logo
Public servants paid ArriveCan's main contractor GCStrategies without ensuring work was done, Auditor-General finds

Public servants paid ArriveCan's main contractor GCStrategies without ensuring work was done, Auditor-General finds

Auditor-General Karen Hogan has found wide-ranging concerns about federal contracts awarded to GCStrategies, an IT staffing agency, including that public servants regularly paid the company without evidence that work was done, failed to request or review time sheets, allowed contractors to work on federal files without security clearances and did not ensure the company was charging fair market rates.
GCStrategies is a two-person company founded in 2015 in the Ottawa-area by Kristian Firth and Darren Anthony, two men who had previously worked in IT sales for other companies in the national capital.
The largely unknown duo jumped into the Canadian political spotlight nearly three years ago in connection to their role as the main private contractors on the Canada Border Service Agency's ArriveCan app for cross-border travellers, which was launched during the pandemic.
Revelations that the cost of the app grew from an initial $80,000 to nearly $60-million led to a wave of independent investigations and years of House of Commons committee hearings into the project and the broader issue of how much Ottawa is paying for private-sector IT consultants.
This is Ms. Hogan's second audit report involving GCStrategies. Her 2024 audit report into federal spending on ArriveCan found a 'glaring disregard' for basic management practices and concluded that GCStrategies was directly involved in setting narrow terms for a $25-million contract involving some ArriveCan work that it ultimately won.
Auditor-General's ArriveCan report finds 'glaring disregard' for basic management practices
The House of Commons later approved a motion calling on Ms. Hogan to review all of GCStrategies' federal contracts, which she agreed to in October of last year, leading to Tuesday's report.
Mr. Firth, the company's managing partner, has told MPs that neither he nor his partner perform any IT work. Rather they secure federal contracts and then subcontract the work to other IT consultants. He said they retain a fee worth between 15 and 30 per cent of the contract value for their services.
Tuesday's report said GCStrategies was awarded 106 contracts by 31 federal organizations between April, 2015 and March, 2024, worth an estimated combined value of $92.7-million. Of those contracts, 41 were awarded without competition. The total amount spent by the government for the contracts is estimated at $64.5-million.
The report said that nearly half of the spending with the company was by the Canada Border Services Agency, which led the ArriveCan project. The CBSA has launched an internal investigation that includes a review of the agency's relationship with GCStrategies and the RCMP has also said it is conducting an investigation.
The RCMP searched Mr. Firth's home in April, 2024.
Neither the CBSA nor the RCMP have released any conclusions related to the investigations.
Tuesday's audit report is based on a review of a sample of the federal contracts awarded to GCStrategies.
The report said that in 46 per cent of the reviewed contracts, the federal organizations had little to no evidence to support that the requested work was actually performed.
'Despite this, federal government officials consistently authorized payments. As a result, we were unable to conclude whether these certifications by government officials were appropriate or amounted to a contravention of the Financial Administration Act,' the report states.
That act is what guides public servants who have authority to approve federal spending.
The report also found that in half of the reviewed contracts, federal organizations were not able to show that all subcontractors had the appropriate security clearance prior to the contract being awarded. It also found that in 21 per cent of the contracts with security requirements, subcontractors were working throughout the contract period without the required clearance on file, including one contract at National Defence and one contract at Innovation, Science and Economic Development Canada.
'Having contract resources working without the required security clearances weakens the government's ability to protect sensitive information, assets, and work sites,' the report states.
Another failing identified in the report relates to poor oversight of the fees charged by GCStrategies and its subcontractors.
The report found that in 58 per cent of the reviewed contracts, public servants either accepted time sheets with poorly documented descriptions of work performed or failed to collect time sheets at all.
In one contract involving the federal innovation department, officials could only provide auditors with time sheets for one of the 25 subcontractors hired to work for them through GCStrategies.
The report also found that in about a third of the reviewed contracts, officials could not show that the subcontractors had the experience and qualifications to do the work.
'Without this information, federal organizations did not know whether contract resources provided by GCStrategies could perform the work in the contract or whether the rates paid were appropriate,' the report said.
The report states that while this audit focused on contracts awarded to one company, the findings highlight gaps in basic requirements that all federal organizations should follow when procuring services. It also says the report confirms weaknesses raised in previous audits.
For instance, the report found that no federal department currently collects government-wide information on rates paid and supplier performance related to contracting.
Public Services and Procurement Canada announced on Friday, just days before the release of the Auditor-General's scheduled report, that it was suspending GCStrategies from all federal contracting for seven years.
The announcement extended an earlier suspension announced in March, 2024. The department did not provide details on its decision, other than to say it was deemed ineligible following 'a thorough assessment of the supplier's conduct by the Office of Supplier Integrity and Compliance.'
Joël Lightbound, the federal minister for Government Transformation, Public Works and Procurement, released a statement Tuesday in response to the Auditor General's findings.
He said the government is in the process of modernizing the contracting process to address issues found in previous audits and reviews.
'We also expect public servants and departments to operate with the highest standards of integrity when procuring professional services to support their program delivery,' he said.
The statement did not indicate whether any public servants have faced consequences for the oversight shortfalls identified in the report.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Green MLAs want quicker action on glyphosate report
Green MLAs want quicker action on glyphosate report

CBC

time25 minutes ago

  • CBC

Green MLAs want quicker action on glyphosate report

Three and a half years after a report recommended tighter restrictions on glyphosate spraying, some lawmakers say the pace of implementation has been too slow. "It's clear that not a lot of work was done on it in that time," Green MLA Megan Mitton said. "There were some things completed and some things very recently completed, but I would have liked to see more progress." The report by the legislature's committee on climate change and environmental stewardship made a number of recommendations on the future of herbicide spraying in the province. It followed extensive hearings with scientists, foresters, Health Canada researchers, First Nations, industry and the public. The recommendations included larger setbacks from dwellings and watercourses, that N.B. Power phase out aerial glyphosate spraying and an analysis of potential alternatives. In an update to the committee, Christie Ward, the assistant deputy environment minister, said 11 of 20 recommendations have been "completed" to date, while the remaining nine are underway. Some MLAs pointed out, however, that what the department has implemented is not what the initial report actually recommended. "When you went through the recommendations of the committee that were unanimously adopted, you pointed to a number of those recommendations that were marked as completed, which were not implemented as recommended," David Coon told department staff Wednesday. "So essentially you rejected those recommendations." For example, the report called for setbacks from dwellings to increase to one kilometre from 500 metres. Ward said permits for aerial glyphosate spraying issued last year increased setbacks to 500 metres from 155 metres. Instead of the minimum 100-metre setback from watercourses recommended in the report, ground application requirements were moved to 30 metres from 15 metres, and aerial spraying requires a minimum distance of 65 metres. Ward said that the department has spent time trying to understand the intent of the committee's recommendations and to carry out the spirit of them, even those based on a misunderstanding of the regulations that already existed. "These recommendations are complex in some cases, many of them require rigorous scientific review, they also require a baseline of information, so you know where you're starting from and where you need to get to," she said. "There's been a lot of work done in the background to really understand all aspects of the pesticide program." But Mitton said she'd prefer a more direct answer from the department on whether the committee's recommendations have been followed. "When the auditor general has a report, there's a response from the department and then there's an update," she said. "I almost feel like we need a bit more of a formal process, or to bring them in more often, to keep that accountability going because I don't accept some of those answers as a checkmark." Environment Minister Gilles LePage backed up his staff, noting the report, which he helped prepare as an opposition member of the committee, did err at times in its understanding of existing regulations. However, LePage agreed with other comments over the pace of action on the report over the last few years. "In the past six years, I think there was a lack of work on that file, and that's why it's part of my mandate," he said. "I was part of the evolution of pesticides in this province, with the research on this committee, and I take it personally, and we are going to focus on pesticides even more than the previous government." LePage's mandate letter from Premier Susan Holt includes two mentions of herbicide spraying. One is to implement all recommendations from the committee's report. The other is to investigate alternatives to pesticide and herbicide use and "re-evaluate the safety of glyphosate with new and comprehensive data specific to New Brunswick." "We're looking daily and monthly on the impacts of how it's done," he said. "But don't forget, our regulations are very strong and very rigid for application and for use."

GME Earnings: GameStop Reports Mixed Financial Results and 4,710 Bitcoin
GME Earnings: GameStop Reports Mixed Financial Results and 4,710 Bitcoin

Globe and Mail

time28 minutes ago

  • Globe and Mail

GME Earnings: GameStop Reports Mixed Financial Results and 4,710 Bitcoin

GameStop's (GME) share price is down about 5% after the video game retailer reported mixed first-quarter financial results. Confident Investing Starts Here: Easily unpack a company's performance with TipRanks' new KPI Data for smart investment decisions Receive undervalued, market resilient stocks right to your inbox with TipRanks' Smart Value Newsletter The Texas-based company announced earnings per share (EPS) of $0.09, which topped the $0.04 consensus expectation of analysts. However, revenue for the quarter came in at $732.4 million, which was below the consensus Wall Street estimate of $754.2 million. The company also reported an improved operating margin of -1.5%, which was up from -5.7% in the same quarter of 2024. GameStop's free cash flow at the end of the quarter totaled $189.6 million, which was a big improvement from negative -$114.7 million a year earlier. GameStop's profitability. Source: Main Street Data Bitcoin Purchases Along with its financial results, GameStop disclosed that it bought 4,710 Bitcoins (BTC) between May 3 and June 10 of this year. It's not known what the average purchase price of the Bitcoin was. However, GameStop's BTC holdings are currently worth $516.6 million based on the current price of Bitcoin. GameStop announced previously that it planned to begin buying and holding cryptocurrencies, adopting a similar playbook to that of software developer turned serial BTC acquirer Strategy (MSTR). GameStop has said it plans to use its excess cash to make investments in risk assets such as crypto and stocks. The company made its first Bitcoin investment in May of this year. Is GME Stock a Buy? Currently, only one Wall Street analysts offers a rating and price target on GME stock. So instead, we'll look at the stock's three-month performance. As one can see in the chart below, GameStop's share price has gained 33% over the last 12 weeks.

Mooseheads asking city for $1.6M to expand Dartmouth training facility
Mooseheads asking city for $1.6M to expand Dartmouth training facility

CBC

time32 minutes ago

  • CBC

Mooseheads asking city for $1.6M to expand Dartmouth training facility

The Halifax Mooseheads are asking Halifax regional council for up to $1.625 million to expand the training facility they lease at the RBC Centre in Dartmouth. Mooseheads general manager Cam Russell and Elizabeth Powell of architecture firm Fathom Studio outlined plans for a proposed 4,700-square-foot addition at a standing committee meeting on Wednesday. They said the project at the municipally owned centre would benefit both the team and the public. Russell, who has been with the Quebec Maritimes Junior Hockey League organization for 25 years, told the committee the current training facility is challenging to use. "Our gym isn't big enough, we have to work out in two or three different groups," he said. "We have a lounge that only seats three to four players. We don't have a wellness area that would be good for the kids, for their mental health and their well-being." Russell told the committee a state-of-the-art facility would enhance the Mooseheads' ability to attract top talent, putting the team on the same level as NCAA teams, universities and colleges. Russell said the proposed expansion would include a high-performance gym equipped with hockey-specific training gear, a 21-metre turf training track, and a dedicated shooting room for skill development, which he said would be a first in the QMJHL. The plans would also incorporate a sauna, steam room and cold plunge recovery area, a more spacious player lounge and a publicly accessible, barrier-free washroom. The timeline for the project is about six months for the design and eight months for construction, said Powell, the project architect. Russell said the Mooseheads are asking the municipality to fund the construction of the building shell, while the team would cover interior costs and remain the exclusive tenant of the training facility. The Mooseheads' current lease, set to expire next year, costs the team about $45,000 annually, he said. Coun. Patty Cuttell said while she understood the need for the expansion, she had concerns about the municipality paying for a space for the exclusive use of a privately owned franchise. "If we build this, what's the cost recovery through the lease?" she asked. Maggie MacDonald, the executive director of parks and recreation, recommended a staff report to examine the financial implications, the assessment of public good, and potential cost recovery mechanisms. Cuttell said she would be willing to ask for a staff report once she examined the motion in greater detail.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store