
Why has a 'rudderless' CalMac ferry been out of action for 16 months
It comes as the normal Arran ferry . 32-year-old MV Caledonian Isles which was due out of its annual overhaul on February 17, last year remains out of service. The vessel was spotted going into dry dock 'rudderless' while returning to dry dock in Greenock this week with CalMac saying repairs were part of planned work to the vessel and that they were being reattached this week.
What is the MV Caledonian Isles?
Commissioned in 1993, the MV Caledonian Isles is a roll-on/roll-off passenger and vehicle ferry. It has been a cornerstone of the Arran ferry service, accommodating both residents and tourists traveling between Ardrossan and Arran. With a capacity for approximately 1,000 passengers and 110 cars, it is one of the largest and oldest vessels in the CalMac fleet.
Why has it been out of action?
The ferry was withdrawn from service in January 2024 for its scheduled annual overhaul but has remained out of circulation. During this maintenance period, engineers discovered significant issues, including deformed steel frames and damage to the port gearbox.
These findings led to extensive repairs, including steelwork replacements and gearbox overhauls.
------------------------------------------------------------------------------------------------------------------------
READ MORE:
£22m public cost expected as CalMac emergency ferry 'kept for another five months'
ScotGov raises 'doubt' on CalMac getting new ferry contract from October
----------------------------------------------------------------------------------------------------------------------
Further complications arose when additional damage was identified during testing, leading to repeated delays in the vessel's return to service.
MV Caledonian Isles (Image: Newsquest) Some users speculated about whether it will be available for its planned return next week after it was spotted being taken back to dry dock near Greenock after some said it appeared "rudderless".
CalMac confirmed repairs to MV Caledonian Isles rudder were part of the planned work to the vessel and are being reattached this week.
CalMac says it is now due back on June 12.
How has this affected ferry services?
The prolonged absence of the MV Caledonian Isles has significantly impacted ferry services to Arran. CalMac has deployed alternative vessels, such as the MV Alfred and the MV Hebridean Isles, to maintain service on the route.
However, these vessels have smaller capacities and have faced their own mechanical issues, leading to reduced service reliability and capacity constraints. The disruptions have affected the local economy, tourism, and the daily lives of island residents.
MV Hebridean Isles has now retired, but the much-delayed and over-budget MV Glen Sannox has been online since January - seven years after it was scheduled to take passengers.
The loss has had a knock on effect across CalMac's Clyde and Hebrides lifeline island ferry network with disruption felt on islands as vessels are repositioned to try and provide the best service possible.
What are the financial implications?
The repairs to the MV Caledonian Isles have been costly, contributing to a broader financial strain on Scotland's ferry infrastructure. The cost of repairing MV Caledonian Isles was last estimated at £7m.
But the cost of chartering MV Alfred as an emergency ferry because of breakdowns to CalMac ageing ferry fleet is expected to run £22m after it was agreed it should remain for a further five months.
MV Alfred (Image: NQ) It was in March 2023, that the Scottish Government announced that it had chartered Alfred for nine months to supplement the fleet.
Over the past decade, nearly £100 million has been spent on repairs for Scotland's major ferries, with the MV Caledonian Isles accounting for a significant portion of this expenditure. These costs have sparked criticism regarding the management and maintenance of the ferry fleet, highlighting the need for investment in new vessels and infrastructure.
What does CalMac say?
Louis de Wolff, interim fleet management director for CalMac, said: 'We are now in the final stages of the repair plan for MV Caledonian Isles, and we're looking forward to seeing her back in service soon. She'll significantly increase capacity and frequency of service for Arran, operating from Ardrossan.
'We are looking forward to seeing the vessel back on the water for sea trials from this Sunday, which, given the length of time she has been off service, will be thorough and will include berthing trials at Ardrossan and Brodick.
'The extension to MV Alfred's charter will give the network much-needed resilience until the end of the summer timetable. Plans for her deployment are being finalised and will be announced soon.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

Western Telegraph
a day ago
- Western Telegraph
Greggs fans gutted as best menu item axed after 9 years
Many have been struggling to find the Chargrill Chicken Oval Bite in their local stores, which was first launched in 2016. It comes as multiple eagle-eyed customers posted on Reddit sharing their concerns that the sandwich had been removed. As someone wrote on the subreddit r/greggsappreciation: 'Chargrill chicken oval bite been taken off the menu? There's a new icon in town 💙 — Greggs (@GreggsOfficial) May 30, 2025 'I've literally checked 5 different greggs locations in the past week and they haven't had the chargrill chicken oval bite in stock. 'They don't even have the little name tag on shelves, are they axing this? It was my favourite since I was wee and i'd be devastated lol.' Social media users were quick to respond as one replied: 'Ye they've got this rubbish roast chick sub instead, sorry to break it to you OP.' To which another commented: 'aw gutted.' This person shared: 'Yes it's been removed from the menu.' 'It's gone,' a third implied. Discontinued UK Sweets/Chocolates This customer joked: 'F*s that was my idea of a healthy option. 2 sausage rolls it is then.' Meanwhile Greggs fans have noticed the Chargrill Chicken Oval Bite has been replaced with the Roast Chicken Salad Roll, which launched in May – a move which has now been confirmed by Greggs to Newsquest. What is Greggs' new Roast Chicken Salad Roll? On the bakery's website it explains: 'Succulent slices of sliced roast chicken breast topped with tomato, cucumber, mixed leaf salad and seasoned mayonnaise in a white and wholemeal roll. 'That's it. That's the whole roll. It's understated, but it packs a punch when it matters the most.' On Reddit, one commented under the original post: 'It's now called roast chicken. It's basically exactly the same. Give it a go!' A second profile said: 'They have replaced it with the roast chicken oval.' Elsewhere on social media, one person even hailed it 'the best sandwich they had'. 'Another one gone that I liked after the beef and Veg pasty what next,' a person said. Someone else who wasn't too happy about the news joined in: 'I'll have to switch up to something else, things will never be the same though. I liked that particular roll.' Yet others didn't seem as bothered as someone posted: 'As long as I can still get me cheese and onion pasty Im Happy.' Also in agreement, this user shared: 'As long as it's not da chicken bake.' Greggs customers demand return of Ham and Cheese Pastry But the axing of the Greggs Chargrill Chicken Oval Bite has prompted customers to debate the menu items they would like to see return, including the Ham and Cheese Pastry. Discussing on social media, one person stated: 'I liked the ham and cheese pastry from years ago.' 'Bring back the ham and cheese pasty! Those were the best,' a second demanded. Recommended reading: Additionally, an account put: 'They need to bring the steak & cheese roll back.' While a profile said: 'Bring back the Jaffa Cake Doughnut…' A Greggs spokesperson said: 'The Chargrill Chicken Oval Bite is taking a well-deserved rest to make room for our brand-new Roast Chicken Salad Roll, which has recently landed in shops.'


The Herald Scotland
a day ago
- The Herald Scotland
Why did ScotGov support award of ferry contracts to overseas firms
It has been confirmed successful sea trials means that MV Isle of Islay - one of the first of the four ferries being built in Turkey in the wake of Scotland's ferry fiasco - is on target to be delivered sometime between next month and September. Why did CMAL award ferry contracts to shipyards in Turkey and Poland? The Scottish Government -owned ferry and port owner CMAL awarded contracts to build ferries to Cemre Shipyard in Turkey and Remontowa Shipbuilding in Poland based on competitive procurement processes. These shipyards demonstrated the capability to deliver vessels that met technical specifications, timelines, and budgetary constraints. The Cemre yard and (inset) one of the vessels it is delivering for Scotland (Image: .) Remontowa was awarded a £175 million contract to build seven all-electric ferries, having received the highest score during the bidding process . The Turkish shipyard Cemre Marin Endustri was contracted to construct four new roll-on/roll-off passenger and vehicle ferries for Scotland's west coast ferry network. These vessels are intended to enhance services on routes to the Isle of Islay and the Little Minch corridor, which includes Skye, Harris, and North Uist. The deals together were worth £206m. Why was Ferguson Marine, the Scots state-owned shipyard firm not awarded these contracts? The Inverclyde firm had faced several challenges that affected its competitiveness in the bidding process. Firstly a lack of experience. The shipyard had not completed any ferries in the past five years, failing to meet the tender's requirement to show recent experience in building at least three similar ferries. READ MORE: 'Laughable': Turkey-built ferry to be delivered seven years faster than fiasco ship Cost to repair CalMac ferry now £2m more than to buy replacement Why has a 'rudderless' CalMac ferry been out of action for 16 months 'Final nail in coffin'. Scots fiasco firm loses out on big ferry contract to Poland 'Material uncertainty' over Scots ferry operator future amidst £45m funding hike 'Mismanagement': Public cost of Scots ferry fiasco firm hits £750m amidst overspends It had financial and operational issues. Ferguson Marine's previous projects, such as the Glen Sannox and Glen Rosa, were significantly delayed and over budget, raising concerns about the yard's financial stability and project management capabilities. CMAL's procurement process emphasized technical and financial suitability. Ferguson Marine is understood to have not scored as highly as other bidders in these areas. What were the issues with the Glen Sannox and Glen Rosa projects? The issues with Glen Sannox and Glen Rosa has become known as Scotland's ferry fiasco. Glen Rosa and Glen Sannox's arrival to serve islands was scheduled to be online in the first half of 2018. Glen Sannox finally went into service on January but islanders are still awaiting the arrival of Glen Rosa. Glen Sannox (Image: Andrew Milligan/PA) Both vessels were significantly behind schedule and over budget. Glen Rosa's delivery has been delayed until spring 2026, with costs soaring. Costs of the entire project are currently expected to have multiply five-fold from the original £96m price. The delays were down to design and construction flaws. Problems included inadequate planning, quality issues, and a lack of detailed construction plans with CMAL and Ferguson Marine blaming each other for failings. The contract also lacked adequate financial safeguards, such as a builder's refund guarantee, which would have protected public funds in case of project failures. What are the implications of awarding contracts to overseas shipyards? Awarding contracts to overseas shipyards has both advantages and disadvantages. Overseas shipyards like Cemre and Remontowa, it is felt, have demonstrated the ability to deliver vessels on time and within budget. These shipyards have experience building similar vessels, ensuring adherence to technical specifications. But the disadvantages are the economic impact on Scotland. Excluding domestic shipyards like Ferguson Marine can have negative effects on local employment and the Scottish shipbuilding industry. Ferguson Marine has previously indicated that losing ferry contracts had an effect on its ability to continue as a going concern. Ferguson Marine (Image: Colin Mearns) The decisions on the contracts have sparked political criticism and debates over the government's commitment to supporting domestic industries. What lessons have been learned from these experiences? While the decision to award ferry contracts to overseas shipyards was based on factors like cost, efficiency, and technical capability, it has raised important questions about the future of domestic shipbuilding in Scotland and the need for improved procurement practices. The challenges faced in ferry procurement have highlighted the need for robust procurement processes and that contracts should include builder's refund guarantees to protect public funds. It has also shown the requirement to balance the need for cost-effective procurement with the importance of supporting local industries.


The Herald Scotland
a day ago
- The Herald Scotland
Turkey ferry to be delivered seven years faster than Scots fiasco ship
It has been confirmed that the first of successful sea trials means that MV Isle of Islay - one of the first of the four ferries being built in Turkey in the wake of Scotland's ferry fiasco - is on target to be delivered sometime between next month and September. That means that the ferry will have taken just less than three years to be complete, with work starting in October, 2022. Meanwhile, the delivery of MV Glen Rosa - the second of Scotland's two ferry fiasco vessels, is running nearly eight years late. The latest in a long series of rescheduled delivery dates for the ship shows that it is due online sometime between April and June - next year. That's over ten years after the first steel was cut on the Ferguson Marine vessels. Glen Rosa and sister ship MV Glen Sannox were due online in the first half of 2018 when Ferguson Marine was under the control of tycoon Jim McColl, with both now due to serve Arran. The last estimates suggest the costs of delivery could more than five-fold from the original £97m cost. MV Glen Rosa - before a delayed launch (Image: Newsquest) It comes as state-owned ferry and port owner CMAL said the first sea trials for MV Isle of Islay had been carried out successfully by Cemre Marin Endustri in Yalova, Turkey. The trials took place from Thursday, May 22 to Friday, May 30 in the Sea of Marmara, with staff from CMAL and state-owned ferry operator CalMac in attendance. CMAL said the first part of the sea trials saw the set-up of the propulsion systems, generators, thrusters, stabilisers and associated electrical systems. These were then tested, trialled and measured with Lloyd's Register and the Marine Coastguard Agency (MCA) in attendance. The delivery date is predicated on the outcome of two sets of sea trials with the second due to take place later this summer, following the vessel's battery system and harbour acceptance trials. READ MORE:] Why did Scots ministers support award of £381m in ferry contracts to overseas firms Cost to repair CalMac ferry now £2m more than to buy replacement Why has a 'rudderless' CalMac ferry been out of action for 16 months 'Final nail in coffin'. Scots fiasco firm loses out on big ferry contract to Poland 'Material uncertainty' over Scots ferry operator future amidst £45m funding hike 'Mismanagement': Public cost of Scots ferry fiasco firm hits £750m amidst overspends A ferry user group official said: "It is great news to hear that things are going well with the Islay ferry. Islanders have long been calling for better investment into ferry services and so to hear that there have been successful sea trials fills me with optimism on that score. "What is incredible and quite frankly laughable is that it is likely to be completed way before Glen Rosa every makes its way to Arran. "It is, perhaps, not the greatest surprise in the world, and you do have to take into account Glen Rosa is a bigger ship than Islay, but nevertheless it is yet another example, if any more were needed of the dire mismanagement of ferries in Scotland." Islay is being built to hold 450 passengers and 107 cars, while Glen Rosa is designed for up to 852 passengers and 127 cars. "That's not to say that Ferguson Marine could not have built Islay. Ideally a Scottish company would do the job. But we know there are problems there that need to be resolved." Ferguson Marine (Image: Colin Mearns) MV Isle of Islay is the first of four ferries being built at the Turkish yard, and marks what Sottish Government-owned ferry owner and procurer Caledonian Maritime Assets Limited (CMAL) says is a "major milestone in its commitment to delivering new ferries to serve the Scottish islands". MV Isle of Islay and sister ship MV Loch Indaal are being both being constructed for CalMac's Islay service. Construction of the vessels got officially underway in October, 2022 after the £105m contract was controversially given to the Turkish shipyard. CMAL has said that the new 310-foot vehicle passenger ferries will provide a combined 40% increase in vehicle and freight capacity on the Islay routes and "improving the overall resilience" of the wider fleet. Testing of Islay evaluated the vessel's performance at full load, including speed, stability, manoeuvrability, anchor deployment/recovery and endurance. The trials also established the effectiveness of the vessel's propulsion plant, automation and navigational systems. Jim Anderson, director of vessels at CMAL, said: 'This is a great step forward in the build programme of the Isle of Islay. The team at Cemre are working hard to prepare the vessel for delivery. There is a great feeling of momentum following the successful completion of this first phase of sea trials.' After a series of false dawns, len Rosa was expected to be taking passengers in September - but now state-owned Ferguson Marine has admitted the full sign off and deliver will not be till the summer of next year - between April and July. Meanwhile the total forecast costs has increased by £22.5m with a further 'risk contingency' of £12.5m. But the £35 million extra public costs for Glen Rosa being asked for by Ferguson Marine is to become subject to further 'due diligence' probing by ministers before a decision is made on whether the extra money will be provided. Last year wellbeing economy secretary Màiri McAllan said nationalised Ferguson Marine considered the latest delays and costs forecasts - which had Glen Rosa ready to use in September - was the "final position" after the firing of chief executive David Tydeman.