Fund reallocation for timely completion sought: World Bank backs govt, Wapda on T5HP extension

Fund reallocation for timely completion sought: World Bank backs govt, Wapda on T5HP extension

ISLAMABAD: The World Bank has reaffirmed its full financial support to the Government of Pakistan and WAPDA for the completion of the Tarbela Hydropower Project Extension-5 (T5HP), citing the need for fund reallocation to ensure timely completion.
In a letter addressed to Secretary Economic Affairs, Dr. Kazim Niaz, World Bank senior official Gailius J. Draugelis commended the hospitality extended by WAPDA and its project teams during the recent visit of the Bank's Executive Directors to the historic Tarbela Dam, the Tarbela Fourth Extension Hydropower Project (T4HP), and T5HP.
Tarbela Dam, the world's largest earth-fill dam, remains a key infrastructure landmark. The T4HP has added 1,410 megawatts (MW) to Pakistan's power grid since its commissioning in 2018, generating over 28,000 GWh of clean electricity and saving the country approximately $3.5 billion in foreign exchange. Additionally, the project has enhanced the long-term sustainability of the dam by protecting critical tunnels from sedimentation for the next 50 years.
World Bank team visits Tarbela 5th extension hydropower project
The Bank expressed satisfaction with the progress of the hydropower component being implemented by WAPDA. It noted that both the Tarbela 5 Project Implementation Consultants (T5PIC) and the contractors—Power Construction Corporation of China (PCCCL) for civil works, and Harbin Electric International/Harbin Electric Company (HEVHEC) for electromechanical (E&M) works—have been performing well.
PCCCL has nearly completed the vertical shaft of the raised intake during this low-flow season and has opened the portal inside Tunnel 5, marking a critical milestone. The next phase involves connecting this portal with the vertical shaft through a connection tunnel. While overall progress on the powerhouse is satisfactory, the World Bank has asked WAPDA to closely monitor construction of the erection/loading bay, which is crucial for the upcoming E&M installations.
The Bank urged WAPDA and T5PIC to ensure that rehabilitation work on the bulkhead and service gates of Tunnel 5 begins no later than August 2025. According to the revised contract schedule, generation units in T5HP are expected to be commissioned by the end of 2026. The Bank emphasized that timely rehabilitation of the service gate is essential for smooth commissioning.
Electromechanical works are also progressing steadily. Installation activities will accelerate once the erection/loading bay is completed.
The Bank has asked WAPDA and T5PIC to (i) monitor the timely delivery of E&M equipment to ensure the majority is on-site by end-2025; and (ii) direct the contractor to finalize the schedule for completing the works at the T4 switchyard, including shifting transmission lines that affect construction of the T5 Transmission Line (T5TL) towers.
The World Bank acknowledged improvements in project oversight, noting that the Project Manager has significantly enhanced construction sequencing and physical progress through timely technical decisions. However, it also advised WAPDA to manage the T5PIC consultancy contract efficiently to ensure sufficient budget for continued supervision by key experts for the duration of the project.
The Bank highlighted the need to reallocate approximately $50 million from the E&M component to the civil works component under both the IBRD and AIIB loans, despite the project having an undisbursed balance of around $299 million. This reallocation is critical to prevent financing constraints in FY2026.
The World Bank reiterated its commitment to supporting WAPDA and the government in completing T5HP. It acknowledged the expected financing gap due to unforeseen geological conditions, gate rehabilitation costs, and price escalations.
Regarding the T5 Transmission Line (T5TL), which connects the T5HP switchyard to the Islamabad West Substation (IWS) and T1–T4 switchyard, the Bank noted that the contract—awarded to Netracon Technologies (Pvt.) Ltd.—is under implementation. The contractor has completed 148 tower foundations and erected 129 towers, and has pledged to deliver all remaining equipment by July 2025.
The Bank urged NTDC, T5PIC, and the contractor to finalize the remaining line route, tower quantities, and foundation designs, particularly near Gawari Sand Quarry and close to the IWS. It also asked NTDC to ensure immediate commencement of conductor stringing and full compliance with the Resettlement Action Plan as foundation and erection works progress.
The Bank emphasized its intent to support Pakistan's long-term transmission expansion through a proposed multi-phase program to boost energy security. With IWS set to receive 1,530 MW from T5HP and 2,160 MW from Dasu Hydropower Stage-I in the coming years, the Bank has advised NTDC to plan the power evacuation accordingly, including evaluating the expansion of the 765kV transmission system to Lahore, Faisalabad, and other major load centres.
The sources said, the issue of reallocation of funds will also be discussed at a meeting between the World Bank and Government's line Ministries on Friday (today).
Copyright Business Recorder, 2025
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Indian cities need $2.4 trillion for climate infrastructure by 2050, World Bank says
Indian cities need $2.4 trillion for climate infrastructure by 2050, World Bank says

Business Recorder

time21 hours ago

  • Business Recorder

Indian cities need $2.4 trillion for climate infrastructure by 2050, World Bank says

NEW DELHI: India needs to invest more than $2.4 trillion by 2050 to build climate-resilient urban infrastructure, as its fast-expanding cities face growing challenges from extreme weather events linked to climate change, the World Bank said on Tuesday. The number of Indians living in cities is projected to nearly double to 951 million by 2050 from 480 million in 2020. But erratic rainfall, heatwaves, and rising sea levels are leaving urban areas in the world's most populous nation increasingly vulnerable, the bank said in a report. Without large-scale investments in housing, transport, water, and waste management systems, India will face escalating costs from weather-related damage, said the report entitled 'Towards Resilient and Prosperous Cities in India'. 'Cities need to become more resilient if people living in those cities are going to be safe,' Auguste Tano Kouame, theWorld Bank's country director for India, said at the launch of the report, which was prepared in collaboration with India's urban development ministry. Urban flooding already causes an estimated $4 billion in annual losses in India, the report found. That figure is projected to rise to $5 billion by 2030 and as much as $30 billion by 2070 without remedial action. India to issue climate risk disclosure rules for banks in the next few months, sources say The report's estimates based on conservative urban population growth put India's investment needs at $2.4 trillion by 2050 and $10.9 trillion by 2070, with those projections increasing to $2.8 trillion and $13.4 trillion respectively if the population is moderately urbanised. 'Timely actions can avert billions of annual damages and losses in flooding and extreme heat while investing in resilient and efficient municipal infrastructure and services,' the report said. India currently spends about 0.7% of its gross domestic product on urban infrastructure, well below global benchmarks, and must significantly scale up public and private financing, the World Bank report said. Federal, state and municipal governments must coordinate to improve project financing and provide climate-linked fiscal transfers. And India must increase partnerships with the private sector in areas including energy-efficient water supply, sanitation, solid waste management, and green buildings, it said. Private finance currently accounts for just 5% of urban infrastructure investment, the report said.

Pakistan's parched future: bonds to bridge the water funding chasm
Pakistan's parched future: bonds to bridge the water funding chasm

Business Recorder

timea day ago

  • Business Recorder

Pakistan's parched future: bonds to bridge the water funding chasm

As the monsoons arrive, once again, Pakistan is facing a water crisis, shifting from drought-like scenarios to the threat of a flood. The seasonal threat is no longer creeping but ferocious. As seasonal relief in monsoon showers may seem to provide, the bitter truth remains the same: our water security is falling, drop after drop, each passing year. Where once favoured with powerful rivers and glacial flows, present-day Pakistan is a water-scarce nation. Water availability on a head-per-capita basis has crashed down to 800–1,017 cubic meters from 5,260 in 1951. By 2035, we could dip below 500–660 cubic meters, a threshold of pure scarcity, while UNDP predicts extreme scarcity below 500 cubic meters in 2025. This is no future prospect; it is present in the dried-out canals in Punjab, Sindh's saline groundwater, drop in water tables in Balochistan, and failing supply lines in main cities like Karachi and Lahore. But behind the green disaster is the less spoken but no less lethal, twin disaster: the disparity between what we need to pay for water security and what we pay. The cost of inaction Pakistan's water economy is bleeding. Analyst estimates and official sources put inefficiencies, climate-related disasters, and old infrastructure at Rs3-4 trillion every year, about 3–4 percent of GDP. The losses occur due to floods, droughts, inefficient irrigation, and crumbling infrastructure. Agriculture, which accounts for more than 90 percent of usable water, loses on conveyance estimated at between 40–60 percent, endangering both productivity and rural livelihoods. Consider, for example, a rural Punjabi smallholder, Abdul Rehman. During the lean season, his wheat crop shriveled for lack of water as irrigation canals dried up, prompting him to sell livestock to make ends meet. Just as in lower Sindh, Ghulam Mustafa encountered an almost identical ordeal in May-June this year; he was waiting for water to begin kharif planting amidst water scarcity. The Indus reduced significantly by the time it flowed to his distributary because of downstream restrains added to existing upstream problems, slowing down and dwindling the stream. By the time water flowed back, as well, it was in vain, the sowing period was gone and his debts increased. Such incidents are not unique. Along the coasts in Sindh, advancing seawater engulfs arable lands as flows of freshwater fail to trickle down to the delta, making previously fertile patches near Thatta and Sujawal desolate areas. Across central and southern Punjab, numerous Rabi growers watched their wheat crop drought for insufficient final irrigations in February just months before harvesting, owing to paucity of water. Across cities such as Karachi, Lahore, Multan, and Quetta, damaged water infrastructure compelled families to rely on costly and sometimes hazardous tanker supplies. The World Bank warned that unabated disruptions would shave an estimated 6 percent of the GDP until mid-decade, long-term estimates could be 10 percent until 2050, or even 18-20 percent because of broader climate damage. The flood damage in 2022 alone was estimated at Rs3.2 trillion, sweeping away homes, crops, and livelihoods. Yet investment hasn't caught up. Why the gap persists The 2018 National Water Policy (NWP) had set a humble target: 10 percent of the Public Sector Development Programme (PSDP) should be for water in 2019, increasing to 20 percent in 2030. We still aren't achieving even the baseline. Present federal PSDP allocations are around 9.5 percent, national water expenditures, across federal and provincial governments, are a mere Rs380–400 billion in FY2025–26, less than 0.3 percent of GDP. Although mega-projects such as Mohmand Dam (Rs35.7 billion) and Diamer-Bhasha (Rs25 billion) are separately funded, the aggregate amount remains inadequate. Provincial budgets are no different. Punjab allocated Rs38 billion for irrigation, Sindh Rs31 billion, KP Rs25.1 billion, and Balochistan Rs32 billion (inclusive of foreign-aided schemes). The figures are humble for a sector for which provinces are the sole operator for canal operations, water distribution, and urban supply. Much of the gap lies in the larger fiscal constraint in Pakistan: debt servicing accounts for more than 20 percent of the federal budget. With IMF austerity, restricted fiscal space, and increasing rivalry from defense, subsidies, and social protection, long-gestation infrastructure initiatives end up on the casualty list. The federal PSDP for water for the next financial year is down by more than 25 percent to Rs185 billion in FY2024–25. Dams receive Rs63.3 billion, canals Rs39.3 billion—the figures 10–15 percent below previous years in real terms. This reduction threatens to trap us in a vicious cycle of postponed upkeep and exposure. Enter: Pakistan Water Bonds In this dismal fiscal context, one idea offers a way out: Water Bonds. These are structured financial instruments that raise dedicated capital for water-related infrastructure and services, independent of the donor cycle or the vagaries of annual PSDP allocations. They are not untested. In 2021, WAPDA raised USD500 million through a Green Eurobond, oversubscribed six times. More recently, the Parwaaz Green Action Bond raised Rs1 billion with a strong AA–rating, while the federal government's Green Sukuk in May 2025 brought in Rs32 billion, testifying to strong investor appetite. Pakistan's Islamic finance market, which is estimated to hold Rs7 trillion in deposits (close to 20 percent of the banking network), is waiting for innovation. The Water Bonds, in the name of green sukuks, can exploit this resource pool and provide 10–12 percent yields while conforming to ethical investment paradigms. They can be traded on home exchanges and can appeal to pension funds, insurance, and even microfinance institutions. The diaspora dividend Arguably, the most promising and emotionally resonant source of capital lies in the Pakistani diaspora. Remittances totaled USD35 billion in FY2025, and the Roshan Digital Account (RDA) mobilized over USD10 billion in just a few years. Overseas Pakistanis have shown that they are willing to invest if credible, transparent, and purpose-driven instruments exist. Green Diaspora Water Sukuk issued in dollars, pounds, or euros would potentially raise USD250–500 million if only 2–3 percent of RDA investors buy in. Such bonds could fund filtration plants, desalination facilities, rainwater harvesting, and pipeline improvements in the very towns where their loved ones live. Picture a Pakistani doctor in the United States funding a desalination plant back in his hometown in Sindh—it would not only provide him 6–8 percent returns but ensure that future generations also drink clean water. With sovereign backing, ESG reporting, and zakat-associated functionalities, such bonds could blend moral responsibility with financial sense. These diaspora flows could unlock matching contributions from development institutions such as the World Bank, the Islamic Development Bank, or the IFC, much like ADB's recentUSD500 million commitment for water resilience. Making it work: a phased roadmap But it won't happen without a phased, strategic roadmap. A Rs100 billion pilot bond in 2025 would aim for low-hanging fruit: wastewater treatment (national efficiency <1 percent) and flood irrigation and unlined channels (up to 60 percent loss of applied water). In 2026–27, scaling could be Rs 560 billion for storage, urban networks, and flood control. By 2030, an additional Rs400–580 billion could be spent on precision agriculture, desalination, and AI-based metering. These initiatives would need to be aligned with the existing water-sector project in the PSDP, worth Rs424 billion but stalled because not adequately funded. Transparency, not just tranches Naturally, finance alone is not a panacea. Diaspora and private investors need reassurance. Transparency must be ingrained through blockchain-powered audit trails, third-party audits, and exchange listing on the Pakistan Stock Exchange. Volumetric water pricing against cross-subsidies, sovereign guarantees, and municipal-level credit enhancements will be imperative. The Council of Common Interests must be empowered to offer interprovincial oversight and break political impasses. Although Pakistan's credit rating is a concern, Fitch's upgrade in the near term and IMF criteria hold promise. The OECD's Asia Capital Markets Report 2025 points to unprecedented growth in sustainable bonds but cites challenges in new markets such as Pakistan, such as regulatory barriers and investor awareness, underlining the imperative for sound frameworks. A bond for our future Our water shortage is reality. But so is our capacity for innovation. We have capital. We have policy frameworks. What we lack is urgency and vision. Water Bonds provide something beyond dollars. They provide a trustworthy, long-term financing tool to pay for the singular most important determinant of our survival: water. Let's not wait for the next flood, the next drought to teach us lessons we know all too well. The moment to act is today. Let's construct our water future, bond for bond, drop for drop. Copyright Business Recorder, 2025

World Bank urges Pakistan to expedite $55mn power efficiency project
World Bank urges Pakistan to expedite $55mn power efficiency project

Business Recorder

time2 days ago

  • Business Recorder

World Bank urges Pakistan to expedite $55mn power efficiency project

ISLAMABAD: The World Bank has urged Pakistan's Power Division and three major Distribution Companies (Discos) to fast-track implementation of the Additional Financing (AF) for the Electricity Distribution Efficiency Improvement Project (EDEIP), warning that continued delays could hamper the timely and effective use of the $55 million credit facility. In a letter addressed to Secretary Economic Affairs Dr. Kazim Niaz, the World Bank's new Country Director for Pakistan, Bolormaa Amgaabazar, noted a significant uptick in disbursements and commitments as of June 30, 2025—with disbursements rising to $18.09 million (9.3%) from 3.6% in November 2024, and commitments to $18.28 million (20.7%) from 9.0%. Still, the Bank flagged that targets for the quarter were not fully met due to rebidding of key contracts, procurement strategy revisions, and delays in grievance resolution. Wolrd Bank approves $55m in additional financing to Discos Despite these hurdles, the Bank remains optimistic. 'The project is now on track to meet its development goals by closure,' the letter stated, projecting end-FY26 disbursement and commitment levels at 30% and 95%, respectively. The World Bank lauded the Economic Affairs Division and Power Division for securing the AF package but emphasized that further momentum depends on meeting several immediate conditions—including finalizing the Financing Agreement and triggering its effectiveness within the 90-day window post-signature. The three Discos—Hyderabad Electric Supply Company (HESCO), Multan Electric Power Company (MEPCO), and Peshawar Electric Supply Company (PESCO)—have been told to promptly roll out activities under the new funding. During the Bank's May 2025 Appraisal Mission, all stakeholders agreed on a roadmap to eliminate project bottlenecks and enhance implementation speed. The World Bank stressed the importance of updating the Project Enhancement Action Plan (PEAP) by July 21, 2025, to reflect on-the-ground realities and lessons learned. Similarly, the Project Procurement Strategy for Development (PPSD) must be revised in line with the Bank's 2025 Procurement Regulations to address persistent contract delays. Key improvements must also be made in procurement quality, bid evaluation speed, complaint management, and oversight of contract execution. All high-value contracts must incorporate rated criteria and early market engagement to ensure transparency and efficiency. Revised procurement plans and bid documents are due to the Bank by July 31, 2025. On the Environmental and Social (E&S) front, the Bank flagged slow progress in preparing key documents like Environmental and Social Impact Assessments (ESIAs) and Resettlement Action Plans (RAPs). These are to be submitted by the end of July. The Bank warned that continued inaction could stall broader project progress. While the capacity of Project Implementation Units (PIUs) has improved—with support from the Project Implementation and Management Support Consultant (PIMSC)—gaps remain. The Bank highlighted the need for greater stability in project teams, urging against frequent changes in PIMSC personnel. DISCOs have been instructed to submit a detailed FY26 work plan for consultant engagement by July 31 and to fill all key PIU vacancies with qualified personnel by August 31. 'With focused effort and leadership, the project can still meet its targets and deliver long-term impact on Pakistan's power distribution performance,' the Country Director noted, reiterating the Bank's commitment to the country's reform agenda. Copyright Business Recorder, 2025

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store