Ashram to Badarpur: Why this 8 km Delhi stretch takes 45 mins instead of 15; Key reasons behind Mathura Road chaos
What's causing the chaos?
This stretch, part of National Highway 2 (NH2), carries over four lakh vehicles daily, rising to five lakh on Mondays and Fridays. After 9 pm, it's opened to heavy trucks entering or leaving Delhi, making things worse. The major reason behind the jams? Poor road design, with multiple cuts between the two carriageways causing heavy blockages.
Key trouble spots
Even before you leave Ashram, traffic starts to pile up. The underpass meant to ease flow is often blocked due to vehicles turning towards Lajpat Nagar and Sarai Kale Khan. Further down, junctions at Okhla, Mata Mandir Marg, CRRI, and Apollo Hospital remain choked, especially the one near the hospital, with traffic coming from all sides.
Failed fixes and long waits
Delhi Traffic Police tried easing the mess by closing cuts like the one at Madanpur Khadar. But cars are now forced to take long U-turns at flyovers, offering only minor relief. At the Okhla-New Friends Colony crossing, vehicles from the Modi Mill side and Jullena end up criss-crossing, leading to long queues even during green signals.
A TOI reporter noted that handcarts, wrongly parked vehicles, and fuel queues also eat up road space. CRRI expert S Velmurugan pointed out that the road lacks proper merging lanes and width consistency, making matters worse.
Live Events
A glimmer of hope?
The National Highways Authority of India (NHAI) may soon take over the road and turn it into a signal-free corridor, as per TOI. While Public Works Department (PWD) had proposed flyovers and underpasses back in 2017, the plan never materialised.
Experts suggest that just removing traffic lights won't help. A well-planned elevated road, with proper entry and exit points, may finally bring relief. CRRI scientist Nasim Akhtar added that flyovers at Okhla Mor and synchronised traffic signals are urgently needed.
Until a long-term fix arrives, however, Delhiites will continue to face this exhausting drive daily.
Inputs from TOI

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
16 hours ago
- Time of India
Metro to charge extra for oversized luggage
Kolkata: Metro Railway will allow passengers to carry suitcases — mostly within standard size limits — from all stations in its network to the airport station. However, those carrying large or oversized luggage will have to pay extra, senior officials said. "We don't want to ruin anybody's journey. People headed to catch a flight usually don't carry multiple suitcases or bags if they choose to travel on the metro to the airport. No one will be stopped in any of the stations across the three corridors (Blue, Green, and Yellow Lines) if they are riding to or from the airport metro station. The idea is to make their journeys seamless," a senior official of Metro, which runs the city's rapid transit network, told TOI, adding that if someone has multiple bags or oversized baggage, he or she will be charged a fee. Officials explained that the eight-car rakes used in Kolkata Metro don't have dedicated storage space like those operating in underground transit systems or semi-speed corridors abroad. The luggage fee will be charged to dissuade people from trooping in with extra and oversized suitcases, they said. You Can Also Check: Kolkata AQI | Weather in Kolkata | Bank Holidays in Kolkata | Public Holidays in Kolkata | Gold Rates Today in Kolkata | Silver Rates Today in Kolkata Two days ago, a Bengaluru commuter raised questions over Namma Metro's policy of charging him for oversized luggage, claiming he was asked to pay Rs 30 for carrying a suitcase during his ride. The post, shared on X, sparked a wider discussion on whether the fee is justified. Metro Railway officials said passengers carrying one or two suitcases of the usual sizes (around 18 by 24 inches) would be given a pass after scanning. Fees would be clamped only on those carrying more. "We are still working on the nitty-gritty of charges, based on the number and sizes of the luggage being carried. We shall have to watch commuter behaviour for a few days before fixing the rules," a senior Metro official said. Metro Railway slackened its luggage rules last year when East-West Metro's Esplanade-Howrah Maidan section was opened. Metro Railway general manager P Uday Kumar Reddy had then said that the rules were being changed for the sake of passengers alighting from trains at Howrah station. Most domestic airlines allow flyers to carry suitcases up to 15 kg as checked-in luggage and up to 7 kg as cabin baggage. Trains, too, have a luggage weight limit, but it's seldom enforced. Earlier, security personnel at metro stations would bar passengers from carrying suitcases on trains. The "prohibition" has been gradually lifted, even though there was no official announcement. With the airport-metro launch, Kolkata will join Mumbai, Delhi, Lucknow, and Chennai, where domestic flyers may avoid expensive cabs to travel to the airport. They can zip between Esplanade and Airport stations in 30 minutes for just Rs 50. Tickets from the airport metro station to those between Chandni Chowk and Tollygunge will cost Rs 40, and to those between Kudghat and Sahid Khudiram stations, Rs 45. Stay updated with the latest local news from your city on Times of India (TOI). Check upcoming bank holidays , public holidays , and current gold rates and silver prices in your area.


Time of India
16 hours ago
- Time of India
Jog Falls gleams as water from Linganamakki dam is released
Shivamogga: Over 15,000 cusecs of water were released into the Sharavathi River from the Linganamakki dam, bringing Jog Falls in Shivamogga to life on Tuesday. The discharged water surged downstream, reaching the falls within two hours and transforming it into a breathtaking spectacle. With the reservoir nearing full capacity, authorities took proactive measures to release excess water, ensuring dam safety, while revitalising one of Karnataka's most stunning natural wonders. The Linganamakki reservoir, situated near Kargal town in Sagar taluk amidst the lush greenery of the Sharavathi calley, plays a crucial role in the Sharavathi River Power Project. This project significantly contributes to the state's total electricity consumption, featuring numerous power generation plants downstream up to Gerusoppa, the final plant after Jog Falls. The Linganamakki Dam has a total storage capacity of 151.64 TMC and a height of 1,819 feet. Currently, the dam is filled to 1,816.2 feet and 142.3 feet (93.8% full). On Tuesday morning, with an inflow of 48,393 cusecs, authorities released 15,000 cusecs of water by lifting 11 sluice gates. The outflow created a wonder in the valley and subsequently enhanced the beauty of Jog Falls. Last year also, the falls also mesmerised tourists. Following the water release, an alert was issued to residents along the riverbank in Honnavar, Uttara Kannada district. The district administration warned of potential flooding in low-lying areas. The released water will flow through Kargal to Gerusoppa Dam in Honnavar, where it will be used for power generation before being released into the Arabian Sea. HR Ramesh, hydroelectric plant chief at Linganamakki, said the dam requires 25 TMC of water to fill up to the brim. It crossed the 1,816-ft mark. To balance the reservoir, keeping the possibilities of good rain, we are releasing water. The downstream people cannot worry about this amount of water. "We have to discharge up to 75,000 cusecs of water without worries. The downstream flowing water will reach the Gerusoppa power plant beneath the Jog Falls. We try to store the water there, and excess water will be moved out from the Gerusoppa to reach the Arabian Sea at Honnavar taluk," he said. M Madesh, civil chief of the unit, informed that the department could not assure the same quantity of water flowing continuously. "If the inflow reduces, the gates will be closed at any time. The official release activities started on Tuesday," he said. Stay updated with the latest local news from your city on Times of India (TOI). Check upcoming bank holidays , public holidays , and current gold rates and silver prices in your area.


Time of India
19 hours ago
- Time of India
Trains passingthrough Nashik city cancelled or postponed
Nashik: Most trains passing through Nashik on Tuesday were either cancelled or delayed due to heavy rain and waterlogging in Mumbai over the past two days. The Panchavati Express, which on Monday was running half an hour late, did not reach Chhatrapati Shivaji Terminus (CST) on Tuesday as the train was halted at Ghatkopar. Senior officials of Nashik Road railway station said numerous trains were cancelled or had their routes changed. Among these, the Mumbai Dhule Express, which starts from Mumbai, was cancelled. The Dhule Mumbai Express scheduled for Wednesday was also cancelled. The Mumbai to Jalna Vande Bharat Express was cancelled from Mumbai on Tuesday, leading to cancellation of Wednesday's Jalna to Mumbai Vande Bharat train. The Mumbai to Hingoli Janshatabdi train from Mumbai was cancelled, causing the Mumbai-bound train from Hingoli to remain cancelled. The Mumbai to Nagpur Sevagram Express was also cancelled. Officials said helpdesks were set up across the railway station to provide information about long-route trains. Stay updated with the latest local news from your city on Times of India (TOI). Check upcoming bank holidays , public holidays , and current gold rates and silver prices in your area.