SC halts HC's Rs 1,169 crore deposit order in MMRDA–Reliance metro dispute
Supreme Court
has halted a
Bombay High Court
order that asked
Mumbai Metropolitan Region Development Authority
(MMRDA) to deposit the entire
arbitral award
of Rs 1169 crore that
Mumbai Metro One Private Ltd
(
MMOPL
), a subsidiary of Anil Ambani's
Reliance Infrastructure
, won in 2023.
However, the apex court said that the HC direction to deposit the entire award amount favouring MMOPL will remain stayed subject to MMRDA depositing 50% of the awarded amount in the HC.
A Bench led by Justice Manoj Mishra sought response from MMOPL on an MMRDA's appeal against the HC July 10 order that refused the latter's request for unconditional stay on the arbitral award.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Join new Free to Play WWII MMO War Thunder
War Thunder
Play Now
Undo
The top court further clarified that the pendency of the proceedings shall not preclude the HC from proceeding further with the hearing of the application filed by MMRDA under of the Arbitration and Conciliation Act, 1996 and if, in the meantime, the HC finally decided the application, one way or the other, this interim order shall abide the order passed by the HC.
Solicitor General Tushar Mehta, appearing for the state entity, contended that stay condition of depositing the entire awarded amount, at this stage, would be unduly harsh and therefore, it was a fit case to modify the condition imposed by the High Court while granting interim relief to the Ambani firm.
Live Events
MMRDA in its appeal submitted that the HC had erred in not granting the interim relief given that the impugned award passed by the tribunal was patently illegal and perverse, beyond the scope of the
arbitration agreement
, in breach of the principles of natural justice and passed without application of mind and without any basis of evidence.
Majority decision of a three-member arbitral tribunal in 2023 had awarded Rs 992 crore with interest to MMOPL, a SPV between Reliance Infrastructure that holds 74% stake and MMRDA that holds 26% stake. The award was passed by the tribunal in 2023, and then corrected in 2024. The JV operates Mumbai's first metro line on Versova -Andheri-Ghatkopar corridor.
The Maharashtra government had in June 2006 awarded the Metro One Project to the consortium of Reliance Infrastructure and Veolia Transport SA (now known as Transdev Lle – de - France).
Multiple disputes arose between the parties over development, design, engineering, financing, procurement, construction, operation and maintenance of a mass rapid transit system, besides a delay in completion of the project. The
metro rail project
started with a delay of over two years. MMOPL claimed that the project costs increased from Rs 2,356 crore to Rs 4,321 crores, which the MMRDA has contested.
Accordingly, the Ambani firm had invoked the arbitration clause under the Concession Agreement.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
25 minutes ago
- Time of India
Tender row at key F&CC meeting lay bare rift between office-bearers
Ludhiana: The Finance and Contracts Committee (F&CC) meeting scheduled for Friday could not be convened as senior deputy mayor Rakesh Prashar and deputy mayor Prince Johar boycotted the session at the mayor camp office, sources said. The matter has been escalated to the party high command. Over 400 resolutions aimed at the city's development were to be discussed at the meeting. However, disagreements between the mayor, senior deputy mayor, and deputy mayor put a spanner in the works. A few days ago, senior deputy mayor Prashar expressed concern about allotment of tenders by the MC for beautification of parks in Focal Point at an approximate cost of Rs 10 crore. He alleged that MC officials had flouted norms by awarding tenders using the e-mail ID of a retired executive engineer. However, officials said that they had permission from the XEN to use his ID. When mayor Inderjit Kaur called Prashar to attend the meeting, he initially insisted that clarification be sought from officials. The mayor then requested his attendance to discuss the issue with MC commissioner Aaditya Dachalwal. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Remember Him? Sit Down Before You See What He Looks Like Now 33 Bridges Undo Upon the mayor's arrival, he inquired about cancellation of the tenders. She replied that they would hold the meeting before addressing the matter. When deputy mayor Prince Johar arrived, Prashar refused to enter the meeting venue till the issue was addressed. This prompted the mayor to tell him to do as he wished. Thereafter, both Prashar and Johar left the meeting venue. Sources said that the deputy mayor was also agitated by recent employee transfers without his approval. After their departure, the mayor attempted to approach them with the assistance of MLAs, but they remained adamant. MLAs are now expected to intervene, and a meeting has been scheduled to resolve the issue. When contacted, senior deputy mayor Rakesh Prashar said, "Officials should clarify why they opened the tenders from the ID of a retired XEN and why they gave away tenders with less savings for the department. Many tenders are given away in this manner. When we are not given answers to previous queries then what is the point in approving more resolutions?" Meanwhile mayor Inderjit Kaur denied boycott of the meeting by the deputy mayor and senior deputy mayor. "Both had some personal engagements, so they could not attend the meeting. We will fix the meeting again next week," she said. MSID:: 122905555 413 |


Time of India
25 minutes ago
- Time of India
Road work in Unkal progressing at a snail's pace
Hubballi: The CC (cement concrete) road construction in Unkal, intended to resolve long-standing commuting issues, is progressing at a snail's pace. Although sanctioned for Rs 20 crore under the national highways, delays in land acquisition and pending compensation to residents have hampered progress. Locals are urging authorities to expedite the work. The road work, which began over two and a half years ago, has made only half the progress. Of the 160 properties involved, land for around 60 properties was acquired, leaving locals to endure severe difficulties. Approximately 300m of road still needs to be constructed. The remaining section of the road has deteriorated, with potholes causing issues for motorists. An electric pole has not been shifted. The work period was already extended many times. As per the last extension, the work should be completed by the end of March 2025. Abdul Razak, a resident of Unkal, said that the CC road construction work was ongoing for the last three years. Due to the rain, the road deteriorated. The road work was stopped. The HDMC is delaying providing compensation for the land. He urged the authorities to complete the road work soon. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Dog Raises 3 Tiger Cubs - Years Later Zookeeper Bursts Into Tears When Tiger Does The Unexpected Undo Pavan Hanjagi, a motorist, said there are potholes causing problems for pedestrians and motorists. The incomplete road work is causing inconvenience. The work started two years ago. The authorities failed to develop the CC road work promptly, he said. HDMC's ward No. 37 corporator, Umeshgouda Koujageri, said that the road work spans 3.5km from Unkal Cross to Sai Nagar Circle and Sai Nagar Main Road, the church, and Hebballi gate. Around 300m of road from Mailarlinga Temple to Chalawadi Oni is pending. The HDMC has to release the amount for land acquisition. He mentioned that 85% of the work was completed. HDMC engineer Sharanbasappa Kembhavi stated that land acquisition and compensation to the house owners will be provided by HDMC. Around Rs 12 crore was estimated for the compensation. Already, Rs 5 crore has been compensated to the 60 house owners. The remaining 100 houses will be compensated. Tulasi G, assistant engineer of national highway, said that the road is being developed under CRF. The HDMC should clear the land for the CC road work. Soon after clearing the land, the work will start, she added.


Deccan Herald
41 minutes ago
- Deccan Herald
Bengaluru: Now, Ferrari & Mercedes owners pay Rs 1 cr in fines, unpaid road tax
Bengaluru: Transport authorities on Friday penalised the owners of two more luxury cars that were registered outside Karnataka but regularly used within the state without paying applicable road tax. .A Jayanagar RTO team collected nearly Rs 1 crore in fines and unpaid road tax from the car owners. .The cars include a Ferrari 812 Superfast registered in Jharkhand (JH 10 BS0099) and a Mercedes-Benz G-Class AMG G 63 registered in Puducherry (PY 05 K 6309). .The Ferrari owner had to fork out Rs 61,94,494 and the Merc owner Rs 37,03,644. .The two cars were being regularly used in Karnataka for more than two years, a Transport Department official told said. .Bengaluru bizman fined Rs 38 lakh for unpaid road tax on luxury cars bought from Amitabh Bachchan, Aamir on Wednesday, transport authorities fined scrap dealer-turned-real-estate businessman Yousuf Shariff, popularly known as KGF Babu, nearly Rs 40 lakh for using two Maharashtra-regitered Rolls-Royce cars in Bengaluru without paying the required road tax. .One of the cars (MH 02-BB-0002) was bought from Bollywood legend Amitabh Bachchan, and the other (MH11-AX-0001) from actor Aamir Khan. .As per transport department rules, any vehicle registered outside Karnataka and used continuously in the state for over a year must pay the applicable road tax.