Clearing for the tailings storage facility (TSF) is complete and the TSF base is being progressively prepared. Lining (HDPE) commenced with more than 90,000m2 laid in March.
QUEBEC CITY, April 02, 2025 (GLOBE NEWSWIRE) -- West African gold producer and developer Robex Resources Inc ('Robex' or the 'Company') (TSX-V: RBX) is pleased to provide a March 2025 project construction update for its Kiniero Gold Project in Guinea, West Africa. Robex is on track to deliver first gold at Kiniero in Q4 CY25. Robex expects to produce 155,000oz gold at Kiniero in 2026.
Figure 1: Overall view of the process plant looking southwest (22 March 2025).
Figure 2: Kiniero overview showing completed mill foundations and CIL tanks (28 March 2025).
Figure 3: Tailings storage facility showing the extent of lining completed (22 March 2025).
Robex's Managing Director and Chief Executive Officer Matthew Wilcox said:
'Kiniero continues to progress to schedule and budget and we remain on track to achieve first gold pour at the project in Q4 2025. It is exciting to see this project taking shape, and our teams working together in a safe and responsible manner to achieve this deadline. It continues to be incredibly busy on site with many key aspects of the project now coming into play. We are keeping a close eye on our targets to ensure they remain achievable as we work towards first gold by the end of the year.'
Construction Activities
Construction continues to track well against the schedule, with the SAG and ball mill foundation completed. The primary crusher ROM wall is now complete, and backfilling of the ROM pad has commenced. Lining of the tailings storage facility commenced in March. Power station concrete works commenced with excavation and blinding of the engine bases. The following figures show a snapshot of the progress achieved on site during March 2025.
Figure 4: Primary crusher ROM wall and chamber
Figure 5: View of reclaim chamber and primary crusher
Figure 6: Excavation of power station engine bases
Figure 7: Grade control drilling commenced at Mansounia pit
Figure 8: First four power station generators and engines nearing completion
Figure 9: Structural steel packed for shipping and platework chutes ready for collection
Next Steps
Award major contracts including Mill installation, mining, haulage and drill and blast.
Commence design of the solar farm.
Mobilisation of SMP contractor in Q2 CY2025.
Mobilisation of mining contractor in Q3 CY2025.
Robex remains very well positioned to advance the construction of Kiniero, which remains on schedule to realise first gold production by Q4 CY25. Robex expects Kiniero to produce 155,000oz gold in 2026.
For more information
Certain information set forth in this news release contains 'forward‐looking statements' and 'forward‐looking information' within the meaning of applicable Canadian securities legislation (referred to herein as 'forward‐looking statements'). Forward-looking statements are included to provide information about Management's current expectations and plans that allows investors and others to have a better understanding of the Company's business plans and financial performance and condition.
Statements made in this news release that describe the Company's or Management's estimates, expectations, forecasts, objectives, predictions, projections of the future or strategies may be 'forward-looking statements', and can be identified by the use of the conditional or forward-looking terminology such as 'aim', 'anticipate', 'assume', 'believe', 'can', 'contemplate', 'continue', 'could', 'estimate', 'expect', 'forecast', 'future', 'guidance', 'guide', 'indication', 'intend', 'intention', 'likely', 'may', 'might', 'objective', 'opportunity', 'outlook', 'plan', 'potential', 'should', 'strategy', 'target', 'will' or 'would' or the negative thereof or other variations thereon. Forward-looking statements also include any other statements that do not refer to historical facts. Such statements may include, but are not limited to, statements regarding: the perceived merit and further potential of the Company's properties; the Company's estimate of mineral resources and mineral reserves (within the meaning ascribed to such expressions in the Definition Standards on Mineral Resources and Mineral Reserves adopted by the Canadian Institute of Mining Metallurgy and Petroleum ('CIM Definition Standards') and incorporated into National Instrument 43-101 – Standards of Disclosure for Mineral Projects ('NI 43-101')); capital expenditures and requirements; the Company's access to financing; preliminary economic assessments (within the meaning ascribed to such expressions in NI 43-101) and other development study results; exploration results at the Company's properties; budgets; strategic plans; market price of precious metals; the Company's ability to successfully advance the Kiniero Gold Project on the basis of the results of the feasibility study (within the meaning ascribed to such expression in the CIM Definition Standards incorporated into NI 43-101) with respect thereto, as the same may be updated, the whole in accordance with the revised timeline previously disclosed by the Company; the potential development and exploitation of the Kiniero Gold Project and the Company's existing mineral properties and business plan, including the completion of feasibility studies or the making of production decisions in respect thereof; work programs; permitting or other timelines; government regulations and relations; optimization of the Company's mine plan; the future financial or operating performance of the Company and the Kiniero Gold Project; exploration potential and opportunities at the Company's existing properties; costs and timing of future exploration and development of new deposits; the Company's ability to enter into definitive documentation in respect of the USD115 million project finance facility for the Kiniero Gold Project (including a USD15 million cost overrun facility, the 'Facilities'), including the Company's ability to restructure the Taurus USD35 million bridge loan and adjust the mandate to accommodate for the revised timeline of the enlarged project; timing of entering into definitive documentation for the Facilities; if final documentation is entered into in respect of the Facilities, the drawdown of the proceeds of the Facilities, including the timing thereof; and the Company's ability to reach an agreement with the Malian authorities to establish a sustainable new tax framework for the Company, and for the sustainable continuation of the Company's activities and further exploration investments at Nampala.
Forward-looking statements and forward-looking information are made based upon certain assumptions and other important factors that, if untrue, could cause the actual results, performance or achievements of the Company to be materially different from future results, performance or achievements expressed or implied by such statements or information. There can be no assurance that such statements or information will prove to be accurate. Such statements and information are based on numerous assumptions, including: the ability to execute the Company's plans relating to the Kiniero Gold Project as set out in the feasibility study with respect thereto, as the same may be updated, the whole in accordance with the revised timeline previously disclosed by the Company; the Company's ability to reach an agreement with the Malian authorities to establish a sustainable new tax framework for the Company, and for the sustainable continuation of the Company's activities and further exploration investments at Nampala; the Company's ability to complete its planned exploration and development programs; the absence of adverse conditions at the Kiniero Gold Project; the absence of unforeseen operational delays; the absence of material delays in obtaining necessary permits; the price of gold remaining at levels that render the Kiniero Gold Project profitable; the Company's ability to continue raising necessary capital to finance its operations; the Company's ability to restructure the Taurus USD35 million bridge loan and adjust the mandate to accommodate for the revised timeline of the enlarged project; the Company's ability to enter into definitive documentation for the Facilities on acceptable terms or at all, and to satisfy the conditions precedent to closing and advances thereunder (including satisfaction of remaining customary due diligence and other conditions and approvals); the ability to realize on the mineral resource and mineral reserve estimates; and assumptions regarding present and future business strategies, local and global geopolitical and economic conditions and the environment in which the Company operates and will operate in the future.
Certain important factors could cause the Company's actual results, performance or achievements to differ materially from those in the forward-looking statements including, but not limited to: geopolitical risks and security challenges associated with its operations in West Africa, including the Company's inability to assert its rights and the possibility of civil unrest and civil disobedience; fluctuations in the price of gold; limitations as to the Company's estimates of mineral reserves and mineral resources; the speculative nature of mineral exploration and development; the replacement of the Company's depleted mineral reserves; the Company's limited number of projects; the risk that the Kiniero Gold Project will never reach the production stage (including due to a lack of financing); the Company's capital requirements and access to funding; changes in legislation, regulations and accounting standards to which the Company is subject, including environmental, health and safety standards, and the impact of such legislation, regulations and standards on the Company's activities; equity interests and royalty payments payable to third parties; price volatility and availability of commodities; instability in the global financial system; the effects of high inflation, such as higher commodity prices; fluctuations in currency exchange rates; the risk of any pending or future litigation against the Company; limitations on transactions between the Company and its foreign subsidiaries; volatility in the market price of the Company's shares; tax risks, including changes in taxation laws or assessments on the Company; the Company's inability to successfully defend its positions in negotiations with the Malian authorities to establish a new tax framework for the Company, including with respect to the current tax contingencies in Mali; the Company obtaining and maintaining titles to property as well as the permits and licenses required for the Company's ongoing operations; changes in project parameters and/or economic assessments as plans continue to be refined; the risk that actual costs may exceed estimated costs; geological, mining and exploration technical problems; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; the effects of public health crises, such as the COVID-19 pandemic, on the Company's activities; the Company's relations with its employees and other stakeholders, including local governments and communities in the countries in which it operates; the risk of any violations of applicable anticorruption laws, export control regulations, economic sanction programs and related laws by the Company or its agents; the risk that the Company encounters conflicts with small-scale miners; competition with other mining companies; the Company's dependence on third-party contractors; the Company's reliance on key executives and highly skilled personnel; the Company's access to adequate infrastructure; the risks associated with the Company's potential liabilities regarding its tailings storage facilities; supply chain disruptions; hazards and risks normally associated with mineral exploration and gold mining development and production operations; problems related to weather and climate; the risk of information technology system failures and cybersecurity threats; and the risk that the Company may not be able to insure against all the potential risks associated with its operations.
Although the Company believes its expectations are based upon reasonable assumptions and has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. These factors are not intended to represent a complete and exhaustive list of the factors that could affect the Company; however, they should be considered carefully. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information.
The Company undertakes no obligation to update forward-looking information if circumstances or Management's estimates, assumptions or opinions should change, except as required by applicable law. The reader is cautioned not to place undue reliance on forward-looking information. The forward-looking information contained herein is presented for the purpose of assisting investors in understanding the Company's expected financial and operational performance and results as at and for the periods ended on the dates presented in the Company's plans and objectives, and may not be appropriate for other purposes.
See also the 'Risk Factors' section of the Company's Annual Information Form for the year ended December 31, 2023, available under the Company's profile on SEDAR+ at www.sedarplus.ca or on the Company's website at www.robexgold.com, for additional information on risk factors that could cause results to differ materially from forward-looking statements. All forward-looking statements contained in this news release are expressly qualified by this cautionary statement.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
3 hours ago
- Yahoo
Orezone Gold Reports Second Quarter 2025 Results
All dollar amounts are in USD unless otherwise indicated and abbreviation 'M' means million. VANCOUVER, British Columbia, Aug. 13, 2025 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX/ASX: ORE, OTCQX: ORZCF) ('Orezone' or 'Company') is pleased to report its operational and financial results for the three and six months ended June 30, 2025. The Company will host a conference call and webcast today at 2:00pm PT / 5:00pm ET (August 14, 7:00am AEST) to discuss the results. Details to join the conference call and webcast are provided at the end of this release. Second Quarter 2025 Highlights Gold production of 27,548 ounces at an AISC of $1,830 per ounce sold Revenue of $94.5M from the sale of 28,265 ounces at an average realized price of $3,338 per ounce Adjusted EBITDA of $45.5M, Adjusted Earnings attributable to Orezone shareholders of $20.6M, and Adjusted Earnings per Share attributable to Orezone shareholders of $0.04 Liquidity of $103.9M at June 30, 2025 with cash of $72.6M and undrawn senior debt of $31.3M Stage 1 hard rock expansion reached 63% completion and remains on schedule for first gold in Q4-2025. Stage 1 is forecasted to increase overall gold production to 170,000-185,000 ounces in 20261. Click link here for August construction video Subsequent to quarter end: Completed A$75.0M initial public offering on the Australian Securities Exchange ('ASX') and commenced trading under the symbol 'ORE'. Proceeds will accelerate the stage 2 hard rock expansion Board approved construction decision for the stage 2 hard rock expansion. Stage 2 commissioning scheduled for Q4-2026, with overall gold production forecasted to increase to 220,000-250,000 ounces per annum2 Patrick Downey, President and CEO, commented 'Q2 marked another solid operating quarter at Bomboré, with all production metrics, including grade, recovery, and tonnes processed, inline with plan. This is a testament to the site operating team, who remain focused on operational excellence. During Q2, this included several stage 1 hard rock operational readiness initiatives, including 1) maintaining an elevated mining rate through the onset of the rainy season to advance a number of pits to the hard rock interface, and 2) processing a greater percentage of corresponding transitional material while achieving a mill throughput rate at 20% above nameplate. The higher realized AISC in Q2 was mainly attributable to external factors including higher royalties, lower grid power availability and unfavourable foreign exchange movements. The higher royalty costs were the result of a record realized gold price of $3,338/oz versus the budgeted $2,600/oz, along with a newly enacted royalty structure that added 1% to the royalty rates. The lower than expected grid power availability that led to more power generation onsite using higher cost diesel, was the result of a fire at a supply line substation, and higher than forecasted seasonal variability, which year over year has materially improved. A steady improvement in grid power has been seen in the past two months with utilization increasing from 50% in Q2, to 76% in July, and a return to >90% in August. The XOF strengthened against the USD by over 7% from Q1 to Q2 which negatively impacted reported costs as the majority of operating expenditures are in the local currency. These three external factors combined are estimated to have added $236 per ounce to the guided AISC per ounce sold in Q2. Through Q2, the Company made steady progress on its multiple growth initiatives. The construction of the stage 1 hard rock plant remains on schedule and on budget, with first gold on track for Q4-2025. This will mark an important milestone for the Company with overall gold production at Bomboré forecasted to increase to 170,000-185,000 ounces in 20263. On the stage 2 hard rock expansion, early progress was made advancing engineering, scheduling and initial procurement, with a Board approved construction decision made subsequent to quarter end. Executing on these growth initiatives over the next 16 months will significantly transform the Company by increasing overall production at Bomboré to 220,000-250,000 ounces per annum4. This production growth will be complemented by an ongoing focus on exploration, with the goal of increasing the current resource base to a targeted 7 to 10 million ounces longer term5. Exploration drilling through H1-2025 was successful on multiple fronts, further underscoring the significant exploration upside to the current stated 5.0 million ounce global resource base at Bomboré. Results included 1) extending the North Zone footwall mineralization up to 200m below the current reserve pits along 800m strike length, 2) extending mineralization of the P17S high-grade sub-zone a further 300m down plunge, and 3) identifying multiple broad near-surface strike extensions. Following several months of hard work, Orezone has commenced trading on the ASX under the ticker 'ORE'. The secondary listing on the ASX has broadened our investor base into the very active Australian mining market, enhancing the Company's capital markets profile and trading liquidity.' ________________________1 Refer to the Company's Prospectus dated July 11, 2025, a copy of which is available on the Company's website. The Company confirms it is not aware of any new information or data that materially affects the information included in the Prospectus and that all material assumptions and technical parameters underpinning the forecast gold production targets in the Prospectus continue to apply and have not materially changed.2 Refer to footnote 1.3 Refer to footnote 1.4 Refer to footnote 1.5 This statement of the Company's goal of increasing the current stated 5 million ounce global resource base to a targeted 7 to 10 million ounces longer term is an aspirational statement, and the Company does not yet have reasonable grounds to believe the statement can be achieved. Highlights for the Second Quarter and Significant Subsequent Events (All mine site figures on a 100% basis) Q2-2025 Q2-2024 H1-2025 H1-2024 Operating Performance Gold production oz 27,548 25,524 56,236 55,663 Gold sales oz 28,265 24,937 57,208 56,166 Average realized gold price $/oz 3,338 2,334 3,092 2,185 Cash costs per gold ounce sold1 $/oz 1,609 1,386 1,415 1,242 All-in sustaining costs1 ('AISC') per gold ounce sold $/oz 1,830 1,613 1,620 1,452 Financial Performance Revenue $000's 94,512 58,343 177,227 123,028 Earnings from mine operations $000's 39,951 23,167 78,514 50,049 Net earnings attributable to shareholders of Orezone $000's 15,906 8,939 31,885 20,636 Net earnings per common share attributable to shareholders of Orezone Basic $ 0.03 0.02 0.06 0.06 Diluted $ 0.03 0.02 0.06 0.05 EBITDA1 $000's 40,270 26,728 81,452 57,057 Adjusted EBITDA1 $000's 45,493 20,491 89,687 46,419 Adjusted earnings attributable to shareholders of Orezone1 $000's 20,607 3,326 39,297 11,062 Adjusted earnings per share attributable to shareholders of Orezone1 $ 0.04 0.01 0.08 0.03 Cash and Cash Flow Data Operating cash flow before changes in working capital $000's 27,023 15,331 67,009 36,671 Operating cash flow $000's 16,357 (51 ) 44,061 13,586 Free cash flow1 $000's (27,154 ) (16,951 ) (23,472 ) (14,938 ) Cash, end of period $000's 72,592 11,446 72,592 11,446 1 Cash costs, AISC, EBITDA, Adjusted EBITDA, Adjusted earnings, Adjusted earnings per share, and Free cash flow are non-IFRS measures. See 'Non-IFRS Measures' section below for additional information. SECOND QUARTER HIGHLIGHTS Strong Liquidity Maintained: Available liquidity stood at $103.9M at June 30, 2025 with $72.6M in cash and XOF 17.5 billion ($31.3M) undrawn on the Phase II term loan with Coris Bank International. The Company remains well-funded to execute on its 2025 and future growth plans. Robust EBITDA, Net Earnings, and Earnings Per Share: Reported Q2-2025 EBITDA of $40.3M, net earnings attributable to Orezone shareholders of $15.9M, and net earnings per share attributable to Orezone shareholders of $0.03 per share on a basic and diluted basis as earnings benefitted from the record rise in gold prices and unhedged gold sales in the current quarter. These earnings figures were 51%, 79%, and 50% higher, respectively, when compared against Q2-2024. Positive Operating Cash Flow Supporting Capital Investment: Reported Q2-2025 cash flow from operating activities of $27.0M after income tax payments of $14.9M but before changes in non-cash working capital. Non-cash working capital increased by $10.7M mainly from the build-up of VAT receivables and long-term ore stockpiles. Cash flow used in investing activities totalled $43.5M as progress and spending on the hard rock expansion and other growth projects accelerated. AISC Impacted by External Factors: AISC was elevated in Q2-2025 mainly due to higher royalties from a better realized gold price and new higher royalty rates (+$92/oz), low grid power availability due to a fire at a supply line substation and higher seasonal variability than forecasted (+$99/oz), and a stronger XOF currency impacting local costs (+$45/oz). Debt Reduction: Principal repayments totalling another XOF 3.0 billion ($5.2M) were made on the Company's senior debt in Q2-2025, bringing scheduled debt repayments to XOF 6.0 billion ($10.0M) in H1-2025. As of June 30, 2025, the principal on senior debt stood at XOF 36.5 billion ($65.3M). OPERATING HIGHLIGHTS Bomboré Mine, Burkina Faso (100% basis) Q2-2025 Q2-2024 H1-2025 H1-2024 Safety Lost-time injuries frequency rate Per 1M hours 0.55 0.00 0.31 0.00 Personnel-hours worked 000's hours 1,823 1,322 3,181 2,372 Mining Physicals Ore tonnes mined tonnes 2,059,136 1,966,547 4,173,679 4,369,080 Waste tonnes mined tonnes 3,948,902 3,451,757 7,967,084 6,574,856 Total tonnes mined tonnes 6,008,038 5,418,305 12,140,763 10,943,936 Strip ratio waste:ore 1.92 1.76 1.91 1.50 Processing Physicals Ore tonnes milled tonnes 1,565,022 1,428,396 3,076,325 2,784,015 Head grade milled Au g/t 0.62 0.64 0.65 0.71 Recovery rate % 87.8 86.8 87.8 88.0 Gold produced Au oz 27,548 25,524 56,236 55,663 Unit Cash Cost Mining cost per tonne $/tonne 3.27 3.29 3.04 3.38 Mining cost per ore tonne processed $/tonne 9.50 8.87 8.79 8.46 Processing cost $/tonne 9.65 9.19 8.74 9.21 Site general and admin ('G&A') cost $/tonne 4.36 3.96 4.08 3.87 Cash cost per ore tonne processed $/tonne 23.51 22.02 21.61 21.54 Cash Costs and AISC Details Mining cost (net of stockpile movements) $000's 14,869 12,672 27,045 23,539 Processing cost $000's 15,106 13,120 26,888 25,640 Site G&A cost $000's 6,824 5,654 12,542 10,788 Refining and transport cost $000's 113 136 279 253 Government royalty cost $000's 8,366 4,595 14,968 9,727 Gold inventory movements $000's 206 (1,625 ) (745 ) (209 ) Cash costs1 on a sales basis $000's 45,484 34,552 80,977 69,738 Sustaining capital $000's 4,284 3,281 7,483 7,299 Sustaining leases $000's 74 73 147 146 Corporate G&A $000's 1,880 2,319 4,062 4,388 All-In Sustaining Costs1 on a sales basis $000's 51,722 40,225 92,669 81,571 Gold sold Au oz 28,265 24,937 57,208 56,166 Cash costs per gold ounce sold1 $/oz 1,609 1,386 1,415 1,242 All-In Sustaining Costs per gold ounce sold1 $/oz 1,830 1,613 1,620 1,452 1 Non-IFRS measure. See 'Non-IFRS Measures' section below for additional details. BOMBORÉ PRODUCTION RESULTS Q2-2025 vs Q2-2024 Gold production in Q2-2025 was 27,548 oz, an increase of 8% from the 25,524 oz produced in Q2-2024. The higher gold production is attributable to a 10% increase in plant throughput and a 1% increase in recovery rates partially offset by a 3% decline in head grades. Plant throughput of 1.57M tonnes in Q2-2025 continues to operate ahead of nameplate by 20% and was 10% higher than Q2-2024 as plant operating hours in Q2-2024 were reduced by more frequent grid power interruptions and the longer length of time needed to transition power on and off of back-up diesel gensets during grid blackouts and restorations. Hourly plant throughput was successfully improved starting in July 2024 and maintained into 2025 by increasing the mill power draw and reducing residence time in the CIL circuit with only a minor loss in recovery. Transition time to switch between the grid and back-up gensets have also been lowered from improvements made to the site power infrastructure in Q1-2025. The better head grades in Q2-2024 were from the sequencing of higher-grade pits in earlier periods of the mine plan and the preferential stockpiling of lower-grade ore mined. BOMBORÉ OPERATING COSTS Q2-2025 vs Q2-2024 AISC per gold oz sold in Q2-2025 was $1,830, a 13% increase from $1,613 per oz sold in Q2-2024. The higher AISC is primarily attributable to: (a) greater per oz royalty costs ($296/oz vs $184/oz) from a 43% increase in the realized gold price and new higher royalty rates enacted into law in April 2025; (b) lower head grades; (c) a higher strip ratio; and (d) XOF currency appreciation against the USD (~5% higher) on costs set in the local currency. Power costs in both quarters suffered from high occurrences of power dips and blackouts to the national grid, resulting in more use of the back-up diesel gensets for power generation at the Bomboré mine. Grid supply is seasonally low in Q2, and similar to 2024, has significantly improved starting in Q3 with weekly grid utilization regularly exceeding 90%. For power consumed at the mine, the national grid supplied 50% in Q2-2025 and 34% in Q2-2024, leading to increased processing costs in these quarters from the use of higher-cost diesel for power generation. Cash cost per ore tonne processed in Q2-2025 was $23.51/tonne, an increase of 7% from $22.02/tonne in Q2-2024, driven by a stronger XOF currency impacting costs in all departments, a 9% increase in the strip ratio in mining, and higher unit consumption rates for power and lime in processing due to the changing composition of ore fed into the mill. BOMBORÉ HARD ROCK EXPANSION Hard Rock Expansion – Stage 1 Construction of the 2.5Mtpa stage 1 hard rock expansion remains on schedule and on budget, with first gold expected in Q4-2025. Progress and milestones achieved to the end of Q2-2025 include: Project completion reached 63% Engineering and drafting are complete Procurement is completed with all equipment and materials ordered. Focus is now on expediting critical path deliveries of electrical equipment and bulks to site. Final shipments of structural steel and tank platework, and other major mechanical equipment are either at site or in transit to site Concrete volume poured of 4,114 m3 (78% of estimated total) with foundations for SAG mill, water tanks, and pipe racks completed, and jaw crusher wing walls, conveyor footings, and other equipment foundations advancing All five CIL tanks are now erected to full height with hydrostatic testing underway Steel erection is progressing well Mill installation works commenced Operational readiness activities continue to progress with safety and training plans under preparation, and recruitment activities launched. Development of plant specific operating and maintenance procedures are underway All major site installation contracts (concrete, structural/mechanical/piping, electrical/instrumentation, and mill installation) were awarded to the same contractors that successfully delivered on the oxide construction. These contractors have now mobilized to site except for the electrical and instrumentation contractor whose team is scheduled to arrive in Q3-2025. As of June 30, 2025, the Company has incurred $57.0M in costs to-date against the project budget, of which $22.7M and $41.7M were incurred in Q2-2025 and H1-2025, respectively. Figure 1: Bomboré Processing Complex – Hard Rock Plant Layout (blue labels) Relative to Oxide Plant and Other Established Infrastructure (white labels)Figure 2: Stage 1 Hard Rock Expansion – Major Plant Component ConstructionHard Rock Expansion – Stage 2 On August 13, 2025, the Company's Board of Directors approved a final investment decision to proceed with stage 2 construction of the hard rock expansion. To the 2.5Mtpa stage 1 hard rock circuit, the stage 2 expansion to 5.5Mtpa comprises the addition of a ball mill, pebble crusher, thickener, oxygen plant, four additional CIL tanks, and a gold room upgrade. The latest capital cost estimate for the stage 2 hard rock expansion is $90M to $95M, with a construction timeline to first gold in Q4-2026 of 16 months. Once in commercial production, stage 2 is projected to increase overall gold production at Bomboré to 220,000-250,000 ounces per annum6. The Company intends to award engineering and procurement for the stage 2 expansion to Lycopodium. During Q2-2025, the Company contracted Lycopodium to perform front-end engineering and design, along with advancing procurement on long-lead equipment as part of stage 2 early works ahead of the approved final investment decision. As of June 30, 2025, the Company has incurred $0.4M in costs in Q2-2025 and for the project to-date. Figure 3: Schematic highlighting mill component additions for stage 2 hard rock expansion. Oxide plant and stage 1 hard rock circuit in grey.________________________6 Refer to footnote 1. CORPORATE AND SIGNIFICANT SUBSEQUENT EVENTS Corporate Bought Deal Equity Offering: In March 2025, the Company closed a bought deal offering including the over-allotment exercise by issuing 49,085,450 common shares at a price of C$0.82 per share for gross proceeds of C$40.3M ($28.0M) with net proceeds at C$37.6M ($26.1M) after commission and other transaction costs. Net proceeds from the offering will be used to fund construction costs for stage 2 of the hard rock expansion, exploration, working capital, and general corporate purposes. Private placement with Nioko Resources Corporation ('Nioko'): On April 2, 2025, the Company closed a non-brokered private placement with Nioko by issuing 10,719,659 common shares at a price of C$0.82 per share for gross proceeds of C$8.8M ($6.1M) in order to maintain its pro-rata share ownership in the Company. The net proceeds received from the share issuance was C$8.8M ($6.1M) after listing fees. Board of Director Changes: At the Company's AGM held on June 12, 2025, Mr. Julian Babarczy was elected as a new board member. Mr. Babarczy is an Australian resident with extensive knowledge of the Australian capital markets and deep relationships with many Australian institutional investment funds and brokerages. Mr. Babarczy will be an essential resource for the Company's local marketing efforts following the Company's recent listing on the ASX. Mr. Marco Locascio and Mr. Matthew Quinlan did not stand for re-election at the AGM. The Company is appreciative of the invaluable contributions and financial insights provided by Mr. Locascio and Mr. Quinlan during their respective tenures as directors. Subsequent Events Hard Rock Expansion – Stage 2 Construction Approval: The Company's Board of Directors approved a final investment decision to proceed with stage 2 construction of the hard rock expansion at its Bomboré mine. See Bomboré Hard Rock Expansion section for further details pertaining to the stage 2 hard rock expansion. ASX Public Offering and Listing: The Company was admitted to the official list of the ASX and commenced trading under the symbol 'ORE'. As part of the ASX listing, the Company completed an initial public offering of 65,789,474 CHESS Depository Interests ('CDIs') over fully paid common shares in the capital of the Company at an offer price of A$1.14 per CDI, raising gross proceeds of A$75.0 million. NON-IFRS MEASURES The Company has included certain terms or performance measures commonly used in the mining industry that is not defined under IFRS, including 'cash costs', 'AISC', 'EBITDA', 'adjusted EBITDA', 'adjusted earnings', 'adjusted earnings per share', and 'free cash flow'. Non-IFRS measures do not have any standardized meaning prescribed under IFRS, and therefore, they may not be comparable to similar measures presented by other companies. The Company uses such measures to provide additional information and they should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. For a complete description of how the Company calculates such measures and reconciliation of certain measures to IFRS terms, refer to 'Non-IFRS Measures' in the Management's Discussion and Analysis for the three months ended June 30, 2025 which is incorporated by reference herein. CONFERENCE CALL AND WEBCAST The condensed interim consolidated financial statements and Management's Discussion and Analysis are available at and on the Company's profile on SEDAR+ at Orezone will host a conference call and audio webcast to discuss its second quarter 2025 results on August 13, 2025: WebcastTiming: August 13, 2025, 2:00pm PT / 5:00pm ET / August 14, 2025, 7:00am AESTConference call webcast link: Conference CallToll-free in U.S. and Canada: 1-800-715-9871International callers: +646-307-1963 Event ID: 9884247 QUALIFIED PERSONS The scientific and technical information in this news release was reviewed and approved by Mr. Rob Henderson, P. Eng, Vice-President of Technical Services and Mr. Dale Tweed, P. Eng., Vice-President of Engineering, both of whom are Qualified Persons as defined under NI 43-101 Standards of Disclosure for Mineral Projects. ABOUT OREZONE GOLD CORPORATION Orezone Gold Corporation (TSX: ORE, ASX: ORE, OTCQX: ORZCF) is a West African gold producer engaged in mining, developing, and exploring its 90%-owned flagship Bomboré Gold Mine in Burkina Faso. Construction of the stage 1 hard rock expansion is well underway, with first gold expected in Q4-2025. Combined production from the oxide and stage 1 hard rock operations is forecasted to total between 170,000 and 185,000 ounces in 2026. The Company is also advancing the stage 2 hard rock expansion, which is forecasted to increase annual production to between 220,000 and 250,000 ounces. The technical report entitled Bomboré Phase II Expansion, Definitive Feasibility Study is available on SEDAR+ and the Company's website. Patrick DowneyPresident and Chief Executive Officer Kevin MacKenzieVice President, Corporate Development and Investor Relations Tel: 1 778 945 8977 info@ / For further information please contact Orezone at +1 (778) 945-8977 or visit the Company's website at The Toronto Stock Exchange neither approves nor disapproves the information contained in this news release. This announcement was authorised for release by the Company's Board of Directors. Cautionary Note Regarding Forward-Looking Statements This press release contains 'forward-looking statements' and 'forward-looking information', including statements and forecasts which include (without limitation) expectations regarding the financial position of the Company, production targets, the stage 1 and stage 2 hard rock expansions, the goal of defining a 7 to 10 million ounce resource base in the near future, future strategies, results and outlook of the Company and the opportunities available to the Company. Often, but not always, forward-looking information can be identified by the use of words such as plans', 'expects', 'is expected', 'is expecting', 'budget', 'outlook', 'scheduled', 'target', 'estimates', 'forecasts', 'intends', 'anticipates', or 'believes', or variations (including negative variations) of such words and phrases, or state that certain actions, events or results 'may', 'could', 'would', 'might', or 'will' be taken, occur or be achieved. Such information is based on assumptions and judgments of the Company regarding future events and results. Readers are cautioned that forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, targets, performance or achievements of the Company to be materially different from any future results, targets, performance or achievements expressed or implied by the forward-looking information. Forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the control of the Company, the Directors and management of the Company. Past performance is not a guide to future performance. Key risk factors associated with an investment in the Company are detailed in the Company's audited annual consolidated financial statements, annual MD&A and Annual Information Form for the year ended December 31, 2024 as well as Section 4 of the Company's prospectus dated July 11, 2025, copies of which can be found on SEDAR+ and the Company's website. These and other factors could cause actual results to differ materially from those expressed in forward-looking statements. Forward-looking information and statements (including the Company's belief that it has a reasonable basis to expect it will be able to fund the hard rock expansion at the Bomboré Mine) are, further to the above, based on the reasonable assumptions, estimates, analysis and opinions of the Company made in light of its perception of trends, current conditions and expected developments, as well as other factors that the Company believes to be relevant and reasonable in the circumstances at the date such statements are made, but which may prove to be incorrect. Although the Company believes that the assumptions and expectations reflected in such forward-looking statements and information are reasonable, readers are cautioned that this is not exhaustive of all factors which may impact on the forward-looking information. The Company does not undertake to update any forward-looking information or statements, except in accordance with applicable securities laws. Due to the risks, uncertainties and assumptions contained herein, investors should not place undue reliance on forward-looking information. Figures accompanying this announcement are available at: in to access your portfolio
Yahoo
5 hours ago
- Yahoo
VIQ Solutions Posts Fifth Straight Positive Adjusted EBITDA Quarter
MISSISSAUGA, Ontario, August 13, 2025--(BUSINESS WIRE)--VIQ Solutions Inc. ("VIQ" or "the Company") (TSX: VQS), a global leader in AI-powered digital documentation, today announced financial results for the three and six months ended June 30, 2025. The Company reported continued margin expansion, its fifth consecutive quarter of positive Adjusted EBITDA, and secured its largest SaaS deployment to date, reinforcing its leadership in secure, evidence-based transcription for regulated sectors. Second Quarter 2025 Financial Highlights Revenue: $10.4 million, decrease of 10%, from the same period in the prior year, reflecting the timing of customer volumes and market conditions. Gross Margin: 48%, up from 45.5% from the same period in the prior year, driven by automation and productivity gains. Adjusted EBITDA: $1 million, increase of $0.2 million or 24% from the same period in the prior year, marking the fifth consecutive quarter of positive results. Adjusted Operating Loss: $0.8 million, compared to $0.6 million from the same period in the prior year. First Half 2025 Financial Highlights Revenue: $20 million, decrease of 7%, from the same period in the prior year, reflecting the timing of customer volumes and market conditions. Gross Margin: Nearly 50%, up from 44.9% from the same period in the prior year, driven by automation and productivity gains. Adjusted EBITDA: $1.8 million, increase of $1.1 million or 164% from the same period in the prior year, reflecting sustained cost discipline and efficiency gains. Adjusted Operating Loss: $1.5 million, an improvement of $0.9 million. Strategic and Operational Highlights Landmark SaaS Court Deployment: In July 2025, VIQ secured its largest SaaS engagement to date, implementing NetScribe® across 9 judicial districts and 22 counties in the U.S. Midwest. This milestone accelerates VIQ's transition to a higher-margin, subscription-based revenue model. AI-Driven Workflow Automation: The deployment integrates NetScribe®, aiAssist™, Advanced Formatter, supporting internally produced transcription with scalability and optional add-ons including domain-specific language models, advanced post-processing rules, multilingual support, and automated summarization. First Half 2025 Organic Bookings Momentum: VIQ secured $1.9 million of new bookings during first half of 2025, supporting ongoing gross margin expansion and strengthening long-term free cash flow prospects. Management Commentary "In the first half of 2025, VIQ delivered 164% growth in Adjusted EBITDA, expanded gross margins to nearly 50%, and achieved our fifth consecutive quarter of positive EBITDA," said Alexie Edwards, CFO of VIQ Solutions. "While we reported a net loss, this includes approximately $2.0 million in non-cash expenses, such as depreciation, amortization, and stock-based compensation, with $1.1 million recorded in Q2. These charges impact earnings per share but do not affect our cash flow." "With our largest SaaS deployment now in motion, increased bookings, and a clear focus on strengthening the balance sheet and reducing debt, we are expanding our financial flexibility to reinvest in growth. Our AI-driven platform and automation strategy continue to fuel stronger margins and sustained EBITDA gains, laying the foundation for long-term growth and value creation." A copy of the Company's unaudited financial statements and accompanying MD&A for the three and six months ended June 30, 2025 (collectively, the "Financial Information") will be available under the Company's profile on SEDAR+ at Conference Call Details VIQ will host a conference call and webcast to discuss Financial Information on August 14, 2025, at 11:00 a.m. (Eastern time). The call will consist of updates by Alexie Edwards, VIQ's Chief Financial Officer followed by a question-and-answer period. Investors may access a live webcast of the call on the Company's website at or by dialing 1-888-440-4052 (North America toll-free) or +1-646-960-0827 (international) to be connected to the call by an operator using conference ID number 4983233. Participants should dial at least 10 minutes before the call starts. A replay of the webcast will be available on the Company's website through the same link approximately one hour after the conference call concludes. For more information about VIQ, please visit About VIQ Solutions VIQ Solutions is a global provider of secure, AI-driven, digital voice and video capture technology and transcription services. VIQ offers a seamless, comprehensive solution suite that delivers intelligent automation, enhanced with human review, to drive transformation in the way content is captured, secured, and repurposed into actionable information. The cyber-secure, AI technology and services platform are implemented in the most rigid security environments including criminal justice, legal, insurance, government, corporate finance, media, and transcription service provider markets, enabling them to improve the quality and accessibility of evidence, to easily identify predictive insights and to achieve digital transformation faster and at a lower cost. Forward-looking Statements Certain statements included in this press release constitute forward-looking statements or forward-looking information (collectively, "forward-looking statements") under applicable securities legislation. Such forward-looking statements or information are provided for the purpose of providing information about management's current expectations and plans relating to the future. Readers are cautioned that reliance on such information may not be appropriate for other purposes. Forward-looking statements typically contain statements with words such as "anticipate", "believe", "expect", "plan", "intend", "estimate", "propose", "project" or similar words, including negatives thereof, suggesting future outcomes or that certain events or conditions "may" or "will" occur. These statements are only predictions. Forward-looking statements in this press release include but are not limited to statements with respect to the Company's ability to accelerate automation, optimize costs, and improve scalability in the future, expected margin improvement, the Company's focus and its priorities, the filing of the Financial Information on SEDAR+ and the conference call to discuss the Company's financial results. Forward-looking statements are based on several factors and assumptions which have been used to develop such statements, but which may prove to be incorrect. Although VIQ believes that the expectations reflected in such forward-looking statements are reasonable, undue reliance should not be placed on forward-looking statements because VIQ can give no assurance that such expectations will prove to be correct. In addition to other factors and assumptions which may be identified in this press release, assumptions have been made regarding, among other things, recent initiatives, cost savings from workforce and product optimization, cost reductions from the Company's workflow solutions and that sales and prospects may increase revenue. Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions that have been used. Forward-looking statements are necessarily based on a number of opinions, assumptions and estimates that while considered reasonable by the Company as of the date of this press release, are subject to known and unknown risks, uncertainties, assumptions, and other factors that may cause the actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements, including but not limited to the factors described in greater detail in the "Risk Factors" section of the Company's annual information form and in the Company's other materials filed with the Canadian securities regulatory authorities. These factors are not intended to represent a complete list of the factors that could affect the Company; however, these factors should be considered carefully. Such estimates and assumptions may prove to be incorrect or overstated. The forward-looking statements contained in this press release are made as of the date of this press release and the Company expressly disclaims any obligations to update or alter such statements, or the factors or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. Non-IFRS Measures The Company prepares its financial statements in accordance with IFRS. Non-IFRS measures are provided by management to provide additional insight into our performance and financial condition. VIQ believes non-IFRS measures are an important part of the financial reporting process and are useful in communicating information that complements and supplements the consolidated financial statements. Adjusted EBITDA and adjusted operating loss are not measures recognized by IFRS and do not have a standardized meanings prescribed by IFRS. Therefore, Adjusted EBITDA and adjusted operating loss may not be comparable to similar measures presented by other issuers. Investors are cautioned that Adjusted EBITDA and adjusted operating loss should not be construed as alternatives to net income (loss) as determined in accordance with IFRS. For a reconciliation of net income (loss) to Adjusted EBITDA and adjusted operating loss please see the Company's MD&A for three and six months ended June 30, 2025. To evaluate the Company's operating performance as a complement to results provided in accordance with IFRS, the term "Adjusted EBITDA" refers to net income (loss) before adjusting earnings for stock-based compensation, depreciation, amortization, interest expense, accretion, and other financing expense, (gain) loss on revaluation of options, (gain) loss on revaluation of restricted share units, gain (loss) on revaluation of derivative warrant liability, restructuring costs, strategic review costs, loss on modification of debt, impairment of property and equipment, impairment of goodwill and intangibles, other expense (income), foreign exchange (gain) loss, current and deferred income tax expense. We believe that the items excluded from Adjusted EBITDA are not connected to and do not represent the operating performance of the Company. We believe that Adjusted EBITDA is useful supplemental information as it provides an indication of the results generated by the Company's main business activities prior to taking into consideration how those activities are financed and taxed as well as expenses related to stock-based compensation, depreciation, amortization, impairment of goodwill and intangibles, loss on modification or extinguishment of debt, other expense (income), and foreign exchange (gain) loss. Accordingly, we believe that this measure may also be useful to investors in enhancing their understanding of the Company's operating performance. The term "adjusted operating loss" refers to net income (loss) excluding the impact of strategic review costs. Management believes it is appropriate to adjust for this item because strategic review costs do not relate to operating activities of the Company and is useful supplemental information as it provides an indication of the results generated by the Company's main business activities. The presentation of this measure enables investors and analysts to better understand the underlying performance of our business activities. We calculate "bookings" for a given period as the estimated contract value (for services tied to volume) of our recurring client contracts entered into during the period from (i) new clients and (ii) net upgrades by existing clients within the same workload, plus the actual (not annualized) estimated value of professional services consulting, advisory or project-based orders received, software licenses, subscriptions, SaaS, and hardware during the period. Trademarks This press release includes trademarks, such as "NetScribe", which are protected under applicable intellectual property laws and are the property of VIQ. Solely for convenience, our trademarks referred to in this press release may appear without the ® or TM symbol, but such references are not intended to indicate, in any way, that we will not assert our rights to these trademarks, trade names, and services marks to the fullest extent under applicable law. Trademarks that may be used in this press release, other than those that belong to VIQ, are the property of their respective owners. VIQ Solutions Inc. Interim Condensed Consolidated Statements of Financial Position (Expressed in US dollars, unaudited) June 30, 2025 December 31, 2024 Assets Current assets Cash $ 1,117,164 $ 1,573,341 Trade and other receivables, net of allowance for doubtful accounts 4,422,766 3,768,699 Inventories 25,914 23,508 Prepaid expenses and other deposits 890,576 1,183,496 Non-current assets 6,456,420 6,549,044 Restricted cash 177,560 169,097 Property and equipment, net 541,883 654,223 Right-of-use assets, net 349,610 153,794 Intangible assets 5,183,967 5,661,614 Goodwill 11,929,976 11,628,213 Total assets $ 24,639,416 $ 24,815,985 Liabilities Current liabilities Trade and other payables and accrued liabilities $ 6,846,250 $ 5,673,346 Income taxes payable 61,890 29,765 Share-based payment liability 643 19,366 Derivative warrant liability 38,019 35,238 Current portion of long-term debt 17,099,730 15,988,401 Current portion of lease obligations 206,345 204,802 Contract liabilities 1,475,909 1,635,041 Non-current liabilities 25,728,786 23,585,959 Long-term lease obligations 167,884 – Other long-term liabilities 924,371 949,622 Total liabilities 26,821,041 24,535,581 Shareholders' equity Capital stock 77,665,053 77,593,993 Contributed surplus 9,364,786 9,145,162 Accumulated other comprehensive loss (1,341,494 ) (1,356,521 ) Deficit (87,869,970 ) (85,102,230 ) Total shareholders' equity (2,181,625 ) 280,404 Total liabilities and shareholders' equity $ 24,639,416 $ 24,815,985 VIQ Solutions Inc. Interim Condensed Consolidated Statements of Loss and Comprehensive Loss (Expressed in US dollars, unaudited) Three months ended June 30, Six months ended June 30, 2025 2024 2025 2024 Revenue $ 10,445,488 $ 11,575,614 $ 20,024,513 $ 21,497,287 Cost of sales 5,436,220 6,312,797 10,040,105 11,841,912 Gross profit 5,009,268 5,262,817 9,984,408 9,655,375 Expenses Selling and administrative expenses 3,866,110 4,328,687 7,676,752 8,639,461 Research and development expenses 179,957 155,416 320,476 320,526 Stock-based compensation 292,682 111,283 291,865 139,816 Gain on revaluation of RSUs (21,482 ) (18,534 ) (19,553 ) (47,311 ) Loss (gain) on revaluation of the derivative Warrant liability 8,260 7,479 1,238 (49,686 ) Foreign exchange gain (354,295 ) (590,719 ) (438,327 ) (487,886 ) Depreciation 175,864 194,237 340,547 389,221 Amortization 658,581 813,889 1,366,158 1,620,346 Interest expense 439,704 405,965 928,326 794,889 Accretion and other financing costs 456,029 425,216 875,059 752,094 Restructuring costs (recovery) 37,349 5,874 36,066 (3,820 ) Strategic review costs 119,124 – 1,294,726 – Other income (1,911 ) (10,208 ) (8,118 ) (21,413 ) Total expenses 5,855,972 5,828,585 12,665,215 12,046,237 Current income tax expense 52,654 6,063 86,933 21,107 Income tax expense 52,654 6,063 86,933 21,107 Net loss for the period $ (899,358 ) $ (571,831 ) $ (2,767,740 ) $ (2,411,969 ) Exchange (loss) gain on translation of foreign operations 16,115 (483,076 ) 15,027 (795,107 ) Comprehensive loss for the period $ (883,243 ) $ (1,054,907 ) $ (2,752,713 ) $ (3,207,076 ) Net loss per share Basic (0.02 ) (0.01 ) (0.05 ) (0.05 ) Diluted (0.02 ) (0.01 ) (0.05 ) (0.05 ) Weighted average number of common shares outstanding – basic 52,563,142 51,348,578 52,449,214 48,065,488 Weighted average number of common shares outstanding – diluted 52,563,142 51,348,578 52,449,214 48,065,488 The following is a reconciliation of Net Loss to Adjusted EBITDA, the most directly comparable IFRS measure for the three and six months ended June 30, 2025, and 2024: Three months endedJune 30 Six monthsJune 30 (Unaudited) 2025 2024 2025 2024 Net Loss (899,358) (571,831) (2,767,740) (2,411,969) Add: Depreciation 175,864 194,237 340,547 389,221 Amortization 658,581 813,889 1,366,158 1,620,346 Interest expense 439,704 405,965 928,326 794,889 Current income tax (recovery) expense 52,654 6,063 86,933 21,107 EBITDA 427,445 848,323 (45,776) 413,594 Accretion and other financing costs 456,029 425,216 875,059 752,094 Gain on revaluation of RSUs (21,482) (18,534) (19,553) (47,311) Loss (Gain) on revaluation of the derivative warrant liability 8,260 7,479 1,238 (49,686) Restructuring costs 37,349 5,874 36,066 (3,820) Strategic Review Costs 119,123 - 1,294,726 - Other income (1,911) (10,208) (159,978) (21,413) Stock-based compensation 292,682 111,283 291,865 139,816 Foreign exchange gain (354,295) (590,719) (438,327) (487,886) Adjusted EBITDA 963,201 778,714 1,835,320 695,388 The following is a reconciliation of Net Loss to Adjusted operating loss, the most directly comparable IFRS measure for the three and six months ended June 30, 2025, and 2024: Three months endedJune 30 Six monthsJune 30 (Unaudited) 2025 2024 2025 2024 Net Loss (899,358) (571,831) (2,767,740) (2,411,969) Add: Strategic Review Costs 119,123 - 1,294,726 - Adjusted operating loss (780,235) (571,831) (1,473,014) (2,411,969) View source version on Contacts Media Contact: Jacob Manning VIQ SolutionsEmail: marketing@ Sign in to access your portfolio
Yahoo
5 hours ago
- Yahoo
Olympia Financial Group Inc. Announces Second Quarter 2025 Results
Calgary, Alberta--(Newsfile Corp. - August 13, 2025) - Olympia Financial Group Inc. (TSX: OLY) ("Olympia") today announces its operating and financial results for the three months ended June 30, 2025. Results from operations for the three months ended June 30, 2025, include the following (compared to operations for the three months ended June 30, 2024): Total net earnings and comprehensive income decreased 8% to $5.42 million from $5.89 million. Total revenue decreased 3% to $25.56 million from $26.22 million. Service revenue increased 6% to $12.95 million from $12.16 million mainly due to an increase in monthly and transaction fees related to account growth within the IAS division. Trust, interest, and other income decreased 10% to $12.61 million from $14.06 million mainly due to a decrease in interest rates on trust fund placements made over the previous 12 months. Total expenses remained consistent at $18.42 million. Basic and diluted earnings per share attributable to shareholders of Olympia decreased 8% to $2.25 per share from $2.45 per share. The unaudited condensed interim financial statements and notes, as well as management's discussion and analysis, are now available on SEDAR ( Both historical and current information on Olympia's stock, financials, press releases, governance, and more can now be found at About Olympia Financial Group Inc. Olympia conducts most of its operations through its subsidiary Olympia Trust Company, a non-deposit taking trust company. Olympia Trust Company is licensed to conduct trust activities in Alberta, British Columbia, Saskatchewan, Manitoba, Quebec, Newfoundland and Labrador, Prince Edward Island, New Brunswick, and Nova Scotia. Olympia Trust Company administers self-directed registered plan accounts, corporate trust, and transfer agency services. Olympia also provides currency exchange and global payment services through its subsidiary Olympia Currency and Global Payments Inc., and offers private health services plans and information technology services to exempt market dealers, registrants, and issuers through its subsidiary Olympia Benefits Inc. Olympia's common shares are listed on the Toronto Stock Exchange under the symbol "OLY". For further information, please contact: Olympia Financial Group Skauge, President and Chief Executive OfficerJennifer Urscheler, Chief Financial Officer Phone: (403) 261-0900Fax: (403) 265-1455 Statements Regarding Forward Looking Information Certain portions of this press release as well as other public statements by Olympia contain "forward-looking information" within the meaning of applicable Canadian securities legislation, which is also referred to as "forward-looking statements", which may not be based on historical fact. Wherever possible, words such as "will", "plans," "expects," "targets," "continue", "estimates," "scheduled," "anticipates," "believes," "intends," "may," and similar expressions or statements that certain actions, events or results "may," "could," "would," "might" or "will" be taken, occur or be achieved, have been used to identify forward-looking information. Forward-looking statements contained in Olympia's public disclosure include, without limitation, Olympia's earnings expectations, fee income, expense levels, general economic, political and market factors in North America and internationally, interest and foreign exchange rates, global equity and capital markets, business competition, technological change, changes in government regulations, unexpected judicial or regulatory proceedings, catastrophic events, and Olympia's ability to complete strategic transactions and other factors. In addition, this news release contains forward-looking statements relating to the monthly dividend payments to holders of Olympia common shares. All material assumptions used in making forward-looking statements are based on management's knowledge of current business conditions and expectations of future business conditions and trends, including their knowledge of the current interest rate and liquidity conditions affecting Olympia and the Canadian economy. Certain material factors or assumptions are applied by Olympia in making forward-looking statements, including without limitation, factors and assumptions regarding interest and foreign exchange rates, availability of key personnel, the effect of competition, government regulation of its business, computer failure or security breaches, future capital requirements, acceptance of its products in the marketplace, its operating cost structure, the current tax regime and the ability of Olympia to obtain necessary third-party and governmental approvals, as applicable. To view the source version of this press release, please visit Sign in to access your portfolio