logo
Jellyfish-hit French nuclear site faces delayed restart

Jellyfish-hit French nuclear site faces delayed restart

The Advertiser2 days ago
Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems.
The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea.
Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total.
The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested.
The original plan was for all four to restart on Tuesday.
EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems.
Its data showed the first reactor had still not restarted by midday on Tuesday.
The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said.
Four reactors were taken offline while the other two were already undergoing planned maintenance.
They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani.
The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said.
Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters.
This is not the first time that jellyfish have disrupted nuclear plants.
Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993.
Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems.
The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea.
Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total.
The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested.
The original plan was for all four to restart on Tuesday.
EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems.
Its data showed the first reactor had still not restarted by midday on Tuesday.
The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said.
Four reactors were taken offline while the other two were already undergoing planned maintenance.
They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani.
The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said.
Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters.
This is not the first time that jellyfish have disrupted nuclear plants.
Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993.
Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems.
The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea.
Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total.
The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested.
The original plan was for all four to restart on Tuesday.
EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems.
Its data showed the first reactor had still not restarted by midday on Tuesday.
The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said.
Four reactors were taken offline while the other two were already undergoing planned maintenance.
They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani.
The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said.
Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters.
This is not the first time that jellyfish have disrupted nuclear plants.
Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993.
Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems.
The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea.
Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total.
The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested.
The original plan was for all four to restart on Tuesday.
EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems.
Its data showed the first reactor had still not restarted by midday on Tuesday.
The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said.
Four reactors were taken offline while the other two were already undergoing planned maintenance.
They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani.
The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said.
Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters.
This is not the first time that jellyfish have disrupted nuclear plants.
Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Nuclear power plant shuts down due to jellyfish invasion
Nuclear power plant shuts down due to jellyfish invasion

Perth Now

time2 days ago

  • Perth Now

Nuclear power plant shuts down due to jellyfish invasion

One of Europe's biggest nuclear power stations was forced to shut down this week after an unexpected invasion - by jellyfish. The Gravelines nuclear power plant in northern France, located between Dunkirk and Calais, was fully shut down on Monday (12.08.25) after a 'massive and unpredictable' swarm of jellyfish clogged its sea water intake system. The plant, which relies on water from the North Sea to cool its reactors, saw four of its six units automatically shut down just before midnight when filter drums became overwhelmed. A fifth reactor followed hours later. Each unit at Gravelines produces 900 megawatts of power, making the disruption a significant hit to the region's energy supply. Fortunately, French energy giant EDF confirmed that the incident posed no threat to staff, the environment, or the facility itself. The jellyfish didn't damage the pumps, but they will need to be removed and the filters cleaned before the reactors can be restarted. This isn't the first time the Gravelines area has seen jellyfish swarms, with similar events washing up on nearby beaches in recent years. Experts say the increase is likely due to rising sea temperatures caused by global warming, as well as the spread of invasive species. Derek Wright, a marine biology consultant with the US National Oceanic and Atmospheric Administration, explained: 'Jellyfish breed faster when water is warmer, and because areas like the North Sea are becoming warmer, the reproductive window is getting wider and wider. Jellyfish can also hitch rides on tanker ships, entering ballast tanks in one port and being pumped out halfway across the globe.' He added: 'Everyone talks about nuclear being clean, but we don't think about the unintended consequences of heat pollution.'

Jellyfish-hit French nuclear site faces delayed restart
Jellyfish-hit French nuclear site faces delayed restart

The Advertiser

time2 days ago

  • The Advertiser

Jellyfish-hit French nuclear site faces delayed restart

Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems. The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea. Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total. The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested. The original plan was for all four to restart on Tuesday. EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems. Its data showed the first reactor had still not restarted by midday on Tuesday. The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said. Four reactors were taken offline while the other two were already undergoing planned maintenance. They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani. The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said. Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters. This is not the first time that jellyfish have disrupted nuclear plants. Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993. Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems. The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea. Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total. The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested. The original plan was for all four to restart on Tuesday. EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems. Its data showed the first reactor had still not restarted by midday on Tuesday. The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said. Four reactors were taken offline while the other two were already undergoing planned maintenance. They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani. The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said. Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters. This is not the first time that jellyfish have disrupted nuclear plants. Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993. Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems. The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea. Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total. The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested. The original plan was for all four to restart on Tuesday. EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems. Its data showed the first reactor had still not restarted by midday on Tuesday. The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said. Four reactors were taken offline while the other two were already undergoing planned maintenance. They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani. The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said. Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters. This is not the first time that jellyfish have disrupted nuclear plants. Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993. Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems. The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea. Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total. The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested. The original plan was for all four to restart on Tuesday. EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems. Its data showed the first reactor had still not restarted by midday on Tuesday. The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said. Four reactors were taken offline while the other two were already undergoing planned maintenance. They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani. The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said. Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters. This is not the first time that jellyfish have disrupted nuclear plants. Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993.

Jellyfish-hit French nuclear site faces delayed restart
Jellyfish-hit French nuclear site faces delayed restart

Perth Now

time2 days ago

  • Perth Now

Jellyfish-hit French nuclear site faces delayed restart

Four reactors at France's Gravelines nuclear plant will return to operation throughout the week, slightly later than initially planned, EDF data indicates after they were forced offline by a swarm of jellyfish in the cooling systems. The plant in northern France is one of the largest in the country and is cooled from a canal connected to the North Sea. Its six units produce 900 megawatts of power each, or 5.4 gigawatts in total. The first reactor, unit 6, is expected to restart on Tuesday, and then one reactor is expected to come back online each day until all four have returned to service on Friday, EDF data suggested. The original plan was for all four to restart on Tuesday. EDF did not give a reason for the delay, although France is in the midst of a heatwave that is creating challenges for many nuclear cooling systems. Its data showed the first reactor had still not restarted by midday on Tuesday. The whole Gravelines plant was temporarily halted on Monday after a "massive and unpredictable" swarm of jellyfish got into the cooling systems, EDF said. Four reactors were taken offline while the other two were already undergoing planned maintenance. They were English Barrel jellyfish, a native, non-stinging species that can grow up to 90 centimetres across, said citizen scientist Aäron Fabrice de Kisangani. The current would have pushed the jellyfish from the harbour and into the canal towards the nuclear plant, and then they would not have been able to escape the suction of the water coolant system, pulling them into the filters, Aaron said. Higher average sea temperatures this year could cause larger jellyfish blooms, he added, noting that jellyfish were staying longer in the North Sea due to mild autumns and winters. This is not the first time that jellyfish have disrupted nuclear plants. Scotland's Torness faced similar problems in 2011 while Gravelines itself was disrupted in 1993.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store