Builder Can't Be Penalised For Authority's Delay In Approving Plans: Allahabad High Court
The court granted relief to M/s Kinetic Buildtech Pvt Ltd on cancellation of allotment by the Greater Noida Industrial Development Authority (GNIDA)
The Allahabad High Court has held that a developer cannot be faulted for construction delays when the development authority itself fails to act on the building plan or hand over lawful possession of the land.
The bench of Justice Prakash Padia, allowing a writ petition filed by M/s Kinetic Buildtech Pvt Ltd, quashed Greater Noida Industrial Development Authority (GNIDA)'s decision to cancel a plot allotted to the builder and forfeit Rs 10.64 crore, the initial premium deposit, over alleged default in payment and construction.
Kinetic Buildtech was allotted a 22,000-square-metre plot in Sector-10 of Greater Noida in 2014. A lease deed was executed in 2015, following which the company paid the mandatory 20% premium. However, the developer contended that it was never given actual physical possession of the plot as per the site plan annexed with the lease deed.
Later on, there was a unilateral change in the site layout by GNIDA. A modified layout was introduced on July 9, 2015, but was never communicated to the builder until years later, during a revision hearing. Even then, the possession letter bore no signature of the person handing over or receiving possession, which the court noted made it merely 'paperwork" and 'no actual physical possession".
The court also found that while the developer had submitted a building plan and even deposited a processing fee of Rs 38 lakh, GNIDA never decided on the application. A letter raising objections to the plan was allegedly sent in May 2016, but the court observed that there was no proof that this letter was ever served to the petitioner.
In light of these findings, the high court concluded that GNIDA's actions—failing to hand over possession, not executing a corrected lease deed, and leaving the construction application pending—could not be used as grounds to punish the petitioner.
'The development authority kept the application for grant of permission for construction pending with him, as such, it cannot be blamed that petitioner has not carried on the construction within the stipulated period…Thus, the petitioner cannot be blamed and charged for the same," the court held.
The court cited the SC judgment in the case of Municipal Committee Katra & others Vs Ashwani Kumar (2024), and said no party should be allowed to profit from its own wrongdoing. 'The development authority itself had faulted in not delivering possession and not taking a decision on the application for construction. For this, the petitioner cannot be penalised," it held.
Accordingly, the court set aside the cancellation orders and directed GNIDA to execute the required correction deed and extend the construction deadline accordingly.
First Published:
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Deccan Herald
18 minutes ago
- Deccan Herald
Parliament panel slams ministry for MGNREGS reply, pendencies
The committee, in its report on the 2025-26 budgetary allocation, said wages worth Rs 12,219.18 crore were pending, while Rs 11,227.09 crore remained uncleared against the material component for a welfare-oriented schematic intervention like the MGNREGS.


Time of India
32 minutes ago
- Time of India
Cool comfort worth the extra 100, say passengers on board state's first AC local
Kolkata: Suburban commuters on board the maiden AC EMU Ranaghat-Sealdah train were ecstatic to experience the much-awaited service on the first day of the week. The feelings were mixed when it came to coughing up Rs 120 for the ride from Ranaghat to Sealdah. While some seemed sensitive about paying Rs 100 more for a journey that otherwise costs Rs 20 in non-AC rakes, others said the cool comfort and the superior travel justified the fare. A monthly ticket costs Rs 2,430. The one-way fare ranges from Rs 35 to Rs 120 depending on the distance travelled. The train was flagged off with much fanfare from Sealdah on Sunday. Commercial services started at 8.29 am on Monday. The inaugural commercial service was fairly crowded, with several passengers standing. But there was enough legroom, unlike the non-AC local trains. Ranaghat resident Dilip Ghosh, who works in Khadi Bhavan on CR Avenue, was smiling as he looked around the ICF-made rake, from the AC vent over the seat, noting the time as the automatic doors closed and the train chugged out of Ranaghat station. "This is like travelling on a metro train. We are covering 90 km in AC comfort and saving time as well. It would have taken around Rs 1,000 for the same ride on a hired car and taken me at least two-and-a-half hours. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Villas For Sale in Dubai Might Surprise You Villas In Dubai | Search Ads Get Rates Undo I shall reach Sealdah station at 10.10 am. A bus ride from there to my office will take another 10 mins," the 55-year-old said happily. "I shall try to catch the return train at 6.50 pm so I can be home by 8.45 pm (the Down train reaches Ranaghat at 8.32 pm)," he added. You Can Also Check: Kolkata AQI | Weather in Kolkata | Bank Holidays in Kolkata | Public Holidays in Kolkata The train will make two trips every day, addressing the morning and evening rush, and stop at Bidhannagar Road, Dum Dum Junction, Sodepur, Khardah, Barrackpore, Naihati, Kanchrapara, Kalyani, and Chakdah, officials of Eastern Railway's Sealdah division said. "I don't know...," said Balmiki Ray, a passenger who took the train from Khardah. "I would have paid Rs 5 for the same journey. Today I bought a ticket to Sealdah for Rs 60. The monthly passes will be a bit cheaper. But I wonder if it makes sense to increase my daily commuting expense 12 times for this comfort," the worker employed with a shop at Bagri Market said. Biplab Mondol, who boarded the train from Chakdah, echoed: "Today I paid Rs 105 because I was curious about the facility. The monthly ticket will cost me Rs 2,125. It's difficult to make a call when the daily commuting by non-AC train costs barely Rs 10," Mondol said. Arati Saha, a schoolteacher from Krishnanagar, insisted: "This is the ultimate comfort and safety. Two reserved coaches for ladies, that, too, air-conditioned! Only two rides may seem tokenistic, but this is certainly a significant start." Stay updated with the latest local news from your city on Times of India (TOI). Check upcoming bank holidays , public holidays , and current gold rates and silver prices in your area.


Time of India
an hour ago
- Time of India
CM lays stones for six road projects worth Rs 766.73 cr in city
Patna: CM Nitish Kumar on Monday laid the foundation stones for six projects worth Rs 766.73 crore to provide road connectivity in the western Patna. The projects were announced during his Pragati Yatra in the Patna district conducted earlier this year. The six projects include four roads, a flyover and an underground drain-cum-road. Three separate functions were held to lay the foundation stones. The first function was held near Patna AIIMS roundabout, the second one near Kothwan Rupaspur canal and the third one on Nehru Path below the Patli road. "The roads, whose foundation stones have been laid, are not only meant to ease the traffic movement in the western Patna that is developing fast, but also provide smooth movement of traffic from J P Setu, Patliputra station, Danapur, Gola Road, Saguna Mor, Naubatpur, Khagaul and Patna AIIMS localities towards Biharsharif," the CM said on the occasion. "They will also give a boost to economic activities and social development in the entire area, as it has been developing fast," he added, and asked the officials to ensure that the projects were completed in time. Among those who accompanied the CM on the occasion were deputy CM Samrat Choudhary and MLC Rabindra Kumar Singh, as well as CM's principal secretary Deepak Kumar, development commissioner Pratyaya Amrit, CM's secretary Kumar Ravi, road construction department secretary Sandeep Kumar R Pudukalkatti, Patna division commissioner Chandrashekhar Singh, Patna DM Thyagarajan SM and SSP Kartikeya K Sharma, among others. At the AIIMS roundabout function, the CM laid the stone for the widening and strengthening of the two-lane 10.5 km Patna AIIMS-Janipur-Painapur Nev road, which would involve expenditure of Rs 138.50 crore. The foundation stone for a flyover to be constructed at Naubatpur Lakh with an investment of Rs 73.06 crore was also laid. At the second function held on Kathwan Rupaspur canal, the CM laid the foundation stone for the construction of 6.9 km four-lane road to provide a link to the Khagaul-Nehru Path, Ashok Rajpath and Rupaspur canal road. It would involve an expenditure of Rs 71.48 crore. The third function was held below Patli Path. From here, the CM laid the foundation stones for a group of three projects. One of them is the construction of a link road to connect Digha-AIIMS-Patli road with Nehru Path on the side of Danapur, which will be completed with an investment of Rs 148.86 crore. The second is construction of an underground drainage facility-cum-road on both the sides of 2.7 km from Rupaspur canal and Saguna Mor up to Nehru Path, whose completion would require an investment of Rs 318.51 crore. The third project related to widening and strengthening of the 2.20 km road between Nehru Path and Gola road will be completed at an expenditure of Rs 21.35 crore. Stay updated with the latest local news from your city on Times of India (TOI). Check upcoming bank holidays , public holidays , and current gold rates and silver prices in your area.