Grid recovery brings hope for load shedding-free summer

Grid recovery brings hope for load shedding-free summer

IOL News4 days ago
Electricity and Energy Minister Kgosientsho Ramokgopa outlines progress in South Africa's electricity sector
Image: Jairus Mmutle/GCIS
South Africa's state of power grid shows real momentum after years of disruption, with unplanned outages shrinking, reliability rising, and a clear path toward a stable summer.
During a media briefing in Pretoria on Wednesday, Minister of Electricity and Energy Dr Kgosientsho Ramokgopa framed the August briefing as evidence that disciplined maintenance, unit returns, and strategic upgrades finally translate into tangible, near-term resilience for households and businesses.
The briefing, which draws on the Department of Electricity and Energy's August 2025 State of Electricity briefing, outlined a landscape in which unplanned outages are trending down and the grid shows signs of strengthened resilience ahead of the coming summer.
Ramokgopa opened by acknowledging the progress while tempering expectations.
'What we're seeing is a recovery trajectory delivering real results - lower unplanned losses, higher reliability metrics, and a clearer path to secure generation capacity for the 2025/26 summer,' the minister said.
'We are not claiming victory, but we are confident that the combination of disciplined maintenance, returning units to service, and strategic upgrades will continue to strengthen the grid's resilience.'
Key numbers presented in the briefing portray a sector moving away from the worst days of load shedding toward a more stable operating envelope.
There has been no load shedding since 15 May 2025, with only 26 hours recorded between 1 April and 31 July 2025. Between 1 April and 7 August 2025, the Unplanned Capacity Loss Factor (UCLF) fell to 28.35%, a week-on-week improvement of about 0.23%.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
Ad loading
The ministry cautioned that the system remains sensitive to external pressures and the realities of operating a large, aging fleet - still, the data point to meaningful gains.
Ramokgopa stated that the year-to-date Energy Availability Factor (EAF) stood at 60.14% by 8 August 2025, up roughly 4.4 percentage points from April 2025.
The weekly EAF oscillated between 62% and 70%, with a month-to-date average of 65.38%, signalling growing fleet stability and reliability.
On the fuel side, he stated that the Open Cycle Gas Turbine (OCGT) performance showed a notable uptick in activity. The OCGT load factor reached 5.99% for the week, up from 0.31% the prior week.
He stated that from 1 April to 7 August 2025 (the winter period), Eskom spent about R5.842 billion on fuel for its OCGT plants, generating 988.56 GWh.
'The year-to-date OCGT load factor stood at 9.35%, a slight week-on-week decrease but still higher than the 4.82% recorded during the same period last year.'
The briefing highlighted a broad set of initiatives under the Operational Reliability and Sustainability Plan, designed to push long-term reliability and safety.
These efforts include reducing the number of trips, improving outage planning and execution, and accelerating the implementation of strategic projects.
The plan also emphasised a strengthened people-plant-process mindset, with root-cause analysis, trip reduction directives, and expanded partnerships with original equipment manufacturers and other utilities to improve availability of spares, technology, and maintenance capability.
Beyond maintenance, the minister emphasised capacity additions and returns from units brought back from long-term outages.
Since late 2023, several key units have returned online or been upgraded, contributing to approximately 2,500 MW of added capacity.
Ramokgopa added that notable milestones include Koeberg Unit 1 returning to service, Kusile units coming back online, and Medupi Unit 4 synchronising in July 2025, all of which aim to reinforce security of supply as the grid moves through a transition period.
The minister said that the improvements are about short-term numbers and longer-term stability.
'The focus on Koeberg, Medupi, Kusile, Tutuka, and other critical stations is about more than today's metrics. It's about maintaining a stable, predictable power system that supports households, industry, and the broader economy,' Ramokgopa said.
thabo.makwakwa@inl.co.za
IOL Politics
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Infrastructure damage to blame for disuse of refurbished trains, says Minister Creecy
Infrastructure damage to blame for disuse of refurbished trains, says Minister Creecy

IOL News

timea day ago

  • IOL News

Infrastructure damage to blame for disuse of refurbished trains, says Minister Creecy

Transport Minister Barbara Creecy has confirmed that Prasa was considering the cancellation of contracts linked to the R7.5 billion train refurbishment project of its coaches. Image: GCIS Transport Minister Barbara Creecy has attributed the disuse of trains refurbished by the Passenger Rail Agency of South Africa (Prasa) to infrastructure damage caused by theft and vandalism that affected the railway lines where the old fleet could be used. Creecy said Prasa has embarked on a rebuilding and recovery programme to revitalise the lines and introduce new trains in the recovered lines. 'The old fleet trains may be best utilised in lines and corridors that are mainly outside the metros. Most of these lines are owned by Transnet, and Prasa is in discussion with Transnet on the recovery of these lines for use to transport passengers,' she said. Some of the refurbished old fleet trains are being used in the Eastern Cape and Western Cape, said Creecy when responding to parliamentary questions from EFF MP Omphile Maotwe. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading Her response comes after Prasa spent R2.5 billion of the R7.5 billion of the General Overhaul Project to refurbish the old grey-and-yellow rolling stock. In June, Prasa told the Portfolio Committee on Transport it has no plans to spend the remaining R5 billion on the refurbishment of the coaches. Creecy revealed that a total of 272 coaches have been refurbished to date. 'About 183 refurbished coaches have not yet been deployed to operations. There are no coaches that have been refurbished that have been discarded,' she said. According to Creecy, Prasa is reviewing the use of the refurbished trains. This could result in internal use of the coaches, leasing to private companies as part of reform in the rail sector and selling to potential buyers within the SADC. Prasa was looking into options to utilise coaches hauled by diesel locomotives on non-electrified lines, optimise operations in the Eastern Cape by introducing more train services, and partner with other organs of state to repurpose some of the refurbished coaches. 'Once completed, the review will be processed for consideration by the board and shareholders,' Creecy said. Meanwhile, the minister confirmed that Prasa was considering the cancellation of contracts linked to the R7.5 billion train refurbishment project of its coaches. Creecy said Prasa was undertaking an option analysis to determine the best way forward with regard to the general overhaul contracts. 'Prasa has sought legal advice on the matter.' Creecy also said her department was working closely with Prasa to ensure that the options analysis supports the long-term goals of rebuilding a reliable, affordable, and accessible public rail system. She was responding to a different set of questions from Maotwe when she asked what legal advice had been sought from Prasa regarding the potential financial and contractual consequences of the cancellation of the contracts. Maotwe also enquired about the risk assessment that has been conducted to determine the possible legal claims and liabilities Prasa could face from contractors of the contracts that were terminated, as well as the impact of the cancellation of the contracts on the rail industry, public funds already spent, and the future viability of commuter rail services. Creecy said the risk assessment, which included evaluating potential legal claims and liabilities arising from possible contract termination, is currently being concluded. 'This forms part of wider options aimed at guiding Prasa's decision in a legally and financially sound manner.' The impact study on the implications for the rail industry, public funds already invested, and the future viability of commuter rail services was being finalised. Creecy said the findings will be integrated into a comprehensive options analysis to ensure that any decisions taken are informed and aligned with broader strategic objectives. 'No decision has been made that will impact the alignment with long-term goals of rebuilding a reliable, affordable, and accessible public rail system,' she said.

Eskom confident it will keep the lights on
Eskom confident it will keep the lights on

eNCA

time3 days ago

  • eNCA

Eskom confident it will keep the lights on

JOHANNESBURG - No surprise power cuts expected for the rest of winter. This according to Electricity Minister Kgosientsho Ramokgopa, who provided an update on the state of the grid. He says the energy availability factor is improving, averaging between 62% and 70%. The country has experienced no rolling blackouts since May 2025 proving Eskom's ability to meet the demand for power supply during the winter period. But to do this, the power utility found itself having to burn more diesel and that saw them spend R5-billion in the last four months.

Ramakgopa urges Eskom to withdraw court challenge on electricity trading licences
Ramakgopa urges Eskom to withdraw court challenge on electricity trading licences

IOL News

time4 days ago

  • IOL News

Ramakgopa urges Eskom to withdraw court challenge on electricity trading licences

Minister for Electricity and Energy, Kgosientso Ramakgopa and Eskom CEO Dan Marokane during the media briefing on the State of the National Grid on Wednesday. Image: GCIS Banele Ginidza Minister for Electricity and Energy, Kgosientso Ramakgopa, has urged Eskom to withdraw its ongoing court challenge against the Energy Regulator of South Africa (Nersa) regarding the awarding of electricity trading licences to private companies. This appeal comes as Ramokgopa emphasised the need for a regulatory environment that fosters competition rather than legal disputes. Ramakgopa's remarks highlight a growing divide amongst business stakeholders. While some, such as Business Leadership South Africa (BLSA) and Business Unity South Africa (BUSA), have been vocal critics of Eskom's decision to litigate, the South African Local Government Association (SALGA) has sided with the utility. In response to the pushback, Ramakgopa advised Eskom, "not to burden the judges to come into this domain," underscoring his belief that court intervention would complicate an already intricate sector. "Nersa then initiated the process of reviewing and coming up with the rules. The initial timeline was that they will do that within 12 months. I asked Nersa that the pressure is such that we need to conclude those rules as soon as possible," Ramokgopa said during a media briefing on Wednesday. "And Nersa has agreed that we'll truncate that to three months without compromising the quality of the impact and what the rules will look like. And in that context, I said to Eskom it's not advisable that you go to the courts. And with the highest respect we have with the judiciary, don't invite the judiciary into a space that is really technical, if you like." Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ However, Ramokgopa acknowledged that introducing competition in this nascent market could be precarious. He explained that the market's current conditions might lead to a dilemma where private entities, driven primarily by profit motives, tend to serve only the higher ends of the market, thus neglecting poorer consumers and potentially decimating local municipalities as they lose their customer base. "Because this is a nascent space we are starting, none of us have been in this space before. There's naturally going to be friction, interpretation, misinterpretation of what this reform means," he said. "There's going to be conversations and, in some instances, disagreement on the pace of these reforms. The issue whether the regulator is capacitated enough to be able to manage and oversee these reforms. "Is this monopoly that is Eskom ready to relinquish that monopoly and accept that they are new players? And what the Eskom team had raised was that we are not opposed to the reforms, but what we want is clarity with regards to the rules." Ramakgopa said what the SA Local Government Association was saying was that what this dispensation does was that munnicipalities were going to lose their best customers who underpin and guarantee them the revenue stream, and they will be left with those that can't afford. "So that's the argument," he said, adding that whether Eskom and its board took that decision was outside of the entity's scope. "I've raised it with the chair. Don't enter the court process. Let's not muddy the space. We have agreed, next time doing that, the shareholder will also oversee the process," Ramokgopa said. "It's a particularly unhelpful approach to muddy the waters. Allow the space and for us as the players, there's friction. And in that period, the expectation is that let's clear the rules. And then once we have cleared the rules, then proceed with the issuing of the license. "I have raised that to the chair and its something that they will go back and ensure that we are able to address it. I have no answer now whether they have initiated it or not, the conversation took place yesterday." BUSINESS REPORT

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store