
Airport to miss May 15 deadline
Noida:
Noida International Airport
will miss its third deadline, which was set for May 15 by chief minister
Yogi Adityanath
, with work on the terminal building unlikely to be completed by then.
While there is no word yet on the new date, sources indicate the launch was unlikely within the next two months.
The airport, as of now, is running one year behind its schedule. Its original deadline was Sept 29, 2024, which was revised to April 17, 2025. But with the work on the terminal building not complete, the date for
domestic flight operation
was revised to May 15 and international flight to June 25. UP has imposed a fine of Rs 10 lakh per day on concessionaire YIAPL from Jan 1 for the delay in completing the project.
On Tuesday, chief secretary Manoj Kumar Singh conducted a site inspection of the airport site in Jewar and met officials from Yamuna International Airport Private Limited (YIAPL), Tata Projects Limited and Noida International Airport Limited (NIA). Singh will now hold a stakeholder meeting to set new completion timelines and submit a full report within 15 days.
During the meeting, the CM emphasised on the need for all stakeholders to act with urgency. Senior officials were directed to conduct regular review meetings and to hold direct discussions with the chairman of Tata Sons to ensure accountability at the highest level.
While the current construction status has not been officially disclosed, the overall physical progress of the project till March 10 was 80%. The runway and associated airside infrastructure, which were 90% complete, were to be ready by April. The passenger terminal building was only 80% complete, with steel roofing and internal finishing still underway. The water and sewage treatment plants, both 40% complete, were significantly behind schedule.
Though the ATC building was to be completed by March 31, the commissioning of CNS/ATM systems by the Airports Authority of India (AAI) was projected only by April 30.
Officials earlier told the CM that non-issuance of the aerodrome licence from the Directorate General of Civil Aviation (DGCA), along with pending construction, were major roadblocks to
commence flight operation by April 30.
At a DGCA review meeting on March 5, AAI submitted that only limited ATC functionality could be achieved for its inspection after April 30. The Bureau of Civil Aviation Security (BCAS), meanwhile, informed that after reviewing key safety documents, including the bomb threat contingency plan, anti-hijack contingency plan and airport security programme, it had noted some observations that required compliance. BCAS stated it would need 45 days after receiving the responses to issue the security clearance, and in the case of a partial terminal opening, a structural stability certificate would be mandatory.
During the DGCA meeting, YIAPL was also asked to submit detailed operational scenarios given the incomplete status of the terminal and cargo apron. Based on the discussions, the DGCA advised YIAPL to complete all pending works listed in the draft Aeronautical Information Publication (AIP) Supplement and ensure full readiness by April 15. The DGCA also recommended three options for operationalising the airport: initiating cargo operations only by May 15, allowing partial passenger operations using a section of the terminal, or achieving full Phase 1 readiness.
Sources indicated that once the airport begins operations, it is likely to follow the DGCA's recommended phased approach, starting with domestic and cargo flights and gradually expanding to include international services.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Indian Express
26 minutes ago
- Indian Express
Copper wire, tube imports hit multi-year highs in FY25; cathode shipments fell 34% year-on-year
India's copper cathode imports declined 34 per cent year-on-year in 2024-25 (FY25), largely due to a three-month supply disruption triggered by a quality control order (QCO), even as imports of downstream products such as wire, tubes, and sheets surged to multi-year highs. While copper cathode imports dropped sharply, imports of key downstream copper products climbed in FY25 — wire rose 17 per cent y-o-y, tubes and pipes 30 per cent, and plates, sheets, and strips 49 per cent. In India, copper is classified as a critical mineral given limited domestic production and high demand in conventional and emerging technologies—from air conditioners and transformers to electric vehicle (EV) batteries and wind turbines. It is also seen as a bellwether of economic activity owing to its extensive application across sectors. From an average of 27,000 tonnes each month between April and November 2024, copper cathode imports fell to around 2,000 tonnes per month between December and February, after the QCO went into effect from December 1. Then, in March 2025, imports recovered slightly to 16,000 tonnes, official trade data showed. India relies on imports for about 30 per cent of its copper cathode demand, a key raw material for wire, tubes, and sheets. The Adani Group's new Gujarat smelter, scheduled to reach peak capacity this financial year, is expected to make the country self-sufficient for the near-term. Cathode imports recover as three-month QCO disruption eases In FY25, India imported 2.39 lakh tonnes (Rs 19,134 crore) of copper cathode, 34 per cent less than 3.63 lakh tonnes (Rs 24,552 crore) in the previous financial year. Amid sharp drop in imports between December to February, two metals trade associations filed a petition against the Union Mines Ministry, which issued the QCO, alleging that the quality norms have caused 'acute shortages' in supply. The petition added that domestic producers could 'charge exorbitant and irrational rates' as imports decline. The case will be heard by the Bombay High Court on June 27. However, a rebound in copper cathode imports in March to around 16,200 tonnes indicates that supply constraints are easing. Official sources told The Indian Express that no shortage was recorded on account of the QCO, and that the Mines Ministry has filed its response to the petition in court. The steep drop in imports stemmed from compliance issues among exporters, especially Japanese suppliers who dominate India's copper cathode imports. The QCO mandates that both domestic producers and foreign suppliers obtain the Bureau of Indian Standards (BIS) certification to sell copper cathode in India. Most Japanese producers received certification only after the QCO took effect, and some continued to face minor challenges in ensuring compliance post-certification. 'Roughly 50 per cent of copper cathode demand is in the winding wires segment, which has faced no issue in availability post-December. There has been no impact on downstream sectors,' sources said. Delays in BIS certification were caused by Japanese smelters taking over six months to apply, despite ample time and extensions, they added. Copper wire, tube, sheet imports surge in FY25 Downstream copper imports climbed to multi-year highs in FY25, defying the slump in cathode shipments. Copper wire imports—primarily from the UAE—rose 17 per cent from 1.31 lakh tonnes in FY24 to 1.54 lakh tonnes in FY25, with their value jumping 29 per cent to Rs 12,653 crore. Widely used in electrical wiring, motors, and transformers for its high conductivity and durability, copper wire imports in FY25 hit a five-year high, though still below the over 2 lakh tonnes imported in FY19 and FY20. Similarly, copper tubes and pipes imports—primarily from Vietnam—jumped 30 per cent to 1.14 lakh tonnes, the highest since FY18, valued at Rs 10,157 crore. Copper tubes and pipes are used in air conditioning, refrigeration, and heat exchangers. Copper plates, sheets and strips imports—used in electrical busbars and transformers—surged 49 per cent to around 30,000 tonnes, valued at Rs 2,725 crore. Imports of copper products rose despite the Department for Promotion of Industry and Internal Trade (DPIIT) enforcing a QCO on these items from October 19, 2024, initially for large and medium enterprises. Growth persisted due to potential stocking-up before enforcement, longer timelines for small (January 2025) and micro (April 2025) units, exemptions for certain tubes and export-use products, and timely grant of BIS certification to some foreign manufacturers. Domestic cathode output rises, new smelters coming online Domestic copper cathode production rose 12.6 per cent to 5.73 lakh tonnes in FY25, driven primarily by Hindalco Industries Ltd, which holds a 70 per cent market share and has a capacity of 5 lakh tonnes. Production last year surpassed the previous peak of 5.55 lakh tonnes recorded in FY23. Vedanta's Sterlite Copper, with a smaller capacity of 2.16 lakh tonnes, contributed 26 per cent of cathode in FY25. Notably, India remained self-sufficient in copper cathode until 2018, when Vedanta's Tuticorin plant was shut down over environmental violations. Adani's Kutch Copper Ltd produced 22,000 tonnes (4 per cent share) in its first year, with a smelter capacity matching Hindalco's at 5 lakh tonnes. Production is expected to ramp up to full capacity by October, with sources stating, 'Once the Adani plant is fully operational, India's entire cathode demand will be met internally.' Additionally, the JSW Group plans to establish a 5 lakh-tonne copper smelter in Odisha by 2028-29. With India's per capita copper consumption still at 0.6 kg—well below the global average of 3 kg—demand is set to surge. To meet this, India's smelting capacity must expand as global supplies tighten. Product Quantity (in lakh tonnes) Growth (in %) 2024-25 value (in Rs crore) 2023-24 2024-25 Copper cathode 3.63 2.39 -34 19,134 Copper wire 1.31 1.54 17 12,653 Copper tubes and pipes 0.88 1.14 30 10,157 Source: Department of Commerce Trade Data Aggam Walia is a Correspondent at The Indian Express, reporting on power, renewables, and mining. His work unpacks intricate ties between corporations, government, and policy, often relying on documents sourced via the RTI Act. Off the beat, he enjoys running through Delhi's parks and forests, walking to places, and cooking pasta. ... Read More


India Today
36 minutes ago
- India Today
Must discontinue Rs 500 notes: Chandrababu Naidu's mantra to end corruption
Andhra Pradesh Chief Minister N Chandrababu Naidu said that he believes that big currency notes should be discontinued to eradicate an exclusive interview with India Today TV's Consulting Editor Rajdeep Sardesai, Naidu said that "all big currencies should be abolished."According to Naidu, even Rs 500 notes should be discontinued. "Only currency notes under Rs 100 and Rs 200 should be there. Not even Rs 500 notes should be continued," Naidu big currencies should be abolished. Only then can we eradicate corruption," he November 2016, the Indian government, led by PM Modi, banned old Rs 500 and Rs 1000 notes. The demonitisation aimed at fighting prevalent black money and corruption. Must Watch


Hindustan Times
an hour ago
- Hindustan Times
Launch crackdown on shell, fake firms: U.P. CM to officials
LUCKNOW Uttar Pradesh chief minister Yogi Adityanath on Sunday directed officials to launch a stringent crackdown on shell companies and fraudulently registered firms, warning that any misuse of facilities meant for genuine traders was 'unforgivable'. Chairing a high-level review meeting of the state tax department here, he said tax evasion was a national crime that directly hindered development plans and welfare schemes. Yogi emphasised transparency, technological integration and strict enforcement to strengthen revenue systems. 'GST is a consumer-based tax system, and densely populated regions must reflect proportionate revenue. Underperformance in such areas is unacceptable,' the CM said. He instructed officials to prepare a special report on zones lagging behind headquarters-level collection benchmarks and submit it to the government for further action. Asserting that fraudulent registrations compromise the rights of honest taxpayers, the CM ordered that all newly registered firms undergo on-site verification. He said that any suspicious firms under the state GST regime should be thoroughly investigated with registration cancellations and FIRs in confirmed cases. Yogi also called for coordination with the Centre for cancellation of fake firms registered under the central GST. Officials informed the CM that GST and VAT collections for April and May had reached ₹18,161.59 crore—just over 10% of the ₹1,75,725 crore annual target for FY 2025–26. While he appreciated progress, the CM pushed for accelerated efforts to meet the full-year target. Yogi lauded 14 zones, including both Lucknow zones, Ayodhya, Bareilly, Agra, Ghaziabad, Gautam Buddh Nagar, Meerut, Jhansi and Saharanpur, for achieving 60% or more of their targets. However, he expressed dissatisfaction with low-performing zones like Varanasi-I, Prayagraj, Kanpur-II, Etawah, Aligarh, and Moradabad, where collections were under 50%, and ordered an immediate review. The CM also instructed additional, joint and deputy commissioners to directly interact with traders in these underperforming regions to promote compliance and strengthen trust in the tax system. 'Revenue is not just a number—it is the foundation of development,' the CM said, urging officials to carry out their duties with both accountability and sensitivity.