logo
Pelubang water plant upgrading ahead of schedule

Pelubang water plant upgrading ahead of schedule

ALOR STAR: Upgrading work at the Pelubang Water Treatment Plant (WTP) may be completed ahead of schedule, said contractor Bina Darul Aman Bhd (BDB).
Its group executive director, Raja Shahreen Raja Othman, said the RM431 million project was 62.5 per cent complete, slightly ahead of the targeted 62.3 per cent, and might be completed ahead of the extension period that was granted.
"Once operational, the facility is expected to improve access to treated water for residents in Kubang Pasu and Kota Setar.
"If we factor this into days, it should be an estimated 43 days (ahead of schedule)," he said during a press conference in conjunction with the company's 30th annual grand meeting today.
Raja Shahreen stated that timely delivery remained a priority but noted that the project faced several non-construction challenges.
"In terms of timing, like it or not, this is something we have to meet, but for us to continue progressing smoothly, we need cooperation from other stakeholders as well.
"This isn't just about digging the ground. There are issues involving land acquisition, permits and existing infrastructure such as roads and private properties," he said.
Raja Shahreen said BDB was confident of delivering the project on time.
"We are committed. We have the financial strength and technical capabilities, but we must also take these external factors into account," he added.
The Pelubang WTP upgrading project aims to almost double the plant's capacity, from the current 247 million litres daily to 457 million litres once completed.
Last year, the media reported that state Public Works, Natural Resources, Water Supply, Water Resources and Environment Committee chairman Mohamad Yusuf @ Munir Zakaria said the Pelubang WTP had been granted an Extension of Time (EOT) until Dec 21, 2025, due to earlier technical issues.
On whether BDB was open to rescuing other delayed water treatment plant projects in Kedah, Raja Shahreen said the company was ready to step in if needed.
"We are prepared to assist with stalled projects. Financially, we are stable, and we possess the technical expertise to bring such projects back on track," he said.
Meanwhile, Raja Shahreen said BDB recorded a pre-tax profit of RM4.51 million on revenue of RM294.7 million for 2024, compared to a RM14.47 million pre-tax profit from RM313.1 million revenue recorded in the previous year.
"Despite the softer financial performance, the group remains optimistic about long-term growth prospects," he said.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Sibu's RM291m water treatment upgrade 8.85pc ahead of schedule, set to double regional water capacity, says Sarawak minister
Sibu's RM291m water treatment upgrade 8.85pc ahead of schedule, set to double regional water capacity, says Sarawak minister

Malay Mail

time2 days ago

  • Malay Mail

Sibu's RM291m water treatment upgrade 8.85pc ahead of schedule, set to double regional water capacity, says Sarawak minister

SIBU, July 30 — The Salim Water Treatment Plant (WTP) upgrading project here is progressing smoothly, with 8.85 per cent advancement ahead of original schedule, said Utility and Telecommunication Minister Datuk Seri Julaihi Narawi. Implemented by Sibu Water Board (SWB), the project has reached 25.48 per cent physical progress compared to the original target of 16.63 per cent. 'Based on my observation of the works at the site today, I am pleased that everything is progressing smoothly. 'This is a very good sign, reflecting the extraordinary efforts by all parties involved,' he told reporters during a site visit here yesterday. The project, which costs RM291.4 million (with the main contract valued at RM269.1 million), aims to double the water production capacity of the Salim plant from 150 million litres per day (MLD) to 300 MLD. Julaihi said once completed, Sibu's total water supply capacity ― including the Bukit Lima Plant (45 MLD) will reach 345 MLD, providing a healthy reserve margin not just for Sibu but also surrounding areas. 'This upgrade will meet the increasing demand for clean water in Sibu and nearby regions,' he said. He noted that 120 workers are currently involved in the on-site works to ensure the project remains on track. Julaihi also expressed appreciation to SWB, project engineers and all stakeholders involved in the project's implementation. 'I hope this encouraging momentum will be maintained until the project is completed next year,' he added. — The Borneo Post

Julaihi: Sibu's RM291 mln water treatment upgrade ahead of schedule
Julaihi: Sibu's RM291 mln water treatment upgrade ahead of schedule

Borneo Post

time2 days ago

  • Borneo Post

Julaihi: Sibu's RM291 mln water treatment upgrade ahead of schedule

Julaihi (third right) and others inspect the progress of upgrading works in Sibu. SIBU (July 30): The Salim Water Treatment Plant (WTP) upgrading project here is progressing smoothly, with 8.85 per cent advancement ahead of original schedule, said Utility and Telecommunication Minister Dato Sri Julaihi Narawi. Implemented by Sibu Water Board (SWB), the project has reached 25.48 per cent physical progress compared to the original target of 16.63 per cent. 'Based on my observation of the works at the site today, I am pleased that everything is progressing smoothly. 'This is a very good sign, reflecting the extraordinary efforts by all parties involved,' he told reporters during a site visit here yesterday. The project, which costs RM291.4 million (with the main contract valued at RM269.1 million), aims to double the water production capacity of the Salim plant from 150 million litres per day (MLD) to 300 MLD. Julaihi said once completed, Sibu's total water supply capacity ― including the Bukit Lima Plant (45 MLD) will reach 345 MLD, providing a healthy reserve margin not just for Sibu but also surrounding areas. 'This upgrade will meet the increasing demand for clean water in Sibu and nearby regions,' he said. He noted that 120 workers are currently involved in the on-site works to ensure the project remains on track. Julaihi also expressed appreciation to SWB, project engineers and all stakeholders involved in the project's implementation. 'I hope this encouraging momentum will be maintained until the project is completed next year,' he added. Julaihi Narawi lead Salim Water Treatment Plant Sibu Water Board

Sibu's RM291 mln water treatment upgrade ahead of schedule ―Julaihi
Sibu's RM291 mln water treatment upgrade ahead of schedule ―Julaihi

Borneo Post

time2 days ago

  • Borneo Post

Sibu's RM291 mln water treatment upgrade ahead of schedule ―Julaihi

SIBU (July 30): The Salim Water Treatment Plant (WTP) upgrading project here is progressing smoothly, with 8.85 per cent advancement ahead of original schedule, said Utility and Telecommunication Minister Dato Sri Julaihi Narawi. Implemented by Sibu Water Board (SWB), the project has reached 25.48 per cent physical progress compared to the original target of 16.63 per cent. 'Based on my observation of the works at the site today, I am pleased that everything is progressing smoothly. 'This is a very good sign, reflecting the extraordinary efforts by all parties involved,' he told reporters during a site visit here yesterday. The project, which costs RM291.4 million (with the main contract valued at RM269.1 million), aims to double the water production capacity of the Salim plant from 150 million litres per day (MLD) to 300 MLD. Julaihi said once completed, Sibu's total water supply capacity ― including the Bukit Lima Plant (45 MLD) will reach 345 MLD, providing a healthy reserve margin not just for Sibu but also surrounding areas. 'This upgrade will meet the increasing demand for clean water in Sibu and nearby regions,' he said. He noted that 120 workers are currently involved in the on-site works to ensure the project remains on track. Julaihi also expressed appreciation to SWB, project engineers and all stakeholders involved in the project's implementation. 'I hope this encouraging momentum will be maintained until the project is completed next year,' he added.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store