Slowing pace of capital project delivery has knock-on effects for Irish society
A trawl back to the turn of the century will uncover many examples. They include the
National Children's Hospital
, the
Luas tram system
, the Galway Ring Road, the Metro project, offshore wind, and the proposal to extract water from the
River Shannon
for use in
Dublin
(first tabled by Dublin City Council in 2011).
More than a decade ago prominent management consultant Eddie Molloy created a phrase to describe it: implementation deficit disorder.
The latest in a long line of
Government
reports to grapple with the issue was launched on Tuesday by Minister for Public Expenditure
Jack Chambers
. This one is short (less than 50 pages) and is essentially a scoping exercise with a brief to pinpoint the reasons for such long delays in completing infrastructure. Thinking up solutions will come later, with a report and action plan due in the autumn.
READ MORE
The report has identified 12 distinct barriers to timely completion and has not pulled its punches in presenting its findings.
In short, the time it takes for big projects to be completed has 'lengthened considerably'. This has meant knock-on effects for society.
For example, a wastewater system that is delayed in an area means housing estates cannot be built. The delays of often five years or more can result in the final costs ballooning to a multiple of the initial estimate (look no further than the National Children's Hospital).
The 12 barriers are all related. Many of them link in one way or another to the most highlighted impediment of all: judicial review challenges.
One key finding is the public is not sufficiently aware of the consequences of poor infrastructure for communities. That lack of knowledge of the real benefits of a project tends to 'magnify opposition'.
[
Increase in High Court challenges a key barrier to timely completion of infrastructure, report finds
Opens in new window
]
There are ongoing developments and expansion plans for the Luas tram system. Photograph: Getty Images
That opposition often becomes a High Court challenge.
The report cites the Greater Dublin Drainage Project, which has been held back since 2020 by a successful challenge on a single ground.
The project will not now be completed until 2032. In the meantime, costs have doubled and could have an impact on further development of housing in north Dublin.
The key evidential finding is that the number of judicial review cases is increasing. In 2014, there were 42 cases. In 2024, that figure was 147. Already in the first six months of 2025, there have been 88 such court applications, a 20 per cent increase on last year.
A judicial review case can result in a project taking between three and five years longer to complete.
Red tape is another significant factor. Chambers cited an Irish Water project that has required 30,000 pages of information.
When transposing EU directives, Ireland has often followed the highest possible standard. Elsewhere in Europe, an environmental impact assessment is required for a wastewater treatment plan if it serves a population of 150,000 or more. In Ireland, the threshold is much lower: only 10,000 people. Consequently, it takes more than six years to complete consent for each project in Ireland, many years more than in other EU States.
The report has also identified a culture of risk aversion in the public service, partly caused by the increase in High Court cases. It has found that regulatory bodies and Government departments have spent more time scrutinising applications.
'The number of decisions that face judicial review and the associated reputational risk inevitably drives a more conservative approach to decision-making than might otherwise be the case,' it says.
What is the impact? It takes a decade to complete a small water treatment plant. It takes seven years to develop a modest electricity substation. Major road projects can take 15 years. Capital projects have seen a doubling of timelines compared to 20 years ago.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

The Journal
7 hours ago
- The Journal
Should hospitality workers have to pay tax on tips?
TD KEN O'FLYNN HAS called on the Government to exempt gratuities from income tax. Public Expenditure Minister Jack Chambers confirmed in a Dáil statement that there are no plans to alter the tax treatment of tips, which are treated as taxable income and are therefore subject to USC, PAYE, and PRSI. O'Flynn accused the Government of 'penalising low-paid workers for doing their jobs well', and said that a tip is 'not a wage and it's not a bonus – it's a gesture of appreciation'. So today we're asking you: Should hospitality workers have to pay tax on tips? Poll Results: No (840) Yes (166) If they make above a certain threshold in tips (89) Unsure (25) Yes No Unsure If they make above a certain threshold in tips Vote

The Journal
a day ago
- The Journal
New private members club to open on site of former O'Connell Street hotel
PLANS FOR A large new private members club on O'Connell Street have been welcomed by Dublin City Council, who claim the restoration of a significant Georgian building will have wider benefits for the area. The development firm behind a a €500 million masterplan for a major regeneration of a 2.2-hectare site in the O'Connell Street area has applied for planning permission for a change of use of the former Royal Dublin Hotel at the northern end of the city's main thoroughfare to a private members club. Dublin Central GP is seeking approval for extensive conservation, repair and refurbishment works on the interior of the property as well as for a temporary mural on the side of the building. The company is a wholly owned subsidiary of the British property development group, Hammerson, which owns Dundrum Town Centre as well as the Swords Pavilions and ILAC shopping centres. The developers said the interior design of the proposed club was 'to provide a comfortable home-from-home environment where members can meet, work, eat and socialise in the heart of Dublin city.' The plans provide for various dining and recreational facilities across all four floors of the building including a stage, two dining rooms, two living rooms, several bars including a library bar and 'snug lounge' as well as changing rooms and locker rooms. The site at 42 O'Connell Street Upper contains O'Connell Hall – a protected structure – to its rear adjoining Moore Lane with another building known as 'the Billiard Room' linking it to the main building. The plans provide for O'Connell Hall to have a multi-purpose space with the potential to accommodate occasional public events by invitation of the club and its members. Dublin Central GP said a number of potential end users to run the private members club, who have extensive experience 'in the sophisticated design and operation of hospitality venues' have been identified. Advertisement It added: 'The proposed use will reopen the buildings for active use and enjoyment by members and their guests, and will make a positive contribution to reviving cultural heritage assets and sustaining the activation, vitality and passive surveillance of O'Connell Street both by day and night.' Planning files show council planners supported and welcomed the restoration of the building as well as acknowledging the significant investment required to bring it back into use fully. They also expressed satisfaction that a proposal to use O'Connell Hall as a commercial gym was no longer going ahead. The council said it was satisfied that the development is compatible with the overall policies and objectives of the zoning of the site and would have 'a positive, imperceptible and long term and not significant impact on local tourism and amenities.' However, planners have sought further information about the plans from Dublin Central GP to address some concerns about aspects of the project before reaching a final decision on the company's planning application. Construction of the four-storey Georgian townhouse began in 1752 when it was used as a private home. It went through periods of use as a solicitor's office and by various societies and clubs before being taken over in 1882 by the Catholic Commercial Club, which was established to provide a social space for Catholic businessmen excluded from other clubs. The club, which remained in the property until the 1970s, built O'Connell Hall as a multi-purpose space used for concerts as well as a gymnasium. The property subsequently became an extended part of the Royal Dublin Hotel in 1991 after briefly being used as a Garda Advice Centre. The building has been vacant since the closure of the hotel in 2008 and the demolition of the original hotel property. Planning permission for various elements of the masterplan, which includes the retention of historic lanes associated with the Easter Rising and the development of two new public squares was approved by An Coimisiún Pleanála last year. Readers like you are keeping these stories free for everyone... A mix of advertising and supporting contributions helps keep paywalls away from valuable information like this article. Over 5,000 readers like you have already stepped up and support us with a monthly payment or a once-off donation. Learn More Support The Journal


Agriland
4 days ago
- Agriland
Minister explains how revenue from carbon tax is being used
The Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation, Jack Chambers has said that in 2025, €951 million was allocated from carbon tax revenues. In both 2024 and 2025, the carbon tax increased by €7.50/t, as per the Finance Act 2020. According to Minister Chambers, these increases are phased, with auto fuel changes being introduced annually in October, and changes for all other fuels the following May, to allow for a lower rate on home heating fuels during the winter heating season. The minister outlined that the programme for government commits to maintaining this schedule of annual increases to 2030, and using the resulting revenues raised to support climate action measures. This revenue will aso be used to ensure "the most vulnerable" are protected from unintended impacts of the tax increase, Minister Chambers explained. He said that this includes funding for retrofitting and agri-environmental schemes, alongside targeted social welfare and other initiatives to prevent fuel poverty and ensure a just transition. The minister highlighted that in 2024, €788 million was allocated from carbon tax revenues in total, and that in 2025, this allocation grew to €951 million. This represented an annual increase of €163 million on the amounts funded from the carbon tax increase in 2023 and 2024. Minister Chambers said: "In line with the government's commitment to allocate funding over this decade to encourage and incentivise farmers to farm in a greener and more sustainable way, at Budget 2024, the Department of Agriculture, Food and the Marine (DAFM) was allocated €113 million funded from increases in the carbon tax, 14% of the total annual allocation. "At Budget 2025, this amount was increased to €143 million, 15% of the total annual allocation." "The amounts part-fund the Agri-Climate Rural Environment Scheme (ACRES) and to continue prior commitments on green agriculture pilot projects. "These allocations support farmers as they undertake a range of actions which will result in improved outcomes on biodiversity, climate, air, and water quality," Minister Chambers added. According to the minister, between 2020 and July 16, 2025, DAFM has been allocated a total of €366 million in carbon tax funding for these measures, including as part of Budget 2025. Minister Chambers said that his department issues an annual publication on budget day titled The Use of Carbon Tax Funds, which contains further detail on these allocations.