Water Resources Department to complete first phase of improvements to Cholavaram reservoir's bund soon
The Cholavaram reservoir in Tiruvallur district is one of the five major reservoirs used to store drinking water for Chennai. Spread over 5.42 sq.km, it serves as a balancing reservoir between the Tamaraipakkam anicut and the Red Hills reservoir. Built during British rule prior to 1871, the waterbody currently has a storage of only 157 million cubic feet against its original capacity of 1,081 mcft. The WRD expects the waterbody to be filled during the Northeast monsoon.
A portion of the bund had suffered damage on several occasions, including in 2014, 2015, and 2017. It may be recalled that the bund suffered severe damage during Cyclone Michaung in 2023.
WRD officials said of the total bund length of 3.57 km, work had been completed to strengthen its 1.04-km critical portion to prevent erosion and ensure dam stability. A diaphragm wall — a concrete wall measuring 6 m in depth near the bund — was one of the main components built as part of the project to reinforce the bund and arrest seepage. While this will protect the bund from erosion, a wave deflector wall has also been built to prevent damage caused by wave action when the reservoir reaches its full capacity.
An official said the top portion of the bund had also been widened by a metre. Work is in progress to lay a bitumen road on top of the bund and repair its parapet wall. 'We have already constructed shutters to regulate water discharge during heavy rainfall,' he added. The WRD has sought ₹50 crore to commence the second phase of the work to repair another 1.2 km of the bund.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

The Hindu
10 hours ago
- The Hindu
Minor leak in LBP canal to be fixed in two days, says Minister Muthusamy
Minister for Housing, Prohibition and Excise S. Muthusamy on Saturday said the minor leakage in the Lower Bhavani Project (LBP) canal at the bridge at Vandipalayam in Sathyamangalam taluk would be rectified within two days. Water was released from the Bhavanisagar Dam on July 31 to irrigate 1,03,500 acres in Erode, Karur, and Tiruppur districts. On Friday, a leakage was noticed at the bottom of the bridge located at the 13th mile of the canal. At the time, 1,000 cusecs of water was being discharged. Despite the leak, discharge into the canal was not stopped, and officials from the Water Resources Department began repair works immediately. On Saturday, the Minister, along with District Collector S. Kandasamy and Erode East MLA V.C. Chandhirakumar, inspected the repair works. Mr. Muthusamy told media persons repair and maintenance works had been carried out along a 74-mile stretch of the canal prior to the release of water to ensure smooth flow. 'However, during routine monitoring, a leak was found on the side portion below the Thottipalayam bridge. There is no major damage, and engineers have said that the issue is minor and will be fixed within two days,' he said. Executive Engineer Gopi (Public Works Department), Assistant Executive Engineer P. Thirumoorthy (Lower Bhavani Basin Division), assistant engineers, and officials accompanied the Minister during the inspection.


Time of India
a day ago
- Time of India
Many wards in Danapur affected by waterlogging
1 2 3 4 Patna: Heavy rain has caused widespread waterlogging in most wards under the Danapur nagar parishad jurisdiction, leaving residents to fend for themselves in absence of timely civic response. The worst-affected areas include ward numbers 11, 19, 20, 21, 24, 26, 35, 38 and 40 where ankle to knee-deep water has inundated streets and residential areas, severely disrupting normal life. The crisis has been exacerbated by the non-completion of the town's drainage system, a long-pending civic project that has drawn the ire of locals, particularly senior citizens and the sick who find it difficult to navigate through the flooded lanes, said JD(U) vice president of Patna district, Sanjay Kumar Singh. Women said they are the worst sufferers as they have to wade through stagnant water to procure essential household items, as vendors and daily suppliers have stopped entering the waterlogged localities in Bibiganj police chowky, Gola Road, Sultanpur, Panchsheel colony, Urja Nagar, IAS colony, Lekha Nagar, RPS Engineering College Mor, Machchua Toli and Lal Kothi Road, he said. Talking to this newspaper here on Friday, several residents of Bibiganj locality expressed frustration over the administration's lack of preparedness. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Magherafelt: If You Were Born Between 1945-1974 You Could Be Eligible For This British Seniors Read More Undo "This happens every monsoon, but this year it is the worst. The drains are half-built, and now we are suffering," said Sushila Devi, a resident of ward number 21. According to a resident of Takiapar and RJD activist Afroz Alam, the local administration should have taken steps much earlier to check waterlogging in the nagar parishad wards. Children have stopped going to their schools, as they have to wade through the stinking water and there's lurking fear of poisonous reptiles, he said. Danapur Nagar Parishad executive officer, Pankaj Kumar, said the district administration has deployed 41 water pumps in an effort to clear water from low-lying areas. All possible efforts are being made to clear water as the pumps are running round-the-clock under the strict supervision of the parishad officials, he said, adding the local administration has also started sprinkling disinfectants to check the outbreak of an epidemic.


The Hindu
a day ago
- The Hindu
Water Resources Department to complete first phase of improvements to Cholavaram reservoir's bund soon
This year, the Cholavaram reservoir will be able to store water to its full capacity as the first phase of work to strengthen the critical portions of its bund will be completed in a fortnight. The Water Resources Department (WRD) has completed major components of the work to improve the bund through a ₹40-crore project. The Cholavaram reservoir in Tiruvallur district is one of the five major reservoirs used to store drinking water for Chennai. Spread over 5.42 it serves as a balancing reservoir between the Tamaraipakkam anicut and the Red Hills reservoir. Built during British rule prior to 1871, the waterbody currently has a storage of only 157 million cubic feet against its original capacity of 1,081 mcft. The WRD expects the waterbody to be filled during the Northeast monsoon. A portion of the bund had suffered damage on several occasions, including in 2014, 2015, and 2017. It may be recalled that the bund suffered severe damage during Cyclone Michaung in 2023. WRD officials said of the total bund length of 3.57 km, work had been completed to strengthen its 1.04-km critical portion to prevent erosion and ensure dam stability. A diaphragm wall — a concrete wall measuring 6 m in depth near the bund — was one of the main components built as part of the project to reinforce the bund and arrest seepage. While this will protect the bund from erosion, a wave deflector wall has also been built to prevent damage caused by wave action when the reservoir reaches its full capacity. An official said the top portion of the bund had also been widened by a metre. Work is in progress to lay a bitumen road on top of the bund and repair its parapet wall. 'We have already constructed shutters to regulate water discharge during heavy rainfall,' he added. The WRD has sought ₹50 crore to commence the second phase of the work to repair another 1.2 km of the bund.