Dasu project cost surges to Rs1.7tr

Dasu project cost surges to Rs1.7tr

Express Tribune12-04-2025

Listen to article
The government on Friday recommended the revised Dasu hydropower project for approval at a record-breaking cost of Rs1.7 trillion or $6.2 billion, making it the most expensive hydropower project in the nation's history and raising eyebrows over the "astronomical increase" of 240% in the cost.
With a massive jump of Rs1.3 trillion against the original price tag, the per-unit cost of the supposedly cheapest water-based power generation scheme now comes to Rs8.79. This makes it the most expensive hydro venture in the nation's history and requires further billions of dollars of fresh foreign borrowings to complete it.
The Central Development Working Party (CDWP), under the chairmanship of Minister for Planning Ahsan Iqbal, took up the "revised Dasu Hydropower Project (Stage-I)" worth Rs1.74 trillion and referred it to ECNEC "subject to WAPDA rationalising the costs and answering the queries," according to an announcement by the Ministry of Planning.
The minister "expressed serious concern on massive cost escalation from the original Rs479 billion to almost Rs1.73 trillion due to delays and mismanagement in the project," but still chose to send the scheme to the Executive Committee of the National Economic Council (ECNEC) for final approval with a few observations.
The planning ministry stated that Iqbal "directed third-party validation of the astronomical increase in the revised PC-I." The project had originally been approved at a cost of just Rs486 billion in 2014, with a per-megawatt cost of Rs236 million.
After the escalation, the per-megawatt cost comes to Rs804 million, compared with the Tarbela Fifth Hydropower Project's Rs148 million.
The PML-N government conditionally cleared the scheme for the final nod of the ECNEC, which will be chaired by Deputy Prime Minister Ishaq Dar.
The $6.2 billion cost of the project is now almost equal to the $6.7 billion cost of building a railway track from Karachi to Peshawar under the China-Pakistan Economic Corridor (CPEC).
Iqbal attributed the "substantial cost escalation to Rs1.73 trillion to mismanagement and delays and lack of progress during the previous government."
The minister "took notice of the fact that despite ECNEC directions to appoint an independent full-time project director for each project over Rs3 billion, WAPDA didn't appoint an independent project director for the Dasu project."
"It was also pointed out that there was no professional chief finance officer for the project," and yet the minister agreed to send the project to ECNEC. "The minister asked how WAPDA is running a project of this magnitude without a qualified and competent CFO," stated the planning ministry, but he still agreed to clear it.
"The minister was angry to learn that WAPDA had awarded a contract for the construction of a 66-kilometer Karakoram Highway section in foreign currency."
On his inquiry about why the road construction project was done in foreign currency, WAPDA couldn't give any satisfactory reply. He yet conditionally cleared the project subject to the condition that WAPDA will submit replies to his questions.
Iqbal called giving road project contracts in foreign currency "criminal negligence." It was also pointed out that WAPDA had made design changes and incurred expenditure without approval from CDWP and ECNEC. The minister sought an explanation from WAPDA, it added.
Iqbal emphasised the strategic importance of the Dasu hydropower project for Pakistan's water and food security.
The CDWP was told that in view of the expected increase in the cost of Stage-I of 2,160 MW, the government now needs more foreign and local loans. The forum was informed that WAPDA was in negotiations with the World Bank for a whopping $1 billion new loan. The $1 billion loan will be a mix of expensive and concessional loans. The World Bank has already given a $517 million loan for the project.
The government will also get a $400 million foreign commercial loan by using World Bank guarantees. It will also search for Rs350 billion in domestic commercial loans.
WAPDA will inject Rs289 billion as equity. Out of it, Rs191 billion will be used to finance the project cost and Rs98 billion, already paid by WAPDA against interest during construction. The rate of return against equity is taken as 10%.
The dam height will be 242 meters with roller-compacted concrete type, which has been recommended by the Panel of Experts, as well as the consultants. The powerhouse is located in an underground cavern on the left bank of the Indus River. The main development objective of the project is to improve the management and investment planning of water resources in the Indus River Basin. From 2013-14 onward, PC-I expenditures started, and up to 2023-24, a sum of Rs317 billion has been incurred.
The World Bank has been financing the construction of Stage-I, which also includes land acquisition, resettlement, and pre-construction activities.
Initially, Stage-I, having a capacity of 2,160 MW, was expected to come online in five years, but due to land acquisition issues and an increase in the scope of work, the project was not completed on the due date and had to be extended up to 2029.
The second revised PC-I has been prepared for updating the construction of Stage-I (2,160 MW) of Dasu HPP, including the cost of land acquisition, resettlement, and pre-construction activities such as the construction of the right bank access road from Komila to the Dasu Dam site, relocation of KKH, construction of the project O&M staff colony, and construction of a 132 kV transmission line from Dubair Khwar HPP to Dasu.
So far, the work on the main hydraulic structure, spillway, low-level outlets, river diversions, and hydraulic structures has been completed by 23.6%, and the estimated date of completion is 2028. The work on the underground power complex, tunnels, and hydraulic steel structures is only 15% complete.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

National Open Data Portal launched
National Open Data Portal launched

Business Recorder

time6 hours ago

  • Business Recorder

National Open Data Portal launched

LAHORE: The National Center in Big Data and Cloud Computing (NCBC) at LUMS, in collaboration with the Ministry of Planning, Development & Special Initiatives (MoPD&SI), hosted the Pakistan Open Data Conference 2025 in Islamabad. The event marked a pivotal moment in the country's digital transformation journey with the official launch of the National Open Data Portal (NODP). This first-of-its-kind portal, developed by NCBC at LUMS, will serve as Pakistan's central platform for public access to government datasets across vital sectors such as health, education, economy, environment, infrastructure, and demographics. The portal is designed to promote transparency, empower researchers and civil society, and enable data-driven policymaking and innovation. Federal Minister for Planning, Development and Special Initiatives, Ahsan Iqbal Chaudhary inaugurated the portal and commended the achievement of the NCBC and the LUMS team in making this national platform a reality. He noted that it was a great privilege to be part of the journey that led to the establishment of NCBC, which he said has played a pivotal role in building local capacity in Artificial Intelligence and Machine Learning. He stated that 'Pakistan's development narrative will now be written in code and understood through data,' adding that leveraging digital tools is no longer optional but an urgent national priority. He emphasized that the launch of the National Open Data Portal marks another major milestone, one that will empower policymakers, researchers, and the public by providing access to valuable, structured datasets across key sectors supporting better decision-making, innovation, and transparency for a stronger, more data-informed Pakistan. Ahsan Iqbal concluded with a powerful message: 'In a rapidly digitizing world, it is no longer enough to make declarations – we must deliver results. Let us unite – government, academia, industry, and our youth – to build a data-smart, cloud-enabled, globally competitive Pakistan. The launch of the National Open Data Portal is not the conclusion – it is the beginning of a new era'. Dr Naveed Arshad, Director of NCBC at LUMS, welcomed participants by highlighting the strategic importance of open data in enabling a digitally empowered Pakistan. He remarked that 'data is the new oil but unlike oil, the more we share it, the more value we unlock.' He added that the launch of the Open Data Portal is a critical investment in transparency, knowledge-sharing, and innovation for Pakistan's digital future. Reflecting on the establishment of NCBC at LUMS in 2018, made possible through the generous support of the Government of Pakistan, he shared that working alongside 12 partner institutions across the country has been a journey of collective growth and technical excellence. He acknowledged the dedication of all contributors to the effort, emphasizing that their commitment deserves the highest appreciation and recognition. The conference brought together senior stakeholders from government, academia, development partners, and the tech industry for strategic discussions on the role of open data in advancing inclusive development. Copyright Business Recorder, 2025

Iqbal highlights development priorities
Iqbal highlights development priorities

Express Tribune

time7 hours ago

  • Express Tribune

Iqbal highlights development priorities

Planning Minister Ahsan Iqbal on Thursday acknowledged that tight fiscal space, driven by structural constraints, has reduced its ability to fund development projects under the Public Sector Development Programme (PSDP). At a news conference, he said the development budget has declined from 2.6% of GDP in 2017-18 to just 0.8% — a trend described as a serious structural concern for national development. He said the government aims to meet development and other expenditures through domestic resources, however, achieving this goal requires raising Pakistan's tax-to-GDP ratio to at least 16% — a level already maintained by regional peers.

Cases against 5 MPs of PTI: ECP to conduct hearing on 24th
Cases against 5 MPs of PTI: ECP to conduct hearing on 24th

Business Recorder

time7 hours ago

  • Business Recorder

Cases against 5 MPs of PTI: ECP to conduct hearing on 24th

ISLAMABAD: The electoral entity has fixed cases on 24th June against five legislators, who belong to Pakistan Tehreek-e-Insaf (PTI), on the petitions mainly moved by Pakistan Muslim League Nawaz (PML-N) members, seeking to unseat the said lawmakers. These legislators are: Leader of the Opposition in the National Assembly Omar Ayub Khan, his two cousins — Akbar Ayub Khan and Arshad Ayub Khan — both of whom are Members of Khyber Pakhtunkhwa Assembly — Malik Adeel Iqbal, another Member Provincial Assembly (MPA) in KP legislature, and PTI Lahore chapter President Sheikh Imtiaz Mehmood, who is Member of Punjab Assembly. All the five legislators had won their respective seats in last year's general elections. Of them, Iqbal had to contest the general election as an independent candidate, and Mahmood had to contest the general poll on Sunni Ittehad Council (SIC) ticket — against the backdrop of the PTI election symbol controversy. The reference against Iqbal seeks his disqualification from Punjab Assembly allegedly over having Canadian nationality, an allegation Mahmood denies. The cases against all other four legislators seek re-polling in the respective constituencies, alleging foul play in the general elections. Jamshaid Dasti is another Member National Assembly (MNA) who belongs to PTI against whom cases are pending over allegedly having fake educational credentials, and alleged discrepancies in his wealth statement filed with the Election Commission of Pakistan (ECP). Dasti also had to contest the last year's general election on SIC ticket in the contest of PTI election symbol issue. Apart from that, the hearing of reference against the NA opposition leader, seeking his disqualification from NA over alleged financial corruption and alleged misrepresentation of related facts in the electoral documents, is scheduled in the ECP on July 01. Speaking to the media after the disqualification reference hearing held on 4 June, the NA opposition leader said, Speaker NA Ayaz Sadiq sent reference to the ECP against him out of politically motivated reasons. 'The speaker sent this reference without even using his brain,' Khan deplored. The Article 63(2) of the Constitution of Pakistan provides that if any question arises whether a legislator has become disqualified from being a member, the speaker or chairman (of the legislature concerned), shall, unless they decide that no such question has arisen, refer the question to ECP within 30 days, and if the speaker/chairman fails to do so within the aforesaid period, the question shall be deemed to have been referred to the ECP. The Article 63(3) provides that the ECP shall decide the question within 90 days from its receipt, and if it is of the opinion that the member has become disqualified, the member shall cease to be a lawmaker and their seat shall become vacant. Copyright Business Recorder, 2025

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store