PM Modi inaugurates Unit I of Neyveli Uttar Pradesh Power Limited's Ghatampur Thermal Power Project
Prime Minister Narendra Modi on Friday (May 30, 2025) dedicated Unit I of the Ghatampur Thermal Power Project in Kanpur Nagar district of Uttar Pradesh to the nation.
The project, inaugurated by the Prime Minister on Friday, was developed by Neyveli Uttar Pradesh Power Limited (NUPPL), a joint venture of NLC India Limited (51%) and Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL) (49%).
According to a NLCIL press release, the project comprises three supercritical thermal power units of 660 MW each, adding up to a substantial 1,980 MW of installed capacity.
This initiative aims to meet the growing electricity demand in Uttar Pradesh and other States, enhancing energy security, while aligning with the nation's commitment to sustainable and reliable power generation.
The project cost is ₹21,780.94 crore, and the remaining two units of the Ghatampur Thermal Power Project are expected to be commissioned in 2025-26.
A total of 998.81 hectares of land was acquired for its development.
Project features
According to NLCIL, the project has several advanced environmental technologies, including Selective Catalytic Reduction (SCR) and Flue Gas Desulphurization (FGD) technologies for reducing NOx and (SOx) emissions, respectively.
The project also includes a Zero Liquid Discharge (ZLD) system in place to ensure no water is discharged from the plant. A total of 288 km of canal lining works are being undertaken to conserve 195 MLD of water by preventing seepage losses.
The project is equipped with sophisticated monitoring devices, including Ambient Air Quality Monitoring Stations (AAQMS) and Continuous Emissions Monitoring Systems (CEMS).