PSDP spending fails to go beyond 40%

PSDP spending fails to go beyond 40%

Express Tribune18-04-2025
Listen to article
The coalition government has so far spent hardly Rs424 billion or less than 40% of the annual downward revised development budget, impacting construction work and cash flows of hundreds of projects, including schemes of the provinces and merged districts of Khyber Pakhtunkhwa.
The only exceptions to lower spending were the projects related to parliamentarians, Azad Jammu & Kashmir, Gilgit-Baltistan and Space & Upper Atmosphere Research Commission (Suparco), showed the official documents.
The official data of the Planning Commission showed that from July through the middle of April (nine and half months), the development expenditures amounted to Rs424 billion or 39% of the annual budget. The downward revised Public Sector Development Programme is worth Rs1.1 trillion, which is spread over 1,071 projects.
Under the Finance Ministry's release strategy, 60% of the annual budget can be spent during the first nine months of this fiscal year. But the spending remained below this threshold by at least Rs260 billion. This is despite the fact that the Planning Commission had authorized Rs890 billion spending during this period but the actual expenditures were far lower than the budget spending strategy and the authorized spending.
When contacted, the Planning Minister Ahsan Iqbal said that compared to the last year, the spending during the nine-month period was still higher by Rs102 billion. He said that the monthly spending in March this year was also higher by Rs27 billion.
However, the details showed that despite being higher than last year's spending; the overall situation was not good, which impacted many projects.
The official documents showed that the already approved Rs1.1 trillion budget is not adequately spent on the development schemes.
According to these documents, the government had allocated Rs276.5 billion for projects in provinces, special areas and merged districts of Khyber Pakhtunkhwa. But the actual spending till April 15th remained at Rs98.5 billion or 36% of the annual allocation.
Within this spending, an amount of Rs56.6 billion was spent on AJK and GB projects, which was equal to 76% of the annual budget and higher than the ceiling.
But on the merged districts of KP only Rs15.8 billion or 23% of its Rs70 billion allocation was spent. These merged districts are adversely affected by the terror attacks and are under-developed but yet it could not get the attention of the Prime Minister.
For the provincial projects, Rs132 billion have been allocated but the spending remains at just Rs26 billion or 20% of the annual allocation.
The Planning Ministry did not respond to a question about the annual allocations for Balochistan projects and the actual spending during the first nine and half months of this fiscal year.
But details showed that there were 200 federally-funded projects going on in Balochistan having a total cost of Rs1.4 trillion. These projects need little over Rs1 trillion more for completion and the government has already allocated Rs130 billion for this fiscal year.
An official of the Planning Commission said that the finance ministry was not releasing the funds despite authorization due to its International Monetary Fund related commitments. But such constraints did not impact spending on the parliamentarians' small schemes.
As against the annual allocation of Rs50 billion, Rs35 billion or 69% of the annual budget has already been spent on the parliamentarians' schemes in this fiscal year.
The Water Resource Ministry's annual budget was Rs170 billion and so far Rs71 billion or 42% of the annual allocation is spent. The Water Resources Ministry has already requested additional Rs60 billion cover for spending the foreign loans on its schemes. But the Planning Commission has so far not been able to provide the cover.
The National Highway Authority's annual budget is Rs161 billion but spending remains at only Rs54 billion or little over one-third of the annual allocation. The Balochistan's project that will get petroleum levy funding is also under the purview of the NHA.
The Power Davison's annual budget is Rs95 billion but the spending is just Rs51 billion or little over half of the annual allocation.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

CDWP clears 15 projects worth Rs518.972bn
CDWP clears 15 projects worth Rs518.972bn

Business Recorder

time42 minutes ago

  • Business Recorder

CDWP clears 15 projects worth Rs518.972bn

ISLAMABAD: The Central Development Working Party (CDWP) cleared a total of 15 different development projects at the cost of Rs518.972 billion, out of these, six projects with a cost of Rs22.487 billion were approved at the CDWP level and nine projects amounting to Rs496.485 billion were recommended to the Executive Committee of the National Economic Council (ECNEC) for final approval. The CDWP met with Federal Minister for Planning, Development and Special Initiatives Ahsan Iqbal in the chair at P-Block Secretariat on Friday. The meeting was attended by Awais Manzur Sumra, Secretary Planning, along with VC PIDE, other members of the Planning Commission, federal secretaries, heads of Provincial Planning and Development (P&D) boards/departments, and senior representatives from relevant federal ministries and provincial governments. CDWP approves eight development projects The agenda focused on development projects across key sectors, including Education and Training, Health, Higher Education, Physical Planning and Housing, Social welfare, Special Areas (AJK and GB) and Transport and Communications. Four projects related to Higher Education sector were approved by the forum after detailed discussion namely, 'Uplifting of Academic and Infrastructure Facilities at Hazara Universality, Mansehra' with the revised cost of Rs2,804.899 million, 'Establishment of Women Sub-Campus at Batkhela, University of Malakand' with the revised cost of Rs1,341.873 million, Allama Muhammad Iqbal Scholarships for Bangladesh, Central Asian and Friendly countries study in Pakistan (HEC)- New worth Rs6,637.088 million and hostels for UET Lahore and Sub-Campuses - New worth Rs3,357.095 million. Expressing concern over the decline in foreign student admissions, the minister emphasised that Pakistan's universities still have the capacity to attract them and should offer more scholarships, particularly targeting students from Central Asia, Africa, and other Global South countries. He underscored that higher education is a form of soft power, and attracting at least 10,000 international students would not only enhance the country's goodwill and image abroad but also increase remittances. The deputy chairman of the Planning Commission directed that a special meeting be convened to review the scholarships policy to encourage greater international enrollment. A project related to Education and Training sector presented in the meeting namely, 'System Transformation Grant (STG)-New' worth Rs10.605 billion refereed to ECNEC for further consideration. Source of financing of the project is GPE Grant (World Bank). The project aims to advance Pakistan's progress towards SDG 4 — inclusive and quality education — by improving access, retention, and quality in the school system. A project related to health sector presented in the meeting namely, 'Jinnah Medical Complex and Research Center (JMC&RC) previously Quaid-e-Azam Health Tower Islamabad-New' worth Rs1,429.150 million was approved by the forum. Two project of physical planning and housing sector presented in the meeting namely, 'Flood Response Emergency Housing Project (Phase III) EIB/GoS Financing' worth Rs42.09 billion were referred to ECNEC for further consideration. The project is proposed to be financed through foreign funding of EIB. It aims to rebuild over 116,000 multi-hazard resilient homes for flood victims in Sindh and provide inclusive infrastructure for vulnerable groups. Another project of physical planning andhousing sector got the approval namely, 'AJK Legislative Assembly Complex' with the revised cost of Rs6,917.11 million. Two projects related to social welfare sector presented in the meeting namely, 'Sindh Coastal Resilience Project (SCRP) – Livelihood AND Community Infrastructure - New' worth Rs30.915 billion was referred to ECNEC for further consideration. The project is proposed to be financed through foreign funding of IFAD. The Sindh Coastal Resilience Project (SCRP) – Livelihood and Community Infrastructure aims to promote inclusive and climate-resilient livelihoods for smallholder farmers, fisherfolk, and disadvantaged groups, including women, youth, and the landless, across 500 villages in Badin, Sujawal, and Thatta. While discussing the project, the deputy chairman of the forum, AhsanIqbal, constituted the formation of a committee under the Secretary of Planning to conduct a detailed review of the project before submission to ECNEC, ensuring that all requirements highlighted by the CDWP forum are fully addressed. Another project of Social Welfare sector presented in the meeting namely, 'Karachi Water & Sewerage Services Improvement Project(KWSSIP) Phase-II' referred to the ECNEC with the revised cost of Rs185.895 billion. This WB-, AIIB-, and EIB-financed initiative will enhance Karachi's water and sewerage systems through infrastructure upgrades, institutional reforms, and capacity building. While reviewing development projects in Sindh, Deputy Chairman Planning Commission and Federal Minister for Planning, Ahsan Iqbal, reaffirmed that Sindh's development initiatives remain a top priority for the federal government. He assured that the federation is fully committed to supporting the province and is making every possible effort to meet its development needs. During the meeting, the Minister emphasized the importance of expediting the implementation of ongoing projects to ensure timely benefits for the people of Sindh. A project related to Special Areas of AJK & GB presented in the meeting namely 'Construction of Road from Pissan to Hoper Nagar (40KM.) (Shahrah–e–Nagar)' referred to the ECNEC with the revised cost of Rs13,764.926 million. Copyright Business Recorder, 2025

G-B to Gwadar: ‘Talent of youth will be linked with process of development'
G-B to Gwadar: ‘Talent of youth will be linked with process of development'

Business Recorder

time2 days ago

  • Business Recorder

G-B to Gwadar: ‘Talent of youth will be linked with process of development'

ISLAMABAD: Federal Minister for Planning, Development and Special Initiatives, Professor Ahsan Iqbal, while addressing the inaugural ceremony of the Uraan Fellowship Programme 2025, said that the exceptional talent of youth from Gilgit-Baltistan to Gwadar will be linked with the process of national development, said a press release. He said that the purpose of this program is to make the youth genuine partners in the country's progress and to nurture their leadership skills to meet future challenges. Professor Iqbal said that under the vision of the prime minister, the central focus of Uraan Pakistan is to equip the youth with modern skills. The greatest strength and capital of Pakistan are its youth, who make up 64 per cent of the population. He said that Pakistan came into being as a result of the unparalleled leadership of Quaid-e-Azam Muhammad Ali Jinnah, but it is thought-provoking that countries which were once behind us have now moved ahead. The Minister for Planning said that peace, political stability, continuity of policies, reforms and commitment to modernization are the key pillars of development. Unfortunately, due to political vendettas, the decision-making process has been affected. He stated that through CPEC, $25 billion of investment came into the country, load-shedding was controlled, and law and order was restored. Professor Iqbal urged the youth to protect themselves from hatred and prejudiced attitudes and to play a positive role in the country's development. He said that in the past year, inflation was brought under control and the Pakistan Stock Exchange crossed the 140,000 points mark — a testament to economic improvement. Pakistan is on the path to a new phase of progress, and just as it proved its defensive superiority over India, it will also surpass it in the economic field. He said that the youth must play a key role in turning the dream of making Pakistan a $3 trillion economy by 2047 into reality. Moreover, students from 131 universities across the country will work for seven days with the Ministry of Planning, where they will gain important insights into the country's economic affairs and development projects. Copyright Business Recorder, 2025

Trade deficit widens 44% in July
Trade deficit widens 44% in July

Express Tribune

time3 days ago

  • Express Tribune

Trade deficit widens 44% in July

Listen to article As Pakistan's trade deficit widened 44% in July due to a sharp rise in imports, Planning Minister Ahsan Iqbal on Tuesday expressed hope that it would be a "temporary dip," likely to be offset by an increase in exports driven by higher imports of raw materials. While launching the first monthly development report for the fiscal year 2025-26, the minister said the benefit of the lowest US tariffs on Pakistan in the region would depend on exporters' ability to seize the opportunity by penetrating foreign markets. The 44% higher trade deficit in July "is a temporary dip and will be offset by the increase in exports" in coming months, Iqbal said, when asked if the sudden jump was linked to the government's policy of opening the economy for foreign competition. The government reduced import tariffs in the budget as part of conditions set by the International Monetary Fund (IMF) and the World Bank. The Pakistan Bureau of Statistics (PBS) reported last week that the trade deficit rose to $2.7 billion, or 44% higher, in July. Authorities said it was too early to assess the impact of trade liberalisation, noting one possible reason for the surge in imports was that importers had delayed consignments to benefit from reduced rates starting in the new fiscal year. Iqbal said the government had revised the initial trade liberalisation plan by lowering duties only on items that could boost exports. He added that macroeconomic stability had strengthened, with exports posting a 17% increase in July, which was a reflection of external sector stability. In July, exports grew by 16.9%, reaching $2.7 billion from $2.3 billion in the same month last year, according to the Planning Commission's monthly report. It added that foreign remittances rose 7.4% last month to $3.2 billion, indicating growing confidence among overseas Pakistanis in the government's economic management and overall stability. When asked about the impact of the US trade deal, under which Pakistan agreed to zero tariffs on over 4,100 tariff lines in exchange for a 19% additional customs duty rate, Iqbal said exporters should capitalise on the lowest tariffs on Pakistan compared to the region. Former US President Donald Trump imposed a 19% additional tariff on Pakistani exports, compared to around 20% for the region, except India which faces a 50% additional tariff. The Pak-US trade deal should not be viewed merely in terms of the number of tariff lines receiving relief, said Dr Imtiaz Ahmad, Pakistan's chief economist, but in the context of a gradual increase in foreign direct investment. The government hopes investors from regional countries will set up operations in Pakistan to export goods to US and EU markets. However, the fine details of the trade deal, including rules of origin, are yet to be finalised. The national development report stated that Pakistan entered the new fiscal year with stronger economic performance, marked by improved fiscal management, a turnaround in the external sector from deficit to surplus, falling inflation, and renewed investor confidence. Despite the IMF's warning of slower global growth and persistent downside risks, Pakistan has achieved macroeconomic stability, said Iqbal. He added that at a time when global uncertainty weighs on developing economies, Pakistan's policy-driven turnaround signals a notable shift in its economic trajectory and a promising start to FY2026. Strong fiscal consolidation reduced the deficit to 5.4% of GDP in FY2025, down from 6.9% the previous year. The external sector posted a $2.1 billion current account surplus, driven by higher exports and record remittances, he said. Iqbal further stated that revised accounts from the Accountant General of Pakistan Revenue (AGPR) showed total development spending in the last fiscal year rose to Rs1.068 trillion, which is a new record. The government had earlier reported Rs1.048 trillion in spending in the fiscal operations data released by the Ministry of Finance last week. The Public Sector Development Programme (PSDP) spending now equals 98% of the total annual development budget. In FY2025, 260 projects were monitored, with 40 of strategic nature evaluated. For FY2025-26, the target is to monitor 251 projects and evaluate 50, he said. Iqbal again criticised the finance ministry's strategy of releasing 40% of the total budget in the last quarter, which he argued leads to wastage and strains budgetary resources. "We are in discussions with the Finance Division to withhold only 30% of the total budget for the last quarter and disburse the rest in the first three quarters," said Iqbal. The finance ministry's current quarterly release strategy allows 15% spending in the first quarter, 20% in the second, 25% in the third, and 40% in the last quarter.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store