Public Works Minister: George building collapse could have been prevented

Public Works Minister: George building collapse could have been prevented

IOL News2 days ago
Minister Dean Macpherson asserts that the 2024 George building collapse, which resulted in 34 fatalities, was preventable, citing systemic failures in planning and oversight
Image: Ayanda Ndamane
Minister of Public Works and Infrastructure Dean Macpherson believes that the 2024 George building collapse that claimed 34 lives could have been prevented.
The findings of a probe into the collapse showed that there were systemic failures, failures of planning, oversight, enforcement, and culture.
"At every problem, there was a chance to turn back, but because of weak regulatory environment, there was either no incentive or requirement to do so. And this is what makes me so angry when I view this tragedy from today's perspective, it was entirely preventable. However, we cannot undo what has happened," Macpherson said.
He said the full Engineering Council of South Africa (ECSA) investigation report has been completed and it will be published in the Government Gazette in due course. Meanwhile, an appeal window to these findings is currently underway, which expires on August 3, 2025.
"This report must form part of the police investigation as we must establish criminal negligence for what happened. If criminal wrongdoing is established, those responsible must be prosecuted without delay. We must ensure that people are held accountable for 34 souls losing their lives. No contractor, engineer, or official should be beyond the reach of the law," Macpherson said.
The Council for the Built Environment (CBE) will establish a reporting protocol that mandates the registration of any structural system failure.
"A hotline will be launched to allow workers, built environment practitioners and professionals, or members of the public to anonymously raise safety concerns. These reports will trigger automatic inspections and, where necessary, emergency site shutdowns," the minister said.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
Ad loading
#georgebuildingcollapse Media Briefing || Following a meeting with the families of those affected by the George building collapse,Minister of Public Works and Infrastructure,@DeanMacpherson , convened a media briefing to present the findings of the official investigative report… pic.twitter.com/MT6sbzfImx — Department Of Public Works and Infrastructure (@DepartmentPWI) July 19, 2025
Phase-based reform implementation Phase One from 2025 to 2026: Immediate interventions, including new regulations, mandatory standards and emergency protocols.
Phase Two from 2026 to 2028: Implementation of long-term reform, including legislative amendments and competency-based registration systems.
Phase Three from 2028 onwards: Institutional consolidation and relocation of custodianship of building regulations functions and standards to the Department of Public Works & Infrastructure.
"We are exploring options with the Department of Social Development and NGOs to provide relief or support to the families most affected, including those who have lost primary breadwinners," Macpherson said.
IOL
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Cyril Ramaphosa faces pressure to appoint US ambassador as tariffs loom
Cyril Ramaphosa faces pressure to appoint US ambassador as tariffs loom

IOL News

time2 hours ago

  • IOL News

Cyril Ramaphosa faces pressure to appoint US ambassador as tariffs loom

President Cyril Ramaphosa has been urged to appoint a US ambassador 'urgently' amidst impending tariffs. . Image: Supplied While the Presidency announced the appointment of Ambassador Vivianne Fock Tave as the new Seychelles Ambassador to the United Nations in New York on Monday, partners in the Government of National Unity (GNU) are intensifying calls for President Cyril Ramaphosa to appoint an ambassador to the United States as a matter of urgency. This comes days before the implementation of 30% tariffs on South African products exported to the US, imposed by President Donald Trump's administration. South Africa has been without an ambassador to the US since March when Ebrahim Rasool was expelled over comments deemed an attack on the Trump administration. In response, Ramaphosa appointed Mcebisi Jonas as a special envoy. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading However, the DA revealed that the US government denied Jonas a diplomatic visa in May and informed the Presidency that he would not be recognised as South Africa's official interlocutor. Jonas and Rasool are both seen as Trump's adversaries after they criticised him on two different occasions. In mid-March 2025, the Trump administration expelled Rasool as South Africa's ambassador to the US, following his critical comments about the US government during a webinar. Rasool had characterised the "Make America Great Again" movement as partly a reaction to "a supremacist instinct" and anticipated demographic changes in the US, specifically the projected decline of the white population to minority status. US Secretary of State Marco Rubio publicly denounced Rasool as a "race-baiting politician who hates America" and declared him persona non grata. In 2020, Jonas referred to Trump as "a racist, homophobic, and narcissistic right-winger", which resurfaced following his appointment as Special Envoy to the US. This exclusion of the two officials coincided with escalating tensions between the US and South Africa, fuelled by the US disapproval of South Africa's legal proceedings against Israel at the International Court of Justice and the US freezing aid to South Africa. GOOD Party secretary-general Brett Herron emphasised the need for Ramaphosa to take the nation into his confidence and update citizens on the Washington strategy. "Ramaphosa must update the nation on Washington strategy. President Cyril Ramaphosa owes the nation an update on progress... with the nation's diplomatic relationship with the US," Herron said. Another GNU partner, the IFP, during a media briefing on Monday, also urged Ramaphosa to appoint an ambassador as a priority. IFP national spokesperson Mkhuleko Hlengwa said the party is expecting the president to appoint the ambassador as a matter of urgency, given the diplomatic fallout between the two countries. He further stated that urgency was also necessary because South Africa will hand over the G20 Presidency to the US. Department of International Relations and Cooperation (DIRCO) spokesperson, Chrispin Phiri, referred questions to the Presidency. However, Presidency spokesperson Vincent Magwenya did not respond to questions on what the status of appointing an ambassador was. Last week, the Presidency and the DA were engaged in a war of words after the DA revealed that despite being aware of the US rejection of Jonas's credentials, the Presidency continued to present him as the special envoy to North America. "The United States of America denied Mcebisi Jonas a diplomatic visa in May this year. The US government has formally rejected Jonas's credentials...," the DA initially stated. In response, the Presidency warns against treating DA disinformation on international relations as official government policy. "Special Envoys do not present credentials, and Mr Jonas's role, while supportive of DTIC (Department of Trade, Industry and Competition) and DIRCO in trade negotiations and diplomatic relations, does not supersede them. He has been assisting in developing trade proposals and resetting diplomatic ties. "President Ramaphosa has not urgently required Mr Jonas to visit the US due to ongoing processes and recent contact with President Trump. The Presidency is concerned about the DA's persistent campaign against South Africa's national interest, originating from their ideological visit to the US earlier this year. The DA is attempting to use a foreign state to change national policies and is exploiting critical engagements to protest President Ramaphosa's removal of Mr Andrew Whitfield,' Magwenya said. He further said the DA's insults against other nations and international organisations harm South Africa's international relations and could negatively impact businesses and livelihoods dependent on global trade. The impending 30% tariffs on South African exports to the US, expected to take effect next month, pose significant challenges to South Africa's economy. Additionally, South Africa is on the brink of losing its African Growth and Opportunity Act (AGOA) status when it expires this year. AGOA enables economic growth and development in sub-Saharan Africa by providing eligible countries with duty-free access to the US market for thousands of products.

Serious safety violations flagged days before tragedy struck in George building collapse
Serious safety violations flagged days before tragedy struck in George building collapse

IOL News

time13 hours ago

  • IOL News

Serious safety violations flagged days before tragedy struck in George building collapse

The rubble of the collapsed multi-storey construction site at 75 Victoria Street in George. The building collapse claimed the lives of 34 workers and left dozens injured. Image: Ayanda Ndamane/ Independent Newspapers TWO days before the deadly George building collapse which claimed the lives of 34 people, a contractor observed unusual building movements and vibrations on the roof slab. Public Works and Infrastructure minister, Dean Macpherson, released the outcomes of investigations into the George building collapse at a media briefing in George on Saturday, where this and other damning findings came to light. Cracks were also noted around the base of a column on the ground floor that resembled punch-through patterns. Concerns were apparently raised around the narrow supporting columns and the large spaces between them. Macpherson was joined by the Council for the Built Environment (CBE) as well as the Engineering Council of South Africa, who found a long list of issues behind the tragedy which claimed 34 lives and left 28 people seriously injured, last year. 'A subcontractor warned of cracks starting to appear as early as 2023 to the extent that one could see through them while standing in the basement. The site manager instructed these cracks to be patched with a mixture of sand, cement and mortar.' The health and safety agent also resigned during construction stating that it was 'impossible to safeguard the interests of both the client and contractors amid continuous safety violations', the CBE said. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ The ECSA further found an engineer guilty for several contraventions including misrepresentation of academic or professional qualifications and failure to give due regard to and prioritise the health, safety, and interests of the public, among others. 'The Tribunal has decided to impose the following sanctions, a maximum permissible fine in terms of the Adjustment Fines Act and cancellation of the respondent's registration and the removal of their name from the ECSA register,' the regulator said. Macpherson said the report would also form part of the police investigation. 'If criminal wrongdoing is established, those responsible must be prosecuted without delay. We must ensure that people are held accountable for 34 souls losing their lives. No contractor, engineer, or official should be beyond the reach of the law. He said the concrete used in the slabs did not meet required specifications. 'Where 19 to 25 megapascal were needed, only 13 megapascal of concrete were delivered. These are not minor oversights. These are systemic failures, failures of planning, oversight, enforcement, and culture. What happened here more than a year ago was a lethal convergency of these failures which resulted in the deaths of 34 people. At every problem, there was a chance to turn back, but because of the weak regulatory environment, there was either no incentive or requirement to do so,' Macpherson said. Police spokesperson, Christopher Spies confirmed their investigation was still underway. 'An inquest docket was opened at the time of the incident by the George police. The investigation is at an advanced stage. The case docket will be referred to the National Prosecuting Authority for a decision upon the conclusion of the police probe. The police are not at liberty to divulge any other information at this stage,' Spies said. Over the next three years, the minister said new regulations, legislative amendments, mandatory standards and emergency protocols will be implemented, among others. GOOD party councillor in George, Chantelle Kyd called for the CBE report along with all other reports to be tabled in council. 'We must act decisively to ensure that every municipality, including George, is equipped to strengthen oversight, assess risk, and close the gaps exposed by this collapse. The planning department must review the findings, internal processes must be interrogated, and where necessary, corrective actions must be taken. If we fail to act now, we fail every worker who enters a construction site tomorrow,' said Kyd. Cape Times

Report on ‘entirely preventable' George building collapse will form part of police probe — Macpherson
Report on ‘entirely preventable' George building collapse will form part of police probe — Macpherson

Daily Maverick

timea day ago

  • Daily Maverick

Report on ‘entirely preventable' George building collapse will form part of police probe — Macpherson

Minister of Public Works and Infrastructure Dean Macpherson has announced the completion of both the Engineering Council of South Africa and the Council for the Built Environment's investigations into the collapse of a five-storey development in George, Western Cape, last year. The ECSA report will form part of the police investigation to establish criminal negligence in relation to the incident. Minister of Public Works and Infrastructure Dean Macpherson has announced the completion of the Engineering Council of South Africa's (ECSA) investigation into the culpability of the engineer involved in the construction of the George building that collapsed in 2024. The report will form part of the police investigation to establish criminal negligence in relation to the incident. Speaking at a media briefing on Saturday, 19 July, Macpherson said that both the ECSA and the Council for the Built Environment's (CBE) investigations into the collapse had been completed. He described the CBE report as 'comprehensive and technically detailed', with findings that were 'serious, far-reaching and… alarming'. 'The full ECSA investigation report… will be published in the Government Gazette in due course. An appeal window to these findings is currently under way, which expires on 3 August 2025,' said Macpherson. 'This report must form part of the police investigation as we must establish criminal negligence for what happened. If criminal wrongdoing is established, those responsible must be prosecuted without delay… No contractor, engineer or official should be beyond the reach of the law.' The collapse of the five-storey residential property development, known as 75 Victoria, in George on 6 May 2024 was followed by a days-long recovery effort. It resulted in 34 deaths, with 28 survivors. Many of those who survived continue to endure difficulties linked to serious injuries incurred during the incident. ECSA charges The ECSA charged an engineer implicated in the building collapse with violations of the Code of Conduct and the Code of Practice for the Performance of Engineering Work, the council said on Saturday. The engineer was initially suspended by the ECSA in June 2024, and was subject to a disciplinary hearing on 29 and 30 May 2025. While the ECSA did not name the implicated individual, Daily Maverick has previously reported that the plans for the George building project were signed off by consulting engineer Atholl Mitchell of the company Mitchell & Associates. While the engineer elected not to participate in the hearing, the ECSA noted that a plea of not guilty was entered on his behalf. Upon completion of the disciplinary proceedings, the engineer was found guilty of the charges. The sanctions imposed by the ECSA included the 'maximum permissible fine' in terms of the Adjustment Fines Act 101 of 1991, and the cancellation of the engineer's registration and the removal of his name from the ECSA register. 'The George building collapse complaint was the third complaint received by the ECSA council relating to the conduct of the respondent. In 2019, the ECSA received the first complaint against the respondent and upon review by the investigating committee, it was concluded that there was insufficient evidence to support a finding of a breach of the ECSA's Code of Conduct for Registered Persons,' stated the council. 'A subsequent complaint was lodged in December 2023 against the respondent. Following an independent investigation, the ECSA Council determined that there was prima facie evidence of improper conduct.' The ECSA said its disciplinary ruling, investigation report and supporting evidence had been referred to the South African Police Service for further investigation and action. Key takeaways from CBE report The CBE investigation, conducted by a multidisciplinary team of technical experts, encountered anecdotal evidence suggesting that the failure of the first floor and basement area of the George building initially occurred due to the failure of the reinforced concrete at these levels. The findings of the CBE investigating team included: Unusual building movements and vibrations on the roof slab, observed by a contractor two days before the collapse; Cracks that were noted around the base of a column on the ground floor, resembling 'punch-through patterns', and concerns that were raised about the narrow supporting columns and the large spaces between them; Poor workmanship and quality on site, with a subcontractor reporting that he had observed discrepancies in the concrete supplied for the basement and first-floor slabs – the specifications called for 19-megapascal or 25-megapascal concrete, and the material supplied was 13 megapascals; The resignation of the health and safety agent during construction, with the agent stating that it was 'impossible to safeguard the interests of both the client and contractors amid continuous safety violations'; An inadequate geotechnical investigation, falling 'far short of minimum requirements of South African national standards' and leading to groundwater being discovered in the basement; and A lack of competence on site, with the 'approved competent person' for the structural system lacking the necessary expertise for designing complex structures. The CBE investigation found that South Africa's building regulatory frameworks were outdated, as the National Building Regulations and Building Standards Act and National Building Regulations were last amended during 1996 and 2011, respectively. 'The regulatory bodies and statutory authorities charged with administering construction work in silos, with inadequate information sharing and coordination, hindering effective oversight and enforcement,' added the CBE. The investigating team recommended 16 regulations that would act as measures to strengthen gaps and shortcomings in the building regulatory environment. The implementation of these recommendations requires legislative reform. Macpherson said: 'At every problem [during the construction of the George building], there was a chance to turn back, but because of the weak regulatory environment, there was either no incentive or requirement to do so. This is what makes me so angry when I view this tragedy from today's perspective – it was entirely preventable. 'However, we cannot undo what has happened. But we can, and must, respond with action.' Macpherson announced a 'phase-based reform implementation' process that would include: Immediate interventions, including new regulations, mandatory standards and emergency protocols, between 2025 and 2026; Implementing long-term reform, including legislative amendments and competency-based registration systems, between 2026 and 2028; and Institutional consolidation and relocation of custodianship of building regulations functions and standards to the Department of Public Works and Infrastructure from 2028 onwards. 'We will introduce a revised Council for the Built Environment Bill in Parliament. This Bill will give the CBE stronger investigative powers, consolidate regulatory functions, and establish it as a single, more effective regulator for the built environment,' said Macpherson. He also called for a legislative review of the National Building Regulations that would ensure their alignment with new technologies, climate resilience standards and 21st-century construction practices. 'In partnership with the Department of Labour and Employment, we will propose amendments to the Construction Regulations under the Occupational Health and Safety Act, to strengthen enforcement and accountability of all duty holders,' said Macpherson. The CBE would establish a reporting protocol that mandates the registration of any structural system failure, as well as a hotline to allow workers, built environment practitioners and professionals, or members of the public to anonymously raise safety concerns, he continued. 'We will introduce a national credentialing scheme for built environment professionals that will distinguish the specialised skillset from the generalist, who are already professionally registered,' he said. 'Deeply emotional' Macpherson's briefing on Saturday followed a closed-door engagement with the families of victims of the collapse, which he described as 'deeply emotional'. Elelwani Mawela, a worker from Limpopo who suffered serious injuries during the collapse, said that life had been very hard in the aftermath of the tragedy, as she had no money or support to manage her condition. 'I lost my teeth. I can't eat properly. It's very hard… How can I get money to buy milk, softer food?' she said. 'I've come here today because I want to meet the minister. Thank you very much for your support for all of us. 'I miss my friend. I lost a lot of people. It's very painful. Lots of people at home are starting to bully me because I don't have teeth. Please help us. I will fight until I get justice… I'm still young. I can't eat, I can't smile, I can't talk. Because I'm scared that people are going to bully me with my teeth.' Macpherson acknowledged that the families continued to endure great suffering. 'I would ask and plead that those who so generously reached out after the collapse do so once again until government's internal processes have been finalised. Families are battling to put food on the table. They are battling to deal with the psychological trauma. They are battling with medical bills,' he said. DM Those wishing to help in supporting victims and families affected by the George building collapse can send donations to the Love Garden Route NPC: Standard Bank