ERCOT approves $54 million plan to move CenterPoint's mobile generators to San Antonio

ERCOT approves $54 million plan to move CenterPoint's mobile generators to San Antonio

Yahoo25-02-2025
Texas' main grid operator on Tuesday approved a $54 million plan to replace two aging natural gas-powered plants near San Antonio with the massive mobile generators that CenterPoint Energy came under fire for not deploying in the wake of Hurricane Beryl in July.
Under the plan, 15 mobile generators currently leased by CenterPoint will be moved from Houston to San Antonio this summer. Customers across the state grid will pay the estimated $54 million cost to move, connect and operate the diesel-fueled generators.
The Electric Reliability Council of Texas board unanimously approved the agreement on Tuesday after San Antonio's municipal utility, CPS Energy, said in March that it planned to retire three of its gas-powered units at the Braunig Power Station this year. Each of those units is roughly 60 years old — decades older than gas-powered plants are typically built to last.
ERCOT said that the loss of those units, which sit near a problem area in the state's transmission infrastructure, would increase the risks of power outages across the grid. Transmission capacity has not kept up with an increasing demand for power in North Texas, causing a bottleneck in the San Antonio area where the risk of overloaded lines and widespread outages increase when wind and solar power from South Texas come pouring in.
In December, ERCOT agreed to reimburse the utility $50 million to keep one of the three units, Braunig 3, running.
Tuesday's decision allows the other two units, Braunig 1 and 2, to be retired this year. Their capacity will be replaced by CenterPoint's large mobile generators, each of which provide around 30 megawatts of generation. (ERCOT estimates that one megawatt can power around 250 homes.)
'This is a solution to bridge that gap, to lower that chance of load shed,' or rolling outages, Bill Flores, chair of the ERCOT Board of Directors, said Tuesday. 'Load shed has a severe cost. We're trying to avoid that, but you have to spend money, essentially, for insurance to avoid that.'
CPS Energy, San Antonio's utility, is working on expanding transmission infrastructure to address the bottleneck, but that project will take years to complete. State regulators and lawmakers are also focused on how to build out transmission to address increasing demand for power across the state.
CenterPoint committed to releasing the mobile generators to ERCOT for two years, during which ERCOT could deploy the generators during grid emergencies. ERCOT said it would continue to evaluate updates to transmission infrastructure that could allow it to end its lease of the generators sooner.
ERCOT's analysis showed that taking on the generators was more cost-effective than maintaining the power plants, which would cost $59 million. The agency sought out alternative proposals to replace the plants, and rejected the only plan it received — a battery storage project — for failing to meet its requirements.
Flores said that the plan would increase Texans' average monthly electricity bills by 0.4% — a fraction compared to the costs of a widespread outage due to a transmission overload. ERCOT noted that the actual costs of the plan could end up being higher than estimated.
'$54 million is a boatload of money,' Flores said, 'but it's four tenths of a percent on an average bill, and that is offsetting a much higher cost of a load shed event.'
CenterPoint came under fire by state lawmakers and the public for not deploying the generators in its response to Hurricane Beryl, which left millions in Houston in the dark for days.
The Public Utility Commission had allowed CenterPoint to increase its customers' electricity bills to help pay the $800 million needed to lease and profit from the massive generators.
But CenterPoint did not use the generators in its Beryl response, leading to calls out of the Legislature for regulators to bar the company from passing the costs of the generators onto its customers.
CenterPoint defended its investment, saying the generators — which could not be easily moved to critical facilities needing power — were meant to help in a situation like Winter Storm Uri in 2021, when days of freezing weather caused a statewide power generation failure, rather than outages caused when Beryl sent trees and limbs crashing onto thousands of power lines.
In agreeing to release the generators, CenterPoint will forgo the profits it would have earned on them. Jason Ryan, executive vice president of regulatory services and government affairs at CenterPoint, said the company will ask the PUC to stop charging its customers for the generators.
Some grid experts criticized ERCOT's plan as both unnecessarily expensive and insufficient.
Instead of spending tens of millions to maintain one aging power plant and operate the massive generators, energy consultant Doug Lewin argued that targeted investments in battery storage near San Antonio would provide greater reliability at lower costs.
'We're talking about way more than $100 million in ratepayer money — all to maintain an inadequate status quo for two years, ultimately with nothing to show for it,' he wrote in his newsletter, Texas Energy and Power. 'Arbitrarily building a portfolio of zombie power plants — at huge expense to ratepayers — when better alternatives are clearly and obviously available, is, to put it mildly, not something ERCOT should be doing.'
The plan also raised concerns among regulators that the diesel-fueled generators would not qualify for needed air emissions permits. ERCOT was working with the Texas Commission on Environmental Quality to address the issue, such as by securing an agreement for more discretionary enforcement.
'This is a fairly limited use case that we expect may justify some sort of special permitting approach,' Nathan Bigbee, ERCOT's chief regulatory counsel, said Tuesday.
We can't wait to welcome you to the 15th annual Texas Tribune Festival, Texas' breakout ideas and politics event happening Nov. 13–15 in downtown Austin. Step inside the conversations shaping the future of education, the economy, health care, energy, technology, public safety, culture, the arts and so much more.
Hear from our CEO, Sonal Shah, on TribFest 2025.
TribFest 2025 is presented by JPMorganChase.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Five candidates seek Oklahoma Lieutenant Governor post
Five candidates seek Oklahoma Lieutenant Governor post

Yahoo

time3 hours ago

  • Yahoo

Five candidates seek Oklahoma Lieutenant Governor post

The Oklahoma State Capitol building is pictured. (Photo by Kyle Phillips/For Oklahoma Voice) OKLAHOMA CITY – Four Republicans and one Democrat have filed paperwork indicating they are running for lieutenant governor. Republican Lt. Gov. Matt Pinnell is serving his second term and can't seek reelection to the post. Republicans seeking the post are State Auditor and Inspector Cindy Byrd, state Sen. Darrell Weaver, state Rep. J.J. Humphrey and political newcomer Victor Flores. Kelly Forbes of Oklahoma City is the sole Democrat thus far to file paperwork with the Oklahoma Ethics Commission indicating an intention to run. Byrd, 52, of Coalgate, wants to focus on promoting tourism and the music industry. She said the lieutenant governor sits on a lot of boards and commissions that drive economic development involving millions of dollars. Her skill set makes her ready to start on the first day, she said. About 80% of every tax dollar is spent on education and health care, but the state ranks at the bottom in outcomes, she said. She wants to do a deep dive into the reasons and assist the next governor on making improvements, she said. Weaver, 63, of Moore, is the former head of the Oklahoma State Bureau of Dangerous Drugs Control, an agency in which held various positions. He and his wife operate Weaver clinics, which provide medical care. Weaver said his relationships in the Capitol and law enforcement and business background make him a good fit for the office. He said his background as a pilot has taught him about all of the opportunities the state has in the aerospace industry. Flores, 47, of Edmond is a small business owner and a partner with a national accounting firm. He would like to improve the relationships between the tribes, state agencies and the executive branch. Flores said he wants to focus on making sure economic development is happening statewide, especially in rural areas. Humphrey, 59, of Lane, is a rancher and retired probation and parole officer. He said the Oklahoma House leadership has shut down his efforts to expose problems at the Oklahoma Department of Corrections and Oklahoma Department of Human Services. 'I hope to use the lieutenant governor's position to make the state aware of these things and expose corruption,' he said. He also wants to improve the state's educational system and broadband access in rural Oklahoma so businesses can grow. Forbes could not be reached for comment Wednesday. The filing period is April 1-3 at the state Capitol for federal, state, legislative and judicial offices. The primary election is June 16, followed by a Aug. 25, 2026, runoff. The general election is Nov. 3, 2026. SUBSCRIBE: GET THE MORNING HEADLINES DELIVERED TO YOUR INBOX SUPPORT: YOU MAKE OUR WORK POSSIBLE Solve the daily Crossword

Texas shows how Trump's anti-green moves threaten a red economy
Texas shows how Trump's anti-green moves threaten a red economy

Los Angeles Times

time5 hours ago

  • Los Angeles Times

Texas shows how Trump's anti-green moves threaten a red economy

Deep-red Texas needs to build power plants at an astonishing speed and scale to keep its economy humming. President Donald Trump just made that much harder. So many data centers, crypto-mining operations and factories are planned for the Lone Star State that its peak electricity demand is poised to surge in the next five years — perhaps even double. The vast majority of new power capacity planned there would utilize the sun, the wind or batteries. But Trump's One Big Beautiful Bill kills tax credits for renewable projects starting in 2028, making them more expensive to build. Other states face the same problem, as power demand nationwide is expected to soar after decades of minimal growth. But it's particularly acute in Texas, which has been rapidly adding renewable energy while it struggles to build gas-burning power plants. The state's bustling economy will be threatened if it can't add more electricity. Texas' gross domestic product jumped 51% from 2020 through 2024 — compared to 37% for the country as a whole — fueled by cheap power. 'We're in an energy crunch,' said Joshua Rhodes, an electricity expert and research scientist at the University of Texas at Austin. 'We should be doubling down on everything we can build right now. Making things more expensive is antithetical to that.' Clean power is expected to continue growing across the US, despite Trump's tax and spending bill. But the legislation will cut the amount installed. BloombergNEF, for example, forecasts that annual deployment of new solar, wind and energy storage facilities in 2035 will be 23% lower than it would have been without the bill. Oil and gas get most of the attention, but green energy has been the Texas economic boom's secret ingredient. All but 6% of new electric capacity added to the state's grid since 2020 has come from renewables or batteries. With vast, windswept plains, Texas has long been the top market for wind power. Solar surged as panel prices declined almost 50% in the past five years. It certainly helps that renewables are fast and relatively easy to install, compared to fossil fuel power plants that take years to build. Texas now has more clean energy and storage systems than any other state, supplying more than 30% of its electricity. Texas enjoys relatively low electricity prices — which have become a magnet for energy-hungry facilities like data centers. The state's power grid manager, known as Ercot, forecasts peak demand to approach 150 gigawatts by 2030, up from a record of 85.5 gigawatts in 2023. Transmission service providers, including utility companies, say demand could get even higher, topping 200 gigawatts in 2030. For a sense of scale, a gigawatt is the output of one commercial nuclear reactor and can power about 200,000 Texas homes. The state now has about 178 gigawatts of installed generating or storage capacity, but not all of that electricity is available at any given moment. Gas and coal plants need to be taken offline for maintenance, batteries must recharge after use, and the output of solar and wind facilities varies with the weather and time of day. There always needs to be a comfortable cushion between installed capacity and actual demand. Texas' grid is largely cut off from the rest of the country, so meeting expected demand growth will require adding lots of generation within the state — quickly. The state's clean-energy boom had been expected to continue. But with Trump's budget bill, wind and solar projects that go into service after the start of 2028 will no longer qualify for key federal incentives, unless they begin construction by July 5, 2026. Less-profitable projects will likely be cancelled. A White House spokesman said that depending on 'unreliable energy sources' could lead to reliability issues. The new policies will prompt developers to focus instead on domestically produced coal, gas and nuclear energy, Deputy Press Secretary Harrison Fields said in an emailed statement. Led by Republican Governor Greg Abbott, Texas officials have tried to encourage construction of power plants burning natural gas. They've even set aside $5 billion of public money to offer gas plant developers low-interest loans. But projects keep dropping out of the loan program due to cost uncertainties and problems procuring equipment. Indeed, there's currently a global manufacturing shortage of the turbines used in gas-fired plants, with a five-year backlog for new orders. Anyone planning a new gas plant faces a long wait for the gear. A spokeswoman for Ercot said the state continues to see new power-generating projects being proposed to address growing demand. But any obstacle to new supplies poses a threat to the Texas economy, which would be the world's eighth-largest if the state were considered as a country. Curtailing renewables would mean less electricity added to the grid. The renewable plants that do get built will cost more than before the One Big Beautiful Bill, driving up prices. Residential ratepayers in Texas could pay about 23% more in 2035 than they would have if the bill hadn't upended the market, while industrial customers could see bills surge 54%, according to Energy Innovation Policy & Technology, an energy and climate think tank. Higher utility bills for consumers will mean less money to spend elsewhere every month. 'We will severely restrict economic growth,' said Doug Lewin, a Texas energy expert and president of Stoic Energy Consulting. 'Because we can't grow without energy.' Wade, Malik and Sanchez write for Bloomberg. Mark Chediak and Jennifer A. Dlouhy contributed.

Texas AG Paxton Books A Win: $9.5M Settlement For Hiding Hotel Fees
Texas AG Paxton Books A Win: $9.5M Settlement For Hiding Hotel Fees

Yahoo

time9 hours ago

  • Yahoo

Texas AG Paxton Books A Win: $9.5M Settlement For Hiding Hotel Fees

Texas Attorney General Ken Paxton has secured a $9.5 million settlement with Booking Holdings Inc. for hiding mandatory fees from consumers. The agreement marks the largest state recovery against any hotel or travel agency for 'junk fee' practices. The settlement addresses deceptive pricing tactics that misled Texas consumers and gave Booking unfair advantages over transparent competitors, according to a press release from Paxton's office. Paxton's lawsuit accused and of enticing customers with artificially low room rates. The company allegedly buried mandatory fees within 'Taxes and Fees' line items at checkout. 'Deceiving Texans by hiding fees is both a deeply unethical business practice and a violation of the law,' said Paxton. 'Yet, that's exactly what Booking chose to do, and now it's time for the company to pay for their unlawful actions.' The settlement requires Booking to disclose all fees upfront when displaying hotel room prices. This change allows consumers to compare actual costs across platforms efficiently. 'I will always stand up for Texas consumers and ensure that corporations are fully complying with state law,' Paxton continued. 'Texans deserve transparency when looking at prices, and there will be accountability for any company that chooses to unlawfully mislead consumers.' Paxton has previously reached similar agreements with Marriott, Omni, Choice Hotels, and Hilton. His efforts helped spur new federal regulations targeting hidden fees across industries. Solve the daily Crossword

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store