A year on, Malwa canal project still in planning stage

A year on, Malwa canal project still in planning stage

Time of India2 days ago
1
2
Bathinda: A year after Punjab chief minister
Bhagwant Mann
inspected the site selected for the proposed Malwa Canal at Doda village near Gidderbaha and announced its construction with much fanfare, the project remains in the planning stage.
The process for land acquisition is yet to be put into motion.
The Punjab government had initiated the process for the proposed canal to be constructed parallel to the Rajasthan and Sirhind Feeder canals to provide irrigation facilities in the districts of Ferozepur, Faridkot, and Muktsar. The 149-km-long canal was to be constructed at a cost of Rs 2,300 crore, designed to carry 2,000 cusecs of water and benefit nearly 2 lakh acres of farmland in the Malwa region.
It is to start from the Harike headworks in Ferozepur district.
After the by-election at Gidderbaha was over on Nov 20, 2024, residents of Doda village, Karnail Singh and Baldev Singh, expressed their concerns, stating, "We are asking about progress in the construction of the canal, but there is no one to answer our queries."
Gidderbaha AAP MLA Hardeep Singh Dimpy Dhillon said, "Only recently, I met Punjab water resources department principal secretary Krishan Kumar, who told me that it is still at the planning stage and the land acquisition process has to be taken ahead, and all this may take more time."
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
The Simple Morning Habit for a Flatter Belly After 50!
Lulutox
Undo
With the villages situated on the tail ends of the Sirhind Feeder canal, which runs parallel to the Rajasthan feeder, not getting adequate canal water supply, the need for constructing a new canal was necessitated. The carrying capacity of the Sirhind feeder went down due to seepage, drawing of water by lift pumps, and no proper repairs for long. When the new canal comes up, the demand for such tail-end villages could be met, the state government had then stated.
The state government was to move towards land acquisition needed for the canal, apart from using Rajasthan government land. Bhagwant Mann, while addressing a public meeting at village Doda, said that it is for the first time after independence that a new canal is being constructed, as no previous government ever thought to provide an adequate quantity of canal water to farmers in the last 77 years.
As the groundwater was withdrawn excessively, most of the blocks turned into dark zones for extracting much more water than recharging, and no stress was made to increase canal water.
There are over 300 lift pumps of the Sirhind Feeder which irrigate the area on the left side of the Rajasthan feeder, originally irrigated by Sirhind Canal system (Abohar Branch Upper and Bathinda Branch) being fed from Ropar Head Works. However, instead of improving the supply of water at the tail portion of the Sirhind canal system, the government a long time back decided to supply water to the area from Sirhind feeder through lift pumps.
Thus, there was a shortage of water from the canal system in Abohar and Fazilka. As a long-term measure to improve irrigation facilities in the area, the government has decided to construct the Malwa Canal.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Municipal crackdown on pigeon feeding remains inconsistent across Mumbai
Municipal crackdown on pigeon feeding remains inconsistent across Mumbai

Time of India

timean hour ago

  • Time of India

Municipal crackdown on pigeon feeding remains inconsistent across Mumbai

M umbai: The municipal corporation's drive to curb unregulated pigeon feeding appears inconsistent, with some spots facing strict enforcement while others remain unchecked. TOI visited three of these sites in the city on Friday, especially in the wake of the massive public protest at Dadar Kabutarkhana last week. At GPO Corner on Mint Road, locals said rampant feeding continues unabated as neither BMC staff nor police personnel are deployed to monitor the area. The Kabutarkhana remains uncovered, with citizens openly scattering grains. Locals and shopkeepers warned that the growing pigeon population is raising health risks from droppings and airborne infections, urging BMC to post staff for regular surveillance, cover feeding zones, and fine violators. TOI also saw a man throwing pigeon feed. In sharp contrast, Dadar Kabutarkhana is under tight control with heavy police presence and active civic monitoring. A large tarpaulin has been installed to deter birds, and fines are being imposed on those caught feeding them. While authorities hail the clampdown, local shopkeepers complain that the police bandobast and movement restrictions are hurting festive season business. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like The Most Beautiful Women In The World Undo "There are civic staff with penalty books, and if they argue over payment of penalty, we also ask the police to intervene," said a local resident. You Can Also Check: Mumbai AQI | Weather in Mumbai | Bank Holidays in Mumbai | Public Holidays in Mumbai At the Matunga station site, BMC has covered the Kabutarkhana with tarpaulin, but shopkeepers say people continue tossing grains on top of it, rendering the measure ineffective. They allege a lack of consistent enforcement, with neither civic nor police presence at most times, and warn of unsanitary conditions and potential disease outbreaks. Residents said there is a need for a uniform, sustained crackdown to prevent the city's anti-pigeon feeding drive from becoming patchy and ineffective. The BMC was penalising individuals ₹500 under Solid Waste Management By-Laws and actually collected over ₹68,700 in fines from 142 cases between July 13 and August 3, 2025, across nearly 42 locations. Stay updated with the latest local news from your city on Times of India (TOI). Check upcoming bank holidays , public holidays , and current gold rates and silver prices in your area. Get the latest lifestyle updates on Times of India, along with Raksha Bandhan wishes , messages and quotes !

31 train accidents in 2024–25 alone: Railway Minister tells RS
31 train accidents in 2024–25 alone: Railway Minister tells RS

New Indian Express

timean hour ago

  • New Indian Express

31 train accidents in 2024–25 alone: Railway Minister tells RS

NEW DELHI: Indian Railways witnessed 31 consequential train accidents during 2024–25, including over 20 derailments, despite ambitious claims of significantly reducing major accidents. According to a provisional assessment, these incidents caused damage to railway property valued at approximately Rs 157 crore. Union Railway Minister Ashwini Vaishnaw informed the Rajya Sabha that between 2014–15 and 2023–24, more than 740 passengers lost their lives in 678 consequential train accidents, with over 2,000 passengers sustaining injuries. In a written reply on Friday, the Minister provided a comparative overview, stating, 'the consequential train accidents during 2004–14 were 1,711, occurring on an average of 171 per year, which declined to 31 in 2024–25 and only 3 in 2025–26 up to June.' Detailing the incidents of 2024–25, Vaishnaw said that a total of 31 train accidents were reported, including '3 collisions, 24 derailments, 1 level-crossing accident and 3 fire accidents' across the Indian Railways. He added that the total cost of damages to railway property, such as rolling stock and track damages due to these accidents, has been conservatively assessed at Rs 157.04 crore.

Railway Minister Ashwini Vaishnaw tells Rajya Sabha only 31 train accidents occured in 2024–25
Railway Minister Ashwini Vaishnaw tells Rajya Sabha only 31 train accidents occured in 2024–25

New Indian Express

timean hour ago

  • New Indian Express

Railway Minister Ashwini Vaishnaw tells Rajya Sabha only 31 train accidents occured in 2024–25

NEW DELHI: Indian Railways witnessed 31 consequential train accidents during 2024–25, including over 20 derailments, despite ambitious claims of significantly reducing major accidents. According to a provisional assessment, these incidents caused damage to railway property valued at approximately Rs 157 crore. Union Railway Minister Ashwini Vaishnaw informed the Rajya Sabha that between 2014–15 and 2023–24, more than 740 passengers lost their lives in 678 consequential train accidents, with over 2,000 passengers sustaining injuries. In a written reply on Friday, the Minister provided a comparative overview, stating, 'the consequential train accidents during 2004–14 were 1,711, occurring on an average of 171 per year, which declined to 31 in 2024–25 and only 3 in 2025–26 up to June.' Detailing the incidents of 2024–25, Vaishnaw said that a total of 31 train accidents were reported, including '3 collisions, 24 derailments, 1 level-crossing accident and 3 fire accidents' across the Indian Railways. He added that the total cost of damages to railway property, such as rolling stock and track damages due to these accidents, has been conservatively assessed at Rs 157.04 crore.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store