80ha of Silicon Island reclaimed so far
The project, which covers a total area of 930.78 hectares, is being developed in two phases, namely 510 hectares under Phase 1 and the remaining 420.9 hectares under Phase 2, with reclamation starting in September 2023.
Penang Infrastructure Corporation Sdn Bhd (PIC) chief executive officer Datuk Seri Farizan Darus said the 80-hectare milestone was a positive sign that the project was progressing according to plan, and it was not just about physical progress.
"This project is designed to be a driver of Penang's long-term growth by combining world-class infrastructure, sustainable development practices and community-oriented facilities.
"It will also open up new opportunities for investment, innovation and employment, while ensuring that the local community benefits from better facilities," he said in a statement today.
On the development of the Social Impact Management Plan (SIMP), Farizan said a total of RM11.7 million in ex-gratia payments had been channelled to 791 eligible fishermen, thus strengthening the state government's commitment to the welfare of fishermen.
Apart from cash assistance, he said the government had also implemented a boat and engine assistance scheme as part of its ongoing efforts to provide financial guarantees and modern equipment to local fishermen to ensure they can continue their livelihoods more effectively.
"To date, 118 out of 295 active fishermen who own boats have received new boats and engines, with a total expenditure of almost RM10 million," he said.
Earlier, the Yang Dipertua Negeri Tun Ramli Ngah Talib and his wife Toh Puan Raja Noor Ashikin Raja Abdullah visited the project site to witness the achievements and crossed to the island using a 378m temporary iron bridge built at Permatang Damar Laut.
Also present were state Infrastructure, Transport and Digital Committee Chairman Zairil Khir Johari, Deputy State Secretary (Development) Mohamed Abdul Rahman and Silicon Island Development Sdn Bhd (SIDSB) chief executive officer Datuk Szeto Wai Loong.
During the visit, they were also briefed on upcoming facilities including the 380m marine flyover, Pan Island Link 2A (PIL2A), Matang Food Court and community facilities as well as a new Community Development Department (KEMAS) training centre.
Silicon Island, with a land area of 930.78 hectares, is a reclamation project owned by the Penang government, the first time the state government has directly developed a reclamation project to ensure long-term economic growth.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


New Straits Times
7 hours ago
- New Straits Times
80ha of Silicon Island reclaimed so far
GEORGE TOWN: Reclamation works for Silicon Island have passed the 80-hectare mark, marking steady progress for the largest land reclamation project in Penang to date. The project, which covers a total area of 930.78 hectares, is being developed in two phases, namely 510 hectares under Phase 1 and the remaining 420.9 hectares under Phase 2, with reclamation starting in September 2023. Penang Infrastructure Corporation Sdn Bhd (PIC) chief executive officer Datuk Seri Farizan Darus said the 80-hectare milestone was a positive sign that the project was progressing according to plan, and it was not just about physical progress. "This project is designed to be a driver of Penang's long-term growth by combining world-class infrastructure, sustainable development practices and community-oriented facilities. "It will also open up new opportunities for investment, innovation and employment, while ensuring that the local community benefits from better facilities," he said in a statement today. On the development of the Social Impact Management Plan (SIMP), Farizan said a total of RM11.7 million in ex-gratia payments had been channelled to 791 eligible fishermen, thus strengthening the state government's commitment to the welfare of fishermen. Apart from cash assistance, he said the government had also implemented a boat and engine assistance scheme as part of its ongoing efforts to provide financial guarantees and modern equipment to local fishermen to ensure they can continue their livelihoods more effectively. "To date, 118 out of 295 active fishermen who own boats have received new boats and engines, with a total expenditure of almost RM10 million," he said. Earlier, the Yang Dipertua Negeri Tun Ramli Ngah Talib and his wife Toh Puan Raja Noor Ashikin Raja Abdullah visited the project site to witness the achievements and crossed to the island using a 378m temporary iron bridge built at Permatang Damar Laut. Also present were state Infrastructure, Transport and Digital Committee Chairman Zairil Khir Johari, Deputy State Secretary (Development) Mohamed Abdul Rahman and Silicon Island Development Sdn Bhd (SIDSB) chief executive officer Datuk Szeto Wai Loong. During the visit, they were also briefed on upcoming facilities including the 380m marine flyover, Pan Island Link 2A (PIL2A), Matang Food Court and community facilities as well as a new Community Development Department (KEMAS) training centre. Silicon Island, with a land area of 930.78 hectares, is a reclamation project owned by the Penang government, the first time the state government has directly developed a reclamation project to ensure long-term economic growth.


Borneo Post
8 hours ago
- Borneo Post
SUPP man hits back at Chong, defends new Sarawak airport as long-term investment
Kua says expanding Kuching International Airport is unsustainable due to its landlocked location. KUCHING (Aug 20): Sarawak United People's Party (SUPP) Engkilili chairman (SUPP) Kua Jack Seng has hit back at Democratic Action Party (DAP) Sarawak chairman Chong Chieng Jen, saying his opposition to the proposed new airport project is politically motivated and ignores Sarawak's long-term development needs. The Political Secretary to the Sarawak Premier said expanding Kuching International Airport (KIA) is unsustainable due to its landlocked location. 'Even with an investment of RM100 million, it would only serve as a stop-gap measure for about 10 years. After that, Sarawak would still need a new airport. 'Should Sarawak keep 'patching up' indefinitely, or should we plan boldly for the next 30 to 50 years?' he said in a statement today. Kua argued that the project is not just about capacity but about positioning Sarawak as a regional aviation hub and international gateway. 'How can Sarawak attract more global flights, develop as a Meetings, Incentives, Conferences and Exhibitions (MICE) hub, or draw multinational investments if we continue operating from a constrained airport?' he said. Chong in a statement earlier had said that the RM10 billion airport is a misplaced priority that does not align with the actual needs of the people. He said said the massive expenditure would be better used to uplift the 'world-class living standard' of Sarawakians, rather than investing in a 'world-class' building that showcases state wealth. Chong questioned the necessity of building a new airport, pointing out that the current KIA is significantly underutilised. With that, Kua defended the state's fiscal capacity to fund the project, dismissing Chong's comparisons to federal overspending in the Mahathir era. 'Equating our prudent financial management to federal overspending decades ago is an insult to Sarawak's sound fiscal discipline,' he said. Kua further said Sarawak should not accept 'crumbs' in federal funding while other states receive billions in infrastructure investment. 'The new airport is not just about size; it is the runway for Sarawak's aviation independence and international connectivity,' he said. Kua said Chong's position reflects a 'federal-centric mindset' that discourages Sarawak from dreaming big, adding that the new airport is not wasteful spending, but an investment in Sarawak's future. 'It is a foundation for the next 30 to 50 years, positioning Sarawak as an international gateway and a key aviation hub in the region. 'SUPP firmly believes Sarawakians deserve more than just a token expansion. They deserve infrastructure that matches their resources, potential, and rightful place in Malaysia,' he said. Chong Chieng Jen Kua Jack Seng Kuching International Airport


The Sun
8 hours ago
- The Sun
YTL Green Data Centre positions Malaysia as ASEAN AI hub
KUALA LUMPUR: The YTL Green Data Centre in Kulai, Johor has successfully positioned Malaysia on the global stage as a premier artificial intelligence hub. Minister of Investment, Trade and Industry Tengku Datuk Seri Zafrul Abdul Aziz confirmed the facility now establishes the nation as the AI Centre of Excellence for the entire ASEAN region. This landmark achievement stems from a strategic collaboration between YTL Power International Bhd and technology leader NVIDIA. The partnership focuses on developing cutting-edge AI infrastructure powered entirely by green energy solutions. Tengku Zafrul highlighted the project's immense scale and transformative potential for the local economy. This mega project worth RM10 billion will not only create Malaysia's own large language model (LLM), but will also stimulate the growth of local talent and expertise. He further emphasised the significant job creation this initiative will drive across the high-tech sector. The development is set to generate substantial demand for specialised positions such as data scientists and AI engineers. The minister's Facebook post provided crucial context regarding the project's prestigious backing. YTL is one of five NVIDIA Cloud Partners along with other technology giants such as Amazon Web Services (AWS), Google Cloud, Microsoft Azure and Oracle Cloud. This exclusive partnership underscores the project's global significance and technical credibility. Tengku Zafrul also connected this success directly to high-level governmental engagement. Prime Minister Datuk Seri Anwar Ibrahim's meeting with NVIDIA boss Jensen Huang was not just an empty chat. He proudly concluded that the nation has successfully turned its potential into a concrete reality. - Bernama