How South Africa's Lesotho water project costs ballooned by R45bn

How South Africa's Lesotho water project costs ballooned by R45bn

Mail & Guardian4 days ago
Watershed: The Lesotho Highlands Development Authority building in Maseru. Photo: Sechaba Mokhethi
The cost of the second phase of the
In 2008, phase two was projected to cost R8 billion. By 2022, this had ballooned to R42 billion. It now stands at R53 billion, raising questions about governance, oversight and accountability.
'Despite Minister [Pemmy Majodina]'s public acknowledgement that a probe into the escalating costs of phase two of the [Lesotho Highlands Water Project] would be conducted, no further details have been shared with parliament or the public,' Democratic Alliance deputy spokesperson on water and sanitation Stephen Moore said last week.
Moore has filed a Promotion of Access to Information Act application to the department of water and sanitation. This follows two unanswered letters, the first sent on 8 May.
The department's spokesperson Wisane Mavasa said the May letter had not been sent directly to the minister or director general. 'Unfortunately, the letter was not acted upon by the officials that it was sent to,' she said, adding that the minister would respond 'shortly'.
The department says the escalation is the result of various factors, including years of delays, treaty complications and market fluctuations.
Oversight gaps
South Africa's portfolio committee on water and sanitation raised concerns about the cost of the project with the auditor general at a sitting on 6 May.
Delays have pushed completion from 2019 to 2028, affecting the delivery schedule and future phases of the project.
The committee also noted constraints stemming from the 1986 treaty preventing the auditor general from auditing the LHDA directly, 'leaving South Africa reliant on Lesotho's audit structures'.
But, says Mavasa, the Lesotho Highlands Water Commission (LHWC) has equal representation from both governments, had 'full access to the cost records of the LHDA' and had received detailed information about the delays.
The committee also criticised the royalty arrangement, which it said obliges South Africa to continue payments to Lesotho even when water deliveries are interrupted.
Other concerns included limited local procurement, dominance of foreign contractors and opaque financial flows. Some MPs went as far as calling for an immediate funding suspension, citing mismanagement and treaty flaws.
However, the auditor general cautioned against such a drastic move, warning of legal consequences. It recommended treaty reforms, including joint audits, instead.
Mavasa says South Africa and Lesotho have agreed to review the treaty, but the 'matters for review' have yet to be decided.
Lesotho's Finance Minister Retselisitsoe Matlanyane
From R8 billion to R53 billion
Mavasa outlined the project's financial journey in detail. The original 2008 feasibility study produced a preliminary R8 billion estimate — excluding inflation, currency shifts, contingency allowances and modern environmental and social safeguards.
Construction of the main works was expected to start in 2013 and deliver water to Gauteng by 2019. However, she said, the main contracts were only awarded in 2022 because negotiations with Lesotho took longer than expected. The situation had worsened with years of administrative and procedural delays.
'The phase two agreement was signed in August 2011. It then took 14 months for the [South African] parliament to ratify the phase two agreement and a further seven months for the Lesotho parliament to ratify the agreement after the ratification by the SA parliament,' Mavasa said.
After Lesotho's 2013 change of government, the agreement was subjected to fresh scrutiny, adding further delays, according to Mavasa, who also pointed out that, between 2013 and 2022, the department of water and sanitation had five different ministers and 11 directors general, which slowed decision-making.
There were also financing complications. Funders raised concerns over procurement processes for the main contracts and requested they be tendered afresh. The Covid pandemic also disrupted preparatory work.
In October 2022, the LHDA projected a R42 billion completion cost — incorporating contract prices; social and environmental programmes; foreign exchange effects and administrative costs.
More than R20 billion in extra costs was due to inflation linked to the delays, Mavasa said.
In October, the figure rose to R53 billion. The department attributed this to:
• R4.2 billion from boosting the contingency provision in line with international good practice from R3.3 billion in 2022 to R7.5 billion last year
• R5.4 billion for additional social obligations requested by Lesotho, such as rural water supply and road infrastructure
• R1.7 billion in price escalations, design changes and contractor claims linked to delays, including work-permit issues.
Governance fixes and audits
According to Mavasa, the project costs and time overruns have been a major concern for the department of water and sanitation and Minister Majodina. She said the Lesotho Highlands Development Authority has developed a plan to minimise any further delays and cost overruns.
The LHWC would appoint a multidisciplinary team of experts to conduct management audits of contracts.
Although the project is about half completed, she said two primary contracts are behind schedule.
'However, the LHDA is executing a turnaround plan to avoid further delays and recover lost time.'
Last year, Mavasa said the department had established a governance committee comprising the department, the Trans-Caledon Tunnel Authority and the South African delegation to the LHWC, which meets monthly to review progress.
The director general of the department of water and sanitation and the principal secretary of the relevant department in Lesotho held ad hoc and quarterly meetings to address issues arising from the project. Unresolved issues were escalated to the ministers.
Lesotho's Minister of Natural Resources Mohlomi Moleko said he could only respond next week as he was outside the country.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Helen Zille brags about taking a taxi: 'I'll be using them often'
Helen Zille brags about taking a taxi: 'I'll be using them often'

The South African

time7 hours ago

  • The South African

Helen Zille brags about taking a taxi: 'I'll be using them often'

Former Democratic Alliance leader Helen Zille has opened up about her positive experience taking a taxi. This comes days after an e-hailing Uber driver was shot and burned alive by angry taxi drivers at Maponya Mall in Johannesburg. On her X account, Helen Zille shared her experience of taking a metered taxi home from the Cape Town International Airport. She posted: 'With our children out of town, we decided to take a taxi home. We went to the authorised airport taxi desk and found friendly, helpful, and quick service. 'They immediately accompanied us, helping with our luggage, to a nearby waiting car . And off we went, with no hassle and a professional, friendly driver. Helen added, 'I'll be using them more often. A good, affordable alternative to more expensive options'. Helen Zille has no qualms about taking a taxi or driving a car that is seemingly socially unacceptable for her status. The former DA leader – who now chairs the party's Federal Council – drives a Toyota Yaris. In March, the 74-year-old revealed that she would be finally upgrading her trusted Corsa of 25 years to another affordable option. In the comments section, Helen Zille was asked what car she would be driving next. 'A Toyota Yaris,' she responded. According to Toyota, the Yaris debuted in South Africa in 2005 and quickly became one of its best-selling models globally. In recent years, 'slow sales' have seen the popular car being discontinued in countries around the world. Let us know by leaving a comment below, or send a WhatsApp to 060 011 021 1. Subscribe to The South African website's newsletters and follow us on WhatsApp, Facebook, X, and Bluesky for the latest news.

Saint or statesman? In India Madiba walked his own path
Saint or statesman? In India Madiba walked his own path

Mail & Guardian

timea day ago

  • Mail & Guardian

Saint or statesman? In India Madiba walked his own path

Prisoner-turned-president: Nelson Mandela's life and South Africa's struggle for freedom bore similarities to India's independence from the British colonial yoke and Mahatma Gandhi's role in its transition to a democracy: Photo: File As South Africa and the world observed International Mandela Day on 18 July, my thoughts returned to Nelson Rolihlahla Mandela — the man, the myth, the miracle. A moment etched in my professional and personal memory is how, during his 1995 state visit to India, Madiba diplomatically declined India's subtle efforts to canonise him as a 'saint' in the moral tradition of Mahatma Gandhi. I was among the South African media corps travelling with Mandela — one of his earliest diplomatic journeys as South Africa's first democratically elected president. It was a trip rich in symbolism and sentiment, coinciding with India's own Independence Day on 15 August — the day in 1947 when it broke free from British colonial rule. On that humid day in New Delhi, Mandela stood alongside the then prime minister, PV Narasimha Rao, at the Red Fort, attending the flag-hoisting ceremonies, parades and patriotic festivities. He listened attentively as Rao addressed a nation of more than one billion people. India, with its traditions, freedom struggle credentials and global democratic stature, was welcoming in many ways a kindred spirit. But the Indian media, swept up in the aura of Mandela — prisoner-turned-president, peacemaker-turned-legend — began to invoke saintly comparisons with Gandhi, their own apostle of peace and nonviolence. Gandhi, after all, had lived and worked in South Africa for two formative decades, where he pioneered the nonviolent resistance movement known as satyagraha. Mandela, who studied Gandhi's writings while incarcerated on Robben Island, had long acknowledged the influence of satyagraha on the ANC's strategy. After his release, as he navigated the treacherous road from armed resistance to reconciliation, it was Gandhi's legacy that offered a moral framework for South Africa's negotiated transition. Yet Mandela, ever the realist and self-effacing statesman, politely stopped short of accepting the spiritual elevation that Indian commentators — and some officials — seemed eager to offer. 'I am no saint,' he said during a press conference in Ahmedabad, where he paid homage at Gandhi's ashram. 'Unless you think of a saint as a sinner who keeps on trying.' The most memorable moment of the visit came when Mandela stood at Gandhi's ancestral home in Gujarat and said: 'You gave us Mohandas; we returned him to you as Mahatma.' It was a moment of diplomatic poetry and historical reflection. Gandhi had come to South Africa as a young lawyer, and it was there — facing institutional racism, fighting for the dignity of Indian indentured workers and learning the discipline of protest — that he was spiritually and politically transformed. When he returned to India in 1915, he was no longer just Mohandas Karamchand Gandhi. He had become the Mahatma, the 'Great Soul'. Mandela's acknowledgment of Gandhi's South African apprenticeship was more than a tribute, it was a recognition of the moral traffic between the two nations. India, in turn, had supported the ANC since its banning in the 1950s, offering the party a semi-diplomatic mission in New Delhi, well before the world fully rallied behind the anti-apartheid cause. India was the first country to cut trade and diplomatic ties with apartheid South Africa. Long before Mandela became a global symbol, Indian leaders such as Jawaharlal Nehru and Indira Gandhi had extended solidarity to Oliver Tambo, Yusuf Dadoo and other leaders of South Africa's exiled liberation movement. India had even raised apartheid as a crime against humanity at the United Nations in the 1950s — a bold act of principled diplomacy. But in 1995, amid the adulation and symbolism, Mandela pushed back — gently but firmly — against the idea that he was Gandhi's reincarnation. In the sweltering heat of Ahmedabad, cradled in the philosophies of satyagraha, Mandela was met with reverence. Yet behind the protocol and pageantry, Indian officials quietly suggested that although they honoured Mandela, they saw him as his own man, not merely a disciple of Gandhi. This was not disrespect — far from it. It was a nuanced diplomatic gesture to honour Madiba's unique path, to recognise that although Gandhi's influence loomed large, Mandela had carved his own legacy. Unlike Gandhi's unwavering nonviolence, Mandela had once led uMkhonto weSizwe, the ANC's armed wing, in a strategic turn toward sabotage and resistance. He had walked a harder path — from armed revolutionary to peacemaker, from political prisoner to president. And he was human. Three marriages. Twenty-seven years behind bars. Flaws and scars. That was Madiba. Gandhi too, was no flawless saint. He too was complex and controversial. But in the theatre of international diplomacy, India's reluctance to canonise Mandela was a tribute in itself: to let him be a statesman, a father of his nation, without forcing him into another's shadow. The visit to India stirred echoes of another assignment I had undertaken — retracing Mandela's final moments as a free man before his 1962 capture by apartheid police. Disguised as a chauffeur, he was travelling near Howick in KwaZulu-Natal when he was intercepted — allegedly tipped off by a CIA operative stationed at the US consulate in Durban. That arrest would lead to the Rivonia Trial, life imprisonment and nearly three decades of silence. Now, in 1995, that same man stood in the Red Fort, feted by the Indian state and embraced by the Indian people. It was a powerful metaphor: from hunted fugitive to honoured guest, from revolutionary to revered elder. His journey mirrored Gandhi's, but it was also distinctly his own. This year marks 30 years since that unforgettable state visit. Mandela's presence in India was not just about diplomacy, it was about kinship. The emotional bond between the Indian National Congress and the ANC, forged in the fires of colonialism, apartheid and exile, had matured into state-to-state relations between proud democracies. Madiba's gratitude was evident. He often said India was the first place where he felt the ANC was treated as a government-in-waiting. He knew that South Africa's freedom was not only the result of domestic struggle, but also of international solidarity. And India had been there — early, steadfast and unapologetically committed. Mandela died in 2013, bearing 250 global honours including the Nobel Peace Prize. But during that 1995 visit to India, he left behind something more lasting: a diplomatic legacy rooted in shared values, mutual respect and an understanding that true heroes don't seek canonisation. Saint or not, Mandela walked his own path. Marlan Padayachee is a veteran political, foreign and diplomatic correspondent from South Africa's transition to democracy. He is a freelance journalist, photographer and researcher.

How SA's Lesotho water project costs ballooned from R8bn to R53bn
How SA's Lesotho water project costs ballooned from R8bn to R53bn

The Citizen

time2 days ago

  • The Citizen

How SA's Lesotho water project costs ballooned from R8bn to R53bn

More than R20 billion was due to inflation linked to the delays. The cost of the second phase of the Lesotho Highlands Water Project (LHWP) to deliver water to South Africa's industrial heartland and generate hydropower for Lesotho has increased by R45 billion. In 2008, phase 2 was projected to cost R8 billion. By 2022, this had ballooned to R42 billion. It now stands at R53 billion, raising questions about governance, oversight and accountability. 'Despite Minister [Pemmy Majodina]'s public acknowledgement that a probe into the escalating costs of Phase 2 of the LHWP would be conducted, no further details have been shared with Parliament or the public,' Democratic Alliance (DA) deputy spokesperson on water and sanitation Stephen Moore noted in a statement issued by the party last week. Moore has now filed a Promotion of Access to Information Act (PAIA) application to the Department of Water and Sanitation (DWS). ALSO READ: Here's how many millions SA sends to Lesotho each month for water This follows two unanswered letters, the first sent on 8 May. DWS spokesperson Wisane Mavasa said the May letter was not sent directly to the minister or director general. 'Unfortunately, the letter was not acted upon by the officials that it was sent to,' she said, adding that the minister would respond 'shortly'. DWS says the price escalation is the result of various factors, including years of delays, treaty complications and market fluctuations. Regarding the DA's PAIA application, Mavasa said the department has 30 calendar days to respond, and it would do so within the legal timeframe. Oversight gaps The South African Portfolio Committee on Water and Sanitation raised concerns about the cost of the project with the Auditor-General of South Africa (AGSA) at a sitting on 6 May, chaired by the DA's Leonard Basson. The meeting flagged weaknesses in governance created by the dual-implementation model between the Trans-Caledon Tunnel Authority (TCTA) and the Lesotho Highlands Development Authority (LHDA). Delays have pushed completion from 2019 to 2028, affecting the delivery schedule and future phases of the project. The committee also noted constraints stemming from the 1986 treaty preventing AGSA from auditing LHDA directly, 'leaving South Africa reliant on Lesotho's audit structures'. But, says Mavasa, the Lesotho Highlands Water Commission (LHWC), has equal representation from both governments, had 'full access to the cost records of the LHDA', and had received detailed information about the delays. The committee also criticised the royalty arrangement, which it said obliges South Africa to continue payments to Lesotho even when water deliveries are interrupted. READ MORE: Completion date for R53 billion Lesotho Highlands Water Project postponed again Other concerns included limited local procurement, dominance of foreign contractors, and opaque financial flows. Some MPs went as far as calling for an immediate funding suspension, citing mismanagement and treaty flaws. However, AGSA cautioned against such a drastic move, warning of legal consequences. It recommended treaty reforms, including joint audits, instead. Mavasa says South Africa and Lesotho have agreed to review the treaty, but the 'matters for review' have yet to be decided. She said South Africa has already set up its review team. Submission of the Lesotho government's team is awaited. Lesotho's Finance Minister Retšelisitsoe Matlanyane told Parliament in February that the government intended to pursue 'the overdue review of the treaty' to negotiate a better deal for Lesotho. How R8 billion became R53 billion Mavasa outlined the project's financial journey in detail. The original 2008 feasibility study produced a preliminary R8 billion estimate – excluding inflation, currency shifts, contingency allowances, and modern environmental and social safeguards. Construction of the main works was expected to start in 2013 and deliver water to Gauteng by 2019. However, she said the main contracts were only awarded in 2022 because negotiations with Lesotho took longer than expected. The situation worsened with years of administrative and procedural delays. 'The Phase 2 agreement was signed in August 2011. 'It then took 14 months for the RSA Parliament to ratify the Phase 2 agreement and a further seven months for the Lesotho Parliament to ratify the agreement after the ratification by the SA Parliament,' said Mavasa. READ MORE: Municipal water crisis 'nothing to do with bulk water supply', says minster at LHWP reopening After Lesotho's 2013 change of government, the agreement was subjected to fresh scrutiny, adding further delays, according to Mavasa, who also pointed out that between 2013 and 2022, the DWS had five different ministers and 11 director-generals, a turnover that slowed decision-making. There were also financing complications. Funders raised concerns over procurement processes for the main contracts and requested that they be tendered afresh. The covid pandemic also disrupted preparatory work, pushing back the award of main contracts. In October 2022, the LHDA projected a R42 billion completion cost – incorporating contract prices, social and environmental programmes, foreign exchange effects, and administrative cost of managing the project. More than R20 billion was due to inflation linked to the delays, said Mavasa. In October 2024, the figure rose to R53 billion. The department attributed this to: R4.2 billion from boosting the contingency provision in line with international good practice from R3.3 billion in 2022 to R7.5 billion in 2024. R5.4 billion for additional social obligations requested by Lesotho, such as rural water supply and road infrastructure – not yet approved by the LHWC but included in the LHDA's projections. R1.7 billion in price escalations, design changes, and contractor claims linked to delays, including work-permit issues. Governance fixes and audits According to Mavasa, the project cost and time overruns have been a major concern for DWS and Minister Majodina. She said LHDA has developed a plan to minimise any further delays and cost overruns. She said LHWC will appoint a multidisciplinary team of experts to conduct management audits of contracts. Although the project is about 50% complete, she said two primary contracts are behind schedule. 'However, the LHDA is executing a turnaround plan to avoid further delays and recover lost time.' READ MORE: Trump gunning for Lesotho: SA sees opportunity for 'closer collaboration' In 2024, Mavasa said the department had established a governance committee comprising the department, the TCTA, and the South Africa delegation to the LHWC, which meets monthly to review progress. Mavasa said the DWS director-general and the principal secretary of the relevant department in Lesotho hold ad-hoc and quarterly meetings to address issues arising from the project. Unresolved issues are escalated to the ministers. Lesotho Minister of Natural Resources Mohlomi Moleko said he could only respond next week as he is outside the country. This article was republished from GroundUp under a Creative Commons license. Read the original article here.