No need to worry, Sabah Energy Commission assures genset owners over inspection rules
Many owners have raised concerns about being required to schedule regular visits by certified professionals, known as Competent Persons. But ECoS Chief Executive Officer Datuk Abdul Nasser Abdul Wahid clarified that the requirement does not apply to everyone in the same way.
He explained that installations using low-voltage systems and switchgear rated below 100 amperes, whether in homes, shops, or factories, do not need regular inspections by a Competent Person.
Even for residential and commercial buildings using switchgear rated above 100 amperes but below 300 amperes, ECoS has decided that regular visits will not be mandatory.
As for industrial premises, including petrol stations, the inspection schedule has been relaxed, from once a month to once every three months.
Abdul Nasser said that for large-scale commercial and industrial premises receiving supply at 11,000 volts, the frequency of visits may be reduced from twice a month to once a month.
For installations receiving supply from above 11,000 volts up to 132,000 volts, the frequency may be reduced from four times a month to twice a month,' he said.
'These adjustments reflect the level of risk involved — the higher the voltage, the greater the potential danger not just to owners and workers, but also to the public,' said Abdul Nasser.
He said these changes are allowed under Regulation 72 of the Electricity Supply Regulations 2024, but stressed that owners must apply for reduced inspections. Each application will be assessed by ECoS officers to ensure safety standards are still met.
Despite the relaxation of rules, Nasser reminded all genset owners that they remain fully responsible for the safety of their installations.
For more information or assistance, owners can contact any ECoS office or visit the 'Talk2ECoS' portal at www.ecos.gov.my.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Daily Express
9 hours ago
- Daily Express
ECoS aims for full rural electrification in Sabah
Published on: Wednesday, August 20, 2025 Published on: Wed, Aug 20, 2025 Text Size: Musa (3rd from right) receiving a souvenir from Abdul Nasser during the courtesy call at Istana Seri Kinabalu. Kota Kinabalu: The Energy Commission of Sabah (ECoS) is committed to ensuring that every rural village in the state has access to electricity by 2030, in line with the Sabah Energy Roadmap Master Plan and data from the 2022 census. ECoS Chief Executive Officer Datuk Ir Abdul Nasser Abdul Wahid said the State Government has agreed to establish a special committee to coordinate the rural electrification initiative. Advertisement 'This will take time, but we are confident that the 100 per cent target can be achieved,' he said during a courtesy call on Head of State Tun Musa Aman at Istana Seri Kinabalu on Monday. The visit was held to brief Tun Musa on the current status of electricity and onshore gas supply in Sabah, as well as to share updates on ongoing plans and achievements through various energy initiatives. Abdul Nasser noted that Sabah's electricity supply performance has shown positive progress, especially in reducing the Consumer Average Interruption Duration Index (Citi), which measures the duration of power supply disruptions. 'In 2023, the average outage duration was around 500 minutes. This decreased to 400 minutes in 2024, and we expect it to drop below 300 minutes this year. By 2030, our goal is to reach just 100 minutes through the addition of new power generators and continuous upgrades to the transmission and distribution systems,' he said. He also emphasised the importance of human capital development in the energy sector. In collaboration with the Papar Institute of Technical and Vocational Training (ILTP), ECoS is working to improve training modules in electricity and gas to produce more skilled local manpower for the industry. * Follow us on our official WhatsApp channel and Telegram for breaking news alerts and key updates! * Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available. Stay up-to-date by following Daily Express's Telegram channel. Daily Express Malaysia


Borneo Post
2 days ago
- Borneo Post
Sabah aims for full rural electrification by 2030
Tun Musa (third from right) receiving a souvenir from ECoS presented by Abdul Nasser. KOTA KINABALU (Aug 18): The Energy Commission of Sabah (ECoS) is focusing on ensuring all rural villages in Sabah receive electricity supply by 2030. Its Chief Executive Officer, Datuk Ir. Abdul Nasser Abdul Wahid, said the target aligns with the Sabah Energy Roadmap Master Plan based on the 2022 census. 'The state government has also agreed to establish a special committee to coordinate efforts to supply electricity to all rural villages in Sabah. 'This will take time, but we are confident the 100% target can be achieved,' he said after paying a courtesy visit to the Governor, Tun Musa Aman, today. The visit to Istana Seri Kinabalu aimed to brief Tun Musa on the current status of electricity and onshore gas supply in Sabah, including ongoing plans and achievements through various initiatives. Abdul Nasser also reported that Sabah's electricity supply continues to show progressive improvement with a reduction in the Customer Interruption Time Index (CITI). 'In 2023, outages averaged 500 minutes, decreasing to 400 minutes in 2024. This year, we expect less than 300 minutes. 'Our target is to reach 100 minutes by 2030 through the addition of new generators and the upgrading of transmission and distribution systems,' he explained. He added that human capital development in the energy sector is also being prioritized through collaboration with the Papar Institute of Technical and Trade Training (ILTP) to upgrade electrical and gas training modules, thereby producing more local skilled workers.


Borneo Post
02-08-2025
- Borneo Post
Sabah Oil & Gas Terminal integrated maintenance postponed
KOTA KINABALU (Aug 2): The temporary shutdown for scheduled maintenance at the Sabah Oil & Gas Terminal (SOGT) has been postponed to a date that will be determined later. According to the Chief Executive Officer of ECoS, Datuk Ir. Abdul Nasser Abdul Wahid, 'the postponement at SOGT was made after taking into account the current situation of the Sabah Grid and the additional time needed to complete the testing of Independent Power. Producer (IPP) power generation units in Kimanis using an alternative diesel fuel, in addition to ongoing repair works at other power plants owned by Sabah Electricity and IPPs.' He added that the decision was made after assessing the risk of power supply disruptions to the Sabah Grid based on current conditions, compared to the impact of delaying the maintenance work at SOGT. 'This aims to ensure that consumers in Sabah and Labuan are not affected by power supply rationing,' he said in a statement on Saturday. The integrated maintenance work at SOGT was initially scheduled from August 1 to 7 before it was postponed to August 5 to 11 and then to a date that will be determined later.