Oman: $319mln sewage and water works underway in Bausher

Oman: $319mln sewage and water works underway in Bausher

Zawya8 hours ago
Muscat – Nama Water Services is pressing ahead with major infrastructure projects across Oman to expand wastewater networks, build trea-tment plants, and improve pumping and treated water systems.
One of the largest initiatives under way is in Bausher, Muscat governorate, where seven sewage network projects are being implemented at a combined cost of RO123mn.
Jafar bin Mahna al Hadhrami, Project Manager for Muscat governorate at Nama Water Servic-es, said the works in Bausher inc- lude 311km of main and seconda- ry sewage network lines and 34km of potable water networks. 'The aim is to enhance basic services for residents while supporting long-term infrastructure plans.'
In Bausher Heights, a sewage network project costing RO17.5mn is under construction. Set for completion in 2028, it will serve 60,000 people and cover 68km of sewage networks with 1,100 inspection chambers and 6,850 house connections. Current completion rate is 10%.
A sewage network project in South Azaiba costing RO5.6mn is 12% complete. With 49km of networks, 1,714 inspection chambers and 722 house connections, it will benefit 13,000 people on completion by 2027.
Hadhrami said the first phase of rehabilitating sewage networks in North Ghubra and North Azaiba, costing RO24mn, will start in mid-September 2025. Completion is expected in 2028. The works will include a new 4km main sewage line, replacement of 812 inspection chambers, rehabilitation of the current main line, and linking networks to the pumping station.
To improve pumping capacity, a RO21mn station is being built for Bausher and Al Ansab. It will feature two 17km discharge lines and a 3.5km gravity sewer line to connect both networks. Completion is targeted for 2028.
In Al Ansab, a RO25.7mn sew-age network project is 8% comp-lete. It will include 75.5km of net- works, 1,160 inspection chambers and 4,180 household connectio-ns, with completion set for 2028.
Hadhrami said two projects are also under way in Al Khuwair. The Al Khuwair 1/17 project, cos-ting RO14.3mn, will provide 882 home connections, 30km of sew-age networks, 15km of potable water networks and 1km of trea-ted wastewater networks. The Al Khuwair 2/17 project, worth RO15mn, will provide 858 home connections, 30km of sewage networks, 19km of potable water networks and 2.2km of treated wastewater networks. Both are due for completion in 2029.
© Apex Press and Publishing Provided by SyndiGate Media Inc. (Syndigate.info).
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Kenya taps development banks for airport expansion after ditching Adani deal
Kenya taps development banks for airport expansion after ditching Adani deal

Zawya

time5 hours ago

  • Zawya

Kenya taps development banks for airport expansion after ditching Adani deal

Kenya has invited international development lenders to finance a $2 billion expansion of its main airport in Nairobi nine months after it cancelled a deal with India's Adani Group after its founder was indicted in the United States. The East African nation, which is seeking new ways to finance infrastructure projects due to sharply rising debt, will also issue a securitised bond for 175 billion shillings ($1.36 billion) locally and abroad next month for road construction, Transport Minister Davis Chirchir told reporters on Monday. Chirchir said the government had "written" to development agencies "to basically tell them there's an opportunity to build the airport through the Jomo Kenyatta International Airport, borrowing on its balance sheet." The Japan International Cooperation Agency, China Exim, KFW, the European Investment Bank and the African Development Bank had been contacted, Chirchir said. The airport expansion includes a second runway at the airport and a new terminal building. Chirchir said once the funds were secured, the government would then look for a contractor to carry out the work. "Instead of bringing concessioning to build the airport, we build the airport that we can concession later," he said, referring to the difference with the previous plan which would have seen Adani carry out the expansion and then handed a 30-year lease to operate the airport. That plan was scrapped last year when U.S. authorities indicted Gautam Adani and several executives, alleging they paid bribes to secure Indian power contracts and misled U.S. investors. The Adani Group has rejected the allegations as "baseless" and said it was cooperating with legal processes. On the bond issue for road construction, Chirchir said the government would securitise a portion of the fuel levy it charges motorists, adding the bond would be split into two halves for both a local and an offshore listing. It was too early to say in which foreign market the bond would be sold, Chirchir said. ($1 = 128.9000 Kenyan shillings)

Oman: $7.7mln Quriyat fishing port upgrade 83% complete
Oman: $7.7mln Quriyat fishing port upgrade 83% complete

Zawya

time8 hours ago

  • Zawya

Oman: $7.7mln Quriyat fishing port upgrade 83% complete

Muscat – Construction of a marine wharf development project at Quriyat fishing port is 83% complete, according to Ministry of Agriculture, Fisheries and Water Resources. Costing more than RO2.97mn, the project is part of efforts to modernise fishing ports and boost their role in coastal economies under Oman Vision 2040. Mohammed bin Abdullah al Rashdi, Civil Engineer at Directorate General of Fishing Ports in the ministry, said the project aims to boost economic diversification, attract investment and develop the fishing fleet. 'The ministry seeks to create an investment-friendly environment and make better use of fish resources by improving port services for both public and private use,' he said. The development includes a 185m fixed berth on the breakwater, designed to improve maritime handling operations and expand the port's capacity. 'We are also constructing a new marine berth for mooring ships and boats, which will increase efficiency in port operations,' Rashdi said. A 33,000sqm investment plot is being created within the port to host commercial and service activities linked to the marine fisheries. The site will also have a dedicated area for a marine crane to support ship and boat maintenance. © Apex Press and Publishing Provided by SyndiGate Media Inc. (

Oman: $319mln sewage and water works underway in Bausher
Oman: $319mln sewage and water works underway in Bausher

Zawya

time8 hours ago

  • Zawya

Oman: $319mln sewage and water works underway in Bausher

Muscat – Nama Water Services is pressing ahead with major infrastructure projects across Oman to expand wastewater networks, build trea-tment plants, and improve pumping and treated water systems. One of the largest initiatives under way is in Bausher, Muscat governorate, where seven sewage network projects are being implemented at a combined cost of RO123mn. Jafar bin Mahna al Hadhrami, Project Manager for Muscat governorate at Nama Water Servic-es, said the works in Bausher inc- lude 311km of main and seconda- ry sewage network lines and 34km of potable water networks. 'The aim is to enhance basic services for residents while supporting long-term infrastructure plans.' In Bausher Heights, a sewage network project costing RO17.5mn is under construction. Set for completion in 2028, it will serve 60,000 people and cover 68km of sewage networks with 1,100 inspection chambers and 6,850 house connections. Current completion rate is 10%. A sewage network project in South Azaiba costing RO5.6mn is 12% complete. With 49km of networks, 1,714 inspection chambers and 722 house connections, it will benefit 13,000 people on completion by 2027. Hadhrami said the first phase of rehabilitating sewage networks in North Ghubra and North Azaiba, costing RO24mn, will start in mid-September 2025. Completion is expected in 2028. The works will include a new 4km main sewage line, replacement of 812 inspection chambers, rehabilitation of the current main line, and linking networks to the pumping station. To improve pumping capacity, a RO21mn station is being built for Bausher and Al Ansab. It will feature two 17km discharge lines and a 3.5km gravity sewer line to connect both networks. Completion is targeted for 2028. In Al Ansab, a RO25.7mn sew-age network project is 8% comp-lete. It will include 75.5km of net- works, 1,160 inspection chambers and 4,180 household connectio-ns, with completion set for 2028. Hadhrami said two projects are also under way in Al Khuwair. The Al Khuwair 1/17 project, cos-ting RO14.3mn, will provide 882 home connections, 30km of sew-age networks, 15km of potable water networks and 1km of trea-ted wastewater networks. The Al Khuwair 2/17 project, worth RO15mn, will provide 858 home connections, 30km of sewage networks, 19km of potable water networks and 2.2km of treated wastewater networks. Both are due for completion in 2029. © Apex Press and Publishing Provided by SyndiGate Media Inc. (

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store