Amtrak set to close one East River tube Friday night, starting 2.5 years of repairs
The single tube closure, slated to last 10 days, is the first step in a two-and-a-half year repair project that will reduce the train capacity of the subterranean structure by 25%. The tunnel is used daily by Amtrak, Long Island Rail Road and New Jersey Transit trains.
'While I continue to believe this work could be accomplished without a full shutdown, I understand the importance of moving this project forward,' Hochul said in a statement following a meeting with Amtrak and Metropolitan Transportation Authority leadership Thursday.
'Amtrak has agreed to provide enhanced inspections, additional shift crews and the development of an operational response plan to help mitigate potential impact on commuters throughout the duration of the project,' she added.
The East River Tunnel, owned by Amtrak and first opened in 1910, consists of four tubes linking Manhattan and Queens. Two of the tubes — Nos. 3 and 4 — primarily serve the LIRR, the main user of the tunnel, allowing its service to Penn Station. The other two tubes — Nos. 1 and 2 — are used by Amtrak for service on the Northeast Corridor, and by NJ Transit for storage of commuter trains in Queens' Sunnyside Yard.
Tubes 1 and 2 were inundated with salt water during Hurricane Sandy in 2012, and Amtrak has said the resulting corrosion of wires has played havoc with signaling and traction power in the tubes over the past decade. Railway officials also point to spalling concrete along the tunnel benchwall — the structure through which the tunnel's high-voltage power lines run — that they say has been caused by the saltwater exposure.
On a recent press tour of Tube 2, Amtrak officials highlighted a slew of issues in the tunnel — from large gaps where the benchwall had crumbled to corrosion caused by groundwater incursion unrelated to Sandy.
Only a full shutdown of each tube, the officials said, would allow work crews to rebuild the benchwalls, replace all the wiring and make tweaks to the trackbed to improve drainage.
'The reliability of these tunnels is not going to get any better,' Amtrak spokesman Craig Schulz told reporters last week. 'These tunnels are aged, they've been damaged by Superstorm Sandy, and they are in urgent need of repair.'
'The longer we delay this work, the more we risk the chance of service disruptions that are not acceptable to anybody,' he added.
After Amtrak closes Tube No. 1 to all train traffic Friday night, crews will conduct 10 days of work on this tube — shoring up third-rail infrastructure and making other tweaks — before reopening it, and then shutting down Tube No. 2 next.
If all goes according to plan, Tube No. 2 will then be closed for 13 months, during which time Amtrak crews will overhaul its tracks, wiring and benchwalls, effectively building a new tunnel in the shell of the old.
Three months after Tube No. 2 is complete, Amtrak will shut down Tube No. 1, and give it the same treatment.
During the two-and-a-half years when one of the four tubes will be shut to train traffic, the current LIRR and Amtrak schedules — both of which were slightly reduced as of November in anticipation of the shutdown — should, in theory, be unaffected.
But LIRR sources tell The News that signal failures inside all four tubes are somewhat common, and that it is not unusual to have a tube go out of service for hours while Amtrak crews are making repairs on it. While one tube is down for Amtrak's upcoming overhaul, that means any relatively minor problem in another tube could leave the three railroads competing for space in just two tubes — for hours at a time.
As a result, MTA leadership has questioned the necessity of a full overhaul — and expressed concerns that even an hour of operations with potentially only two tubes operating could bring commuter train service to its knees.
LIRR President Rob Free said last week that Amtrak should be asking: 'What [work] is absolutely essential, and only essential, to make sure the tunnels are in good condition?'
Free and other MTA brass have called on Amtrak to adopt a similar approach to what the MTA did — unwillingly, at first — to repair similar corrosion damage in the L train's Canarsie Tunnel.
The MTA's eleventh-hour decision in 2019 to abandon the old electrical wiring inside the Canarsie Tunnel's benchwall and mount new wiring on exposed racks along the tunnel's length removed the need to demolish concrete infrastructure within the tunnel — averting a planned 15-month shutdown.
But Amtrak officials have repeatedly claimed that approach won't work in this case — saying that while the 600-to-800-volt DC wiring in the Canarsie Tunnel could be left exposed, the 12,000-volt AC lines that run the overhead power for Amtrak and NJ Transit trains cannot.
Though similar high-voltage lines have been rack-mounted in other systems around the world — a 2020 report by independent experts at London Bridge Associates said such an approach was feasible on the East River Tunnel's sister structure, the North River Tunnel beneath the Hudson — Amtrak officials say they're committed to the additional layer of fire safety and insulation that a benchwall provides.
A diagram of the planned rebuild reviewed by the Daily News shows that Amtrak does indeed plan to use rack mounting for the tunnel's lower-voltage wiring — including everything from radio communication to the tunnel's signal system. The massive cables used to carry the high-voltage traction power that runs the trains, however, will be placed inside a new benchwall.
In a statement issued Thursday, an Amtrak spokesman said the meeting with Hochul and MTA officials had been 'productive,' adding they would continue to monitor their work plan and make adjustments as necessary to minimize the impact on commuters.
'It is important to all of us this project is a success, so that all passengers, including Long Island and upstate New York residents and travelers, continue to have strong, reliable, on-time service now and in the future,' the statement read.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


CBS News
8 hours ago
- CBS News
MTA holding 1st public hearing on proposed $3 subway and bus fares
New Yorkers have a chance to weigh in on the MTA's proposed fare hikes this week. The first of three public hearings is scheduled for Tuesday night in Brooklyn. Under the proposed fare hikes, subway and bus rides would cost $3, up from the current $2.90. Monthly and weekly tickets for the Long Island Rail Road and Metro-North Railroad would also increase up to 4.5%. The hikes are slated to take effect early next year to align with the launch of a full tap-and-go system on subways and buses. Tuesday's public hearing is scheduled for 6 p.m. to 9 p.m. at 130 Livingston Street in Brooklyn, or participants can attend via Zoom. The other two sessions will be held Wednesday from 10 a.m. to 1 p.m. and from 5 p.m. to 8 p.m. CLICK HERE for all the details. The MTA Board made another big decision Monday, approving a massive $1.9 billion contract to begin construction on Phase 2 of the Second Avenue Subway expansion in East Harlem. Phase 2 includes work to bore a new tunnel, rehab an existing one and create new stations. The MTA says it will improve and reduce commute times for area residents by creating two new stations on Second Avenue at 106th and 116th streets, as well as extending Q train service to a third new station at 125th Street and Lexington Avenue that will connect to the 4, 5 and 6 trains, as well as Metro-North. The expansion means some New Yorkers now face eviction by eminent domain, but many say they understand the need to improve mobility in the community. Phase 2 is being funded, in part, by revenue from congestion pricing. The MTA estimates the project will generate some 70,000 jobs, with a target of 20% of those being local hires from East Harlem. While preliminary work on the project will begin this year, heavy construction will start in 2026 and the tunnel boring will take place in 2027. The goal is to get trains moving by 2032.


CBS News
15 hours ago
- CBS News
With New York's 2nd Avenue subway expansion, eminent domain will force dozens to move
As New York City's long-awaited 2nd Avenue subway expansion finally gets the green light to move forward, some New Yorkers will now face eviction by eminent domain. The Metropolitan Transportation Authority approved a nearly $2 billion contract to add three more stops on the Q line, extending the subway into East Harlem. Phase Two of the $1.9 billion project approved by the MTA board on Monday will extend the Q train from 96th Street to 125th Street. It will include work to bore a new tunnel, rehab an existing one and create the new stations. "The contract before us today would be the largest tunneling contract ever awarded by the MTA," Chair and CEO Janno Lieber said. Gov. Kathy Hochul said it will build on a promise made nearly 100 years ago. "For the people of East Harlem, the time of promises is over. We are moving down the tracks as quickly as we possibly can," Hochul said. Phase Two comes with a nearly $7 billion price tag, funded in part by congestion pricing, the governor said. The subway's arrival in East Harlem means some people have to depart. The MTA is seizing buildings through eminent domain to make way for the construction of new tunnels and stations. Cheikh Diop, who owns Touba Africa Store, said the MTA first notified him about vacating over a year ago. A 90-day commercial vacancy notice in June told him the agency "plans to acquire the property ... before the end of 2025." "I have no choice. If we gotta move, we gotta move," Diop said. But he doesn't mind losing the property because he also lives in the neighborhood and relies on public transportation. "It's good," he said. The MTA said roughly 33 units in another building are being forced out too. Early construction is expected to start later this year. The goal is to get trains moving into East Harlem by 2032. For more information about Phase 2 of the Second Avenue Subway extension, click here.


New York Post
19 hours ago
- New York Post
Dozens of New Yorkers at risk of eviction as MTA makes way for Second Avenue Subway: ‘People are nervous'
Make way for the eviction train. Dozens of New Yorkers in 33 apartments across East Harlem are at risk of getting kicked out of their homes and businesses as the MTA forges ahead with the Second Avenue Subway's next phase. The Metropolitan Transportation Authority has embarked on a blitz of legal seizures to clear the way for planned new subway stations at 116th and 125th streets — with evictions unfolding as soon as Oct. 15, officials said and records show. Advertisement Aaliyah Vasquez, 42, told The Post her grandmother was being uprooted from her life after receiving an eviction notice for 2058 Second Ave. 'She's very sad about it,' said Vasquez. 'My grandmother has lived here for years. Her pharmacy is the one on the corner. She gets her home supplies from the deli across the street. She buys her meat from the butcher next door. 'I understand the need for more trains down here, it's a subway drought on Second Avenue. But you can't uproot people's lives to do it. I don't even see how it's legal,' said Vasquez, who is now helping her grandma find a new home. Advertisement The MTA, according to court records, is claiming eminent domain — the government's constitutional power to snatch private public property for public use, as long as the owner is given just compensation — to seize the buildings. 3 New Yorkers in 33 apartments will be evicted to make way for the second phase of the Second Avenue subway. MTA During the Second Avenue Subway's $4.45 billion first phase — which extended the Q line to 96th Street and was completed in 2017 — the MTA spent roughly $10 million of the total cost to relocate residents whose homes were in the path of the new stations, officials said. The MTA helped the tenants who were forced to relocate due to eminent domain with financial assistance, finding a real estate agent and other other moving resources, an MTA spokesperson said. Advertisement The project's anticipated $7.7 billion second phase is expected to have fewer relocations, but the final cost has yet to be tallied as the acquisitions are ongoing, the spokesperson said. The addresses up for seizure can be found on a list of properties, mostly along Second Avenue and 125th Street, posted online by the MTA as the agency held public hearings on the issue. At least one of those properties is no longer being considered for eminent domain, officials said. MTA officials couldn't come up with the full list of properties that would be seized, despite repeated requests by The Post Monday. 3 The second phase will move forward after a crucial vote attended by Gov. Kathy Hochul. James Keivom Advertisement 3 The eminent domain seizures could remake 125th Street. MTA Officials did confirm that New Yorkers living in 33 apartments will be evicted under their subway plans. Court records showed eminent domain proceedings have started for at least 13 of the properties on the original list, some of which are vacant. One Harlem family interviewed by Gothamist shared with the outlet a notice giving them 90 days to leave their home. 'We're definitely in limbo,' a family member, Jocelyn Diego, told Gothamist. 'It's too much to process, and not only that, we're just hoping that they find us an apartment because at the end, me and my mom feel like [the MTA] have the responsibility to find an apartment.' A worker in a store along Second Avenue, who did not want to be identified, said she's unsure what the owner will do. 'People are nervous. They have been in the neighborhood for years,' she said. 'It's really hard. People don't know where to go since rent is so high everywhere.' Advertisement MTA board members Monday approved a $1.9 billion contract for crews to begin tunneling and work on two new subway stations as part of the next phase of the project — a vote attended by Gov. Kathy Hochul. 'It's a handful of properties that we haven't yet acquired, and then there's a set of easements that we require and agreements to underpin property or put vibration monitoring on it,' said Jamie Torres-Springer, the MTA's president of construction and development. 'We are way, way ahead of where (phase one) was in terms of acquisitions. Not everything has been completed, but it's no secret to this.' — Additional reporting by Dorian Geiger and Peter Senzamici