Eskom faces R1 billion damages for cancelling steam generator contract
Eskom has been ordered to pay nearly R1 billion to French nuclear contractor Framatome after the Western Cape High Court ruled that the utility refused to pay damages for cancelling a contract to install steam generators at Koeberg nuclear power station.
This ruling stems from a 2014 agreement originally made with Areva, which was later ceded to Framatome, covering the design, manufacture, and installation of six replacement steam generators—three for each unit at Koeberg.
Framatome, which has been in operation for 60 years, was contracted to supply and install two sets of three replacement steam generators, one set to be installed in each of the reactor buildings at units 1 and 2 at Koeberg during separate planned outages of these units.
These installations were meant to take place during a scheduled maintenance outage, which kept getting postponed. Two months after the outage was finally scheduled to happen, 'Eskom informed Framatome that it would not be continuing with the steam generator replacement,' the judgement said.
As a result of the cancellation of the deal, Eskom's project manager 'acknowledged that Eskom's decision to postpone the work constituted a compensation event,' the judgment read.
Although the project manager had acknowledged that Eskom's cancellation triggered compensation, he determined that the value of compensation was nil.
The entire matter then went to arbitration, where the adjudicator ordered that Eskom must pay compensation for cancelling the contract, including for storing equipment, as well as implementation activities, which work had been wasted by Eskom delaying the date of the planned maintenance outage.
After some back and forth between the parties and the adjudicator, during which the parties didn't agree on costs, 'Eskom made it clear that it had no intention of providing the adjudicator with any further information or participating any further in the adjudication process,' the ruling read.
As a result, the adjudicator issued a determination of the damages amount, and Eskom decided to take the issue to the Western Cape High Court, arguing that the amount in damages was not determined by the date it was due – voiding his determination.
In defending Eskom's legal action, Framatome argued that none of the arbitration proceedings were improper, nor was the adjudicator abusing his power.
The Judge ruled that 'there is no basis to set aside the decisions of the adjudicator which are valid and binding. In terms of the parties' contract Eskom was obliged to comply therewith.'
Eskom, it found, had to comply with its contractual obligations. The court found that Framatome was entitled to the full amount it sought.
In addition to the R1bn payment, Eskom had to pay interest and costs.
Cape Argus

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Daily Maverick
5 hours ago
- Daily Maverick
Johannesburg Property Company retreats amid backlash over parks cash grab
Johannesburg Property Company's moves coincide with the sorry state of the city's finances — under the spotlight ahead of next year's municipal elections — giving rise to the impression of a rent-seeking dash for cash while the trough remains open. The Johannesburg Property Company's (JPC) attempts to 'alienate' historic properties, including public spaces for sale or lease, seem to be coming unstuck. Concern erupted among Johannesburg residents after a council agenda in late June suggested that several public open spaces – including Marks Park and surrounding greenbelt areas – could be up for sale or re-leasing agreements. Daily Maverick can also report that the Bryanston Sports Club has been on JPC's radar screen, but it is undermining its attempts to monetise such assets through its blundering approach. The initial flagging of designs on Marks Park triggered a widely circulated petition opposing the moves, which garnered 13,300 signatures. The petition was submitted to JPC. On Wednesday, 30 July, it was announced during a council meeting that an item regarding the alienation of Marks Park was withdrawn – nipping the process in the bud, for now. 'This is a small victory for us because it might come back. But at least our voices have been heard,' Nicolene Jonker, DA councillor for Ward 88, said in a video message to residents. Bryanston Sports Club targeted The Bryanston Sports Club has also been targeted – but in an opaque and ham-fisted manner. On 5 June, an undated notice providing for 14 days of public participation for a change in the leasing arrangements of 'Portion 1 of erf 4668 Bryanston' – effectively the sports club and municipal library on the grounds – was discovered on the floor of the clubhouse. Club manager Pat Carolin told Daily Maverick that two serious errors were immediately spotted in the notice – it was pointedly undated, and the period is supposed to be 30 days, not 14. The notice also seemed to have been pinned on the sly on a door, and then fell to the floor. Daily Maverick has had sight of this notice. A subsequent government gazette notice published on 15 July made no mention of the lease and instead referred to public participation for the proposed development and sale of the property – contradicting the original notice. 'This discrepancy is worrying,' Carolin said. Carolin met JPC general manager Sizeka Tshabalala at the Bryanston Sports Club on Tuesday, 5 August, along with the ward councillor. Tshabalala said JPC acknowledged the error in the gazette and said it would restart the 'public participation process'. The Bryanston lease ran out in 2019, and Carolin said they had tried several times to renew it on a long-term basis, but to no avail. It is now on a month-on-month basis. The club's annual lease is R1,500 (R125 a month), but it does all of the maintenance, spending an average of R1.2-million a year over the past three years. As a non-profit, it funds this upkeep from membership fees and local sponsors. Some private investors will come to the party – but the club needs a long-term lease agreement for that to happen. 'We are providing a service to the community, that is our mandate, and so we should not be commercialised or pay market rates. If we pay market rates, we will expect the JPC to maintain the asset,' said Carolin, who Daily Maverick spoke to at the clubhouse on Tuesday, 5 August. 'We are concerned that they want their bread to be buttered on both sides, get the rent and have the tenant pay for the upkeep. We are distrustful of their motives because of their lack of communication,' he said. In response to our queries, JPC confirmed a mistake had been made in the gazette and an erratum has been made to correct the error, confirming a public participation process for the lease of the property. JPC's moves come as the sorry state of Johannesburg's finances comes under the spotlight ahead of next year's municipal elections – giving rise to the impression of a rent-seeking dash for cash while the trough remains open. The Sunday Times and Bloomberg have reported that Finance Minister Enoch Godongwana has given Joburg Mayor Dada Morero 14 days to explain how he plans to fix the city's finances and recoup R2.4-billion lost in 'unauthorised, irregular, fruitless and wasteful expenditure.' Against this backdrop of increased scrutiny and a lack of trust among the City of Gold's long-suffering ratepayers, the JPC would do well to get its ducks in a row. Putting a date on public participation notices would be a good start. DM

The Herald
6 hours ago
- The Herald
Bay acting electricity boss dragged out of office by staff
Nelson Mandela Bay's acting executive director of electricity and energy, Tholi Biyela, was forcibly removed from his office at the Munelek building on Tuesday by disgruntled officials who accused him of undermining them and ruling with an iron fist. A large group of officials, accompanied by leaders of the South African Municipal Workers Union (Samwu), stormed Biyela's office, demanding his resignation from the position. His removal was preceded by a union meeting. During the meeting, officials voiced their dissatisfaction with Biyela, and a resolution was passed to remove him from office. Acting city manager Ted Pillay has since called a top-level management meeting for Wednesday to discuss the issue and workers' grievances. Samwu shop steward Ayanda Solani said Biyela allegedly undermined engineers who had worked in the city for years by starting a process to appoint Eskom as an independent contractor. 'On top of this, Eskom will also bring its service providers to work on the municipal infrastructure,' Solani said. 'It is as if we are not capable of doing the work we studied for and have been doing all our professional lives. 'This partnership means that Eskom will be procuring material on behalf of the municipality and will attend to electricity faults at a cost. 'This will cost the municipality twice for the same job.' Solani said Biyela wrote a memorandum and prepared a service level agreement that just needed Pillay's approval. 'The turnaround strategy [for the electricity directorate] has not been presented and agreed with the unions, but Biyela is ready to present it at the next standing committee.' Solani said they were unhappy with Biyela calling a meeting to address workers without Samwu, in which he bashed the union. Biyela has been at odds with some officials in the directorate who have previously accused him of threatening their lives when he said in a meeting that 'lives will be shed'. On the other hand, Biyela opened a case with the police in July after receiving an anonymous phone call from a stranger who said 'You won't see the sun rise tomorrow'. Working relations between Biyela and staff have created unfavourable conditions for all parties involved. Biyela did not respond to a request for comment. Electricity and energy political head Ziyanda Mnqokoyi said, based on information they had received, the only concern raised with Biyela was that staff did not want him in the post. 'The Eskom issue is new to me. 'However, if this concern was raised by the workers regarding the involvement of Eskom in certain technical operations, it has been noted. 'It is important to clarify that the municipality, like many others across the country, occasionally engages with Eskom or other entities when specialised or high-risk technical assistance is required, particularly in instances where the stability of the local grid or resident safety may be at stake. 'This is not a reflection on the competency of our internal teams but rather a strategic step to augment capacity and ensure service continuity.' Regarding allegations about Biyela's management style, Mnqokoyi said they would be investigated through the proper channels. 'I will work closely with the city manager and labour representatives to restore calm, address underlying concerns and ensure that the interests of the residents remain the top priority.' When the reporter arrived at Munelek, one of the workers who spoke at the gathering said Biyela made their work harder and would confront subordinates over office gossip. 'Biyela is entertaining gossip and threatening to suspend people,' the worker said. 'He has a bullying kind of leadership style. 'His appointment as acting executive director with only five months in the metro was a huge disaster. 'He comes from a small local municipality in Knysna and has no experience of running a metro department. 'To add to that, he doesn't have experience and is not mature.' A second worker said Biyela, by bringing Eskom in, was saying they could not do their jobs. 'Many of our colleagues are on leave because they can't deal with his leadership style of threatening people. 'We can't continue like this. 'He must go and we will continue doing our jobs as we have been all along.' Municipal spokesperson Sithembiso Soyaya condemned Biyela's removal. He said such conduct undermined the law, workplace discipline and institutional processes to resolve disputes. 'We can confirm that an unlawful incident involving the forceful removal of Biyela occurred this morning,' Soyaya said. 'This is being investigated and dealt with through the appropriate legal and disciplinary channels. 'Security and legal measures are being put in place to ensure Biyela's safety and to prevent any recurrence of such incidents. 'Leadership appointments follow formal governance processes and decisions cannot be made through unlawful or coercive means. 'Biyela's acting contract remains valid until further notice or formal review by the city manager, who has the delegated authority in this regard.'

The Star
7 hours ago
- The Star
Eskom faces R1 billion damages for cancelling steam generator contract
Nicola Mawson | Published 1 week ago Eskom has been ordered to pay nearly R1 billion to French nuclear contractor Framatome after the Western Cape High Court ruled that the utility refused to pay damages for cancelling a contract to install steam generators at Koeberg nuclear power station. This ruling stems from a 2014 agreement originally made with Areva, which was later ceded to Framatome, covering the design, manufacture, and installation of six replacement steam generators—three for each unit at Koeberg. Framatome, which has been in operation for 60 years, was contracted to supply and install two sets of three replacement steam generators, one set to be installed in each of the reactor buildings at units 1 and 2 at Koeberg during separate planned outages of these units. These installations were meant to take place during a scheduled maintenance outage, which kept getting postponed. Two months after the outage was finally scheduled to happen, 'Eskom informed Framatome that it would not be continuing with the steam generator replacement,' the judgement said. As a result of the cancellation of the deal, Eskom's project manager 'acknowledged that Eskom's decision to postpone the work constituted a compensation event,' the judgment read. Although the project manager had acknowledged that Eskom's cancellation triggered compensation, he determined that the value of compensation was nil. The entire matter then went to arbitration, where the adjudicator ordered that Eskom must pay compensation for cancelling the contract, including for storing equipment, as well as implementation activities, which work had been wasted by Eskom delaying the date of the planned maintenance outage. After some back and forth between the parties and the adjudicator, during which the parties didn't agree on costs, 'Eskom made it clear that it had no intention of providing the adjudicator with any further information or participating any further in the adjudication process,' the ruling read. As a result, the adjudicator issued a determination of the damages amount, and Eskom decided to take the issue to the Western Cape High Court, arguing that the amount in damages was not determined by the date it was due – voiding his determination. In defending Eskom's legal action, Framatome argued that none of the arbitration proceedings were improper, nor was the adjudicator abusing his power. The Judge ruled that 'there is no basis to set aside the decisions of the adjudicator which are valid and binding. In terms of the parties' contract Eskom was obliged to comply therewith.' Eskom, it found, had to comply with its contractual obligations. The court found that Framatome was entitled to the full amount it sought. In addition to the R1bn payment, Eskom had to pay interest and costs. Cape Argus