Five KKDW ‘sick projects' in Sarawak to be completed under 13MP
Ahmad Zahid, who is also the Minister of Rural and Regional Development, said the causes for the projects' delay included site issues such as permits, land acquisition and overlapping pipe alignments, in addition to weather conditions.
'Since the 13MP will be tabled at the coming Dewan Rakyat session, any sick projects will be expedited and its completion period must be within the 13MP, namely from Rolling Plan 1 to 5.
'For example, for non-sick projects, but projects that have been delayed, namely the Maktab Rendah Sains MARA (MRSM) in Lawas which has obtained approval but not yet implemented... my instructions is that it must be implemented under the 13MP Rolling Plan 1,' he said.
He said this at a media conference after attending the Special Meeting on the Implementation of KKDW Development Projects in Sarawak here today.
Ahmad Zahid said that following the landslide incident in Kampung Lereng Bukit, Miri in January, which completely damaged 14 houses, efforts to rebuild the houses of all the affected residents would be carried out after the Gawai Day celebration.
'A suitable plot of land has been obtained as determined by the Sarawak Land Custody and Development Authority (PELITA), with the implementation carried out by the state government agency,' he said, adding that the incident affected a total of 277 residents in the affected settlement.
He also said that his ministry plans to set up the MARA Poly-Tech College (KPTM) of Sarawak either in Kuching or Samarahan to expand opportunities for youths in the state to further their studies at the pre-diploma, diploma and foundation level.
He is targeting a total of 1,000 students to study at the KPTM by 2028.
'We plan to start with about 200 students and, in the following years, we expect to take in 500 students yearly,' he said, adding that the KPTM will offer studies in the fields of business, information technology and humanities.
Also present were Sarawak Deputy Premier Datuk Amar Dr Sim Kui Hian, Deputy Minister of Rural and Regional Development Datuk Rubiah Wang and Sarawak Minister of Utilities and Telecommunications Datuk Julaihi Narawi.
Earlier, the nearly two-hour special meeting aimed to coordinate the implementation of KKDW rural development projects in Sarawak to ensure the people can enjoy the basic facilities and infrastructure.
Meanwhile, the KKDW said in a statement that Sarawak has received an allocation of RM3.2 billion under the 12MP, involving the implementation of 403 programmes and projects, a total project cost of RM21.73 billion.
It added that of the total, 178 projects or 44.71 per cent have been identified as still in the 'Pre-Implementation' status, with 155 projects having been approved from 2021 to this year.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


New Straits Times
2 hours ago
- New Straits Times
Shamsul Azri: Projects under 13MP to be monitored regularly to avoid delays
PUTRAJAYA: Every project under the 13th Malaysia Plan (13MP) will be monitored regularly to ensure there are no delays in implementation, said Chief Secretary to the Government Tan Sri Shamsul Azri Abu Bakar. Accordingly, he said the monitoring of projects under the 13MP will be jointly conducted by the Ministry of Finance and the Ministry of Economy, with reports to be made twice a year. "This time, we will really make sure that the 13MP is implemented as planned, because it spans a long period until 2030. "All approved projects must be implemented promptly, because any delay will cause disappointment among the people," he told reporters after officiating the MAPPA XX 2025 Run in Putrajaya today. Shamsul Azri said he will personally conduct site visits and make surprise inspections at all 13MP project locations. "Our aim is to serve the people and we are supposed to bring them joy. Therefore, we must implement development initiatives without delay and free from bureaucracy," he said. Prime Minister Datuk Seri Anwar Ibrahim, when tabling the 13MP in the Dewan Rakyat on Thursday, said the monitoring mechanism will be enhanced through the Policy Implementation Plan Monitoring System (PPD). "The 13MP governance structure will also be mobilised in stages, culminating in reports to the Cabinet," he said. Under the 13MP, Anwar said infrastructure and public facility projects involving flood mitigation and improved road accessibility are among the people-centric initiatives that will be prioritised from 2026 to 2030. He said a total of RM20 billion has been allocated to implement 103 Flood Mitigation Plan (RTB) projects to reduce the risks and impact of such disasters. In addition, one million units of affordable housing will be built by the Federal and State Governments, as well as private developers, from 2026 to 2035 to enable as many people as possible to live in safe and comfortable homes. Meanwhile, Shamsul Azri expressed appreciation to the approximately 12,000 participants who took part in the MAPPA XX 2025 Run in Putrajaya today. "Healthy citizens, prosperous nation. Let's be active and engage in sports," he said.


The Sun
2 hours ago
- The Sun
13MP key milestone for Malaysia's medium-term development says Lee
KUALA LUMPUR: The tabling of the 13th Malaysia Plan (13MP) in Parliament marks a pivotal moment in shaping the nation's medium-term development, according to Alliance for a Safe Community chairman Tan Sri Lee Lam Thye. As Malaysia faces global economic uncertainty, technological shifts, climate challenges, and demographic changes, he described the plan as an opportunity to realign priorities, strengthen resilience, and drive sustainable progress. 'In general, the plan must be commended for its intent to address critical national challenges such as income inequality, digital transformation, green economy transition and institutional reform,' he said. Lee stressed that the plan's effectiveness relies on disciplined execution, transparency, and collaboration across government and society. He called for a robust monitoring system to track progress, alongside regular public reporting and audits to ensure accountability. Strong coordination between federal, state, and local agencies is essential to prevent inefficiencies, he added. Engagement with civil society and the private sector must continue beyond planning to maintain inclusivity. 'Development expenditure must be prioritised based on impact, equity, and sustainability, with a focus on reducing leakages and wastage,' Lee said. He also emphasised public service capacity building and institutional reforms, urging adaptability to global or domestic changes. - Bernama

The Star
2 hours ago
- The Star
13MP projects to be monitored regularly, says Chief Secretary
PUTRAJAYA: Every project under the 13th Malaysia Plan (13MP) will be monitored regularly to ensure there are no delays in implementation, says Chief Secretary to the Government Tan Sri Shamsul Azri Abu Bakar. Accordingly, he said the monitoring of projects under the 13MP will be jointly conducted by the Ministry of Finance and the Ministry of Economy, with reports to be made twice a year. "This time, we will really make sure that the 13MP is implemented as planned, because it spans a long period until 2030. "All approved projects must be implemented promptly, because any delay will cause disappointment among the people,' he told reporters after officiating the MAPPA XX 2025 Run in Putrajaya on Saturday (Aug 2). Shamsul Azri said he will personally conduct site visits and make surprise inspections at all 13MP project locations. "Our aim is to serve the people and we are supposed to bring them joy. Therefore, we must implement development initiatives without delay and free from bureaucracy,' he said. Prime Minister Datuk Seri Anwar Ibrahim, when tabling the 13MP in the Dewan Rakyat on Thursday, said the monitoring mechanism will be enhanced through the Policy Implementation Plan Monitoring System (PPD). "The 13MP governance structure will also be mobilised in stages, culminating in reports to the Cabinet,' he said. Under the 13MP, Anwar said infrastructure and public facility projects involving flood mitigation and improved road accessibility are among the people-centric initiatives that will be prioritised from 2026 to 2030. He said a total of RM20bil has been allocated to implement 103 Flood Mitigation Plan (RTB) projects to reduce the risks and impact of such disasters. In addition, one million units of affordable housing will be built by the Federal and State Governments, as well as private developers, from 2026 to 2035 to enable as many people as possible to live in safe and comfortable homes. Meanwhile, Shamsul Azri expressed appreciation to the approximately 12,000 participants who took part in the MAPPA XX 2025 Run in Putrajaya. "Healthy citizens, prosperous nation. Let's be active and engage in sports,' he said. Also present were Public Service Director-General Tan Sri Wan Ahmad Dahlan Abdul Aziz and Ministry of Communications Secretary-GeneralDatuk Seri Mohamad Fauzi Md Isa. - Bernama