Bengaluru suburban rail project hits dead end as L&T walks out

Bengaluru suburban rail project hits dead end as L&T walks out

Time of India6 days ago
Bengaluru: With just three months left on Prime Minister Narendra Modi's 40-month promise regarding the Bengaluru Suburban Rail Project, the city's long-awaited transport lifeline has come to a grinding halt.
The reason: a major contractual fallout between Rail Infrastructure Development Company-Karnataka (K-Ride), the implementing agency, and construction giant Larsen & Toubro (L&T).
L&T, which was awarded two key corridors — Benniganahalli-Chikkabanavara (Corridor-2) and Heelalige-Rajanukunte (Corridor-4) — has abruptly terminated its contracts, accusing K-Ride of failing to provide the land and work fronts necessary to proceed.
You Can Also Check:
Bengaluru AQI
|
Weather in Bengaluru
|
Bank Holidays in Bengaluru
|
Public Holidays in Bengaluru
It has moved the courts to restrain K-Ride from invoking the bank guarantee deposited. L&T has also demanded Rs 505 crore in dues for completed work and losses arising from what it called "employer breaches". K-Ride, in turn, has called the termination "unilateral" and "illegal", alleging it reflected L&T's lack of commitment to the project.
The 148km suburban rail network, billed as a mass mobility solution for Bengaluru's commuters, was flagged off with much fanfare in June 2022.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Featuring Brigade Ebony™ at Brigade Showcase 2025 | Aug 8–10, Sheraton Grand, Brigade Gateway
Brigade Group
Learn More
Undo
But 37 months on, only about 22% of the scope has been completed, even though 96% of the scheduled time has passed, according to L&T.
The firm claimed that K-Ride failed to hand over both govt and private land, clear encroachments on railway land, and shift utilities blocking the alignment. As a result, expensive machinery and manpower remained idle for months.
In a statement, K-Ride countered that the agreements had been extended — on L&T's request — to Sept 2026 for Corridor-2 and Oct 2026 for Corridor-4.
It maintained that the contracts don't grant L&T the right to terminate them, and called the walkout a clear violation of contractual terms.
K-Ride also claimed it had made available 84% of the alignment in Corridor-2 and 17km in Corridor-4. Yet, the agency said, progress on the ground was hampered by L&T's failure to mobilise resources and delays in finalising designs.
Senior K-Ride officials met infrastructure development minister MB Patil over the weekend to discuss the way forward. The agency said it is now working on alternatives to complete the remaining work and minimise further delays.
The fallout raises fresh doubts over the delivery of a project that has already seen over two decades of delays.
Get the latest lifestyle updates on Times of India, along with
Friendship Day wishes
,
messages
and
quotes
!
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

PM Modi in Bengaluru tomorrow: Full agenda unveiled, traffic restrictions announced
PM Modi in Bengaluru tomorrow: Full agenda unveiled, traffic restrictions announced

Hindustan Times

time29 minutes ago

  • Hindustan Times

PM Modi in Bengaluru tomorrow: Full agenda unveiled, traffic restrictions announced

Prime Minister Narendra Modi will visit Karnataka on Sunday (August 10), where he will inaugurate and lay the foundation stones of several developmental projects. Traffic restrictions across several key routes on August 10 between 8.30 am and 2.30 pm, during Prime Minister Narendra Modi's visit.(PMO) According to a statement from the Prime Minister's Office, PM Modi will flag off three Vande Bharat Express trains at KSR Railway Station in Bengaluru at around 11 am. Thereafter, he will flag off the Yellow line of the Bangalore Metro and undertake a metro ride from RV Road (Ragigudda) to the Electronic City Metro Station. What's on PM Modi's agenda PM Modi will flag off three Vande Bharat Express trains at KSR Railway Station in Bengaluru at around 11 am. After that, he will flag off the Yellow line of the Bangalore Metro and undertake a metro ride from RV Road (Ragigudda) to the Electronic City Metro Station. At around 1 pm, the Prime Minister will inaugurate and lay the foundation stone of urban connectivity projects in Bengaluru, where he will also address a public function. Projects to be inaugurated by PM Modi tomorrow in Bengaluru Prime Minister will inaugurate the Yellow line from RV Road (Ragigudda) to Bommasandra of Bangalore Metro Phase-2 project, having a route length of over 19 km with 16 stations worth around ₹7,160 crore. With the opening of this yellow line, the operational metro network in Bengaluru will increase to over 96 km, serving a large population in the region. Also Read | PM to inaugurate residential complex for MPs on August 11 The Prime Minister will also lay the foundation stone of the Bangalore Metro Phase-3 project worth over ₹15,610 crore. The total route length of the project will be more than 44 km with 31 elevated stations. The Vande Bharat Express trains, which will be inaugurated by PM Modi, includes trains from Bengaluru to Belagavi, Amritsar to Sri Mata Vaishno Devi Katra and Nagpur (Ajni) to Pune. PM Modi in Karnataka: Traffic restrictions in Bengaluru Bengaluru Traffic Police have announced traffic restrictions across several key routes on August 10 between 8:30 am and 2:30 pm, anticipating heavy crowds and VIP movement during Prime Minister Narendra Modi's visit. Also Read | PM Modi praises 'phenomenal' participation in Har Ghar Tiranga Campaign Routes to be avoided in Bengaluru tomorrow Motorists are advised to avoid Marenahalli Main Road (from Rajalakshmi Junction to Marenahalli 18th Main Road), Marenahalli East End Main Road Junction to Aravind Junction, Silk Board to Hosur via Electronic City Elevated Flyover, and Hosur Road, and the stretch from Hosur to Bengaluru city during this time. Restrictions will also be enforced on roads in Electronic City Phase 1, including Infosys Avenue, Velankani Road, and HP Avenue Road, the advisory said. Alternative routes

Sebi proposes lower entry threshold for large-value AIFs at Rs 25 cr
Sebi proposes lower entry threshold for large-value AIFs at Rs 25 cr

News18

time39 minutes ago

  • News18

Sebi proposes lower entry threshold for large-value AIFs at Rs 25 cr

Agency: PTI New Delhi, Aug 9 (PTI) Markets regulator Sebi has proposed a slew of relaxations for large value funds (LVFs) under the alternative investment funds framework, including reduction in minimum investment requirement to Rs 25 crore from the current Rs 70 crore. In a consultation paper issued on Friday, the regulator said the changes aim to widen investor participation and cut compliance costs. The proposals follow recommendations from Sebi's Alternative Investment Policy Advisory Committee and the Ease of Doing Business Working Group. The key proposal is to lower the investment threshold to Rs 25 crore, which the regulator said will attract more domestic institutional players such as insurance companies and diversify the investor base. At present, the working groups highlighted that LVF threshold of Rs 70 crore is too high and many investors, including some institutional investors, have limitations on the quantum. Sebi has also proposed exempting LVFs from several compliance requirements, including the need to follow the standard template for private placement memoranda (PPM), mandatory annual audits of PPM terms, and the responsibility placed on investment committee members for approving fund decisions. Sebi also recommended allowing existing AIF schemes, whose investors meet LVF criteria, to convert into LVFs with the consent of all investors. This would enable them to benefit from the proposed relaxations. The markets watchdog noted that LVFs have seen steady traction since their introduction in August 2021, but could play a bigger role in channelling long-term investments, especially into unlisted securities, if entry barriers are lowered. The Securities and Exchange Board of India has invited public comments on the proposals till August 29. PTI HG TRB view comments First Published: Disclaimer: Comments reflect users' views, not News18's. Please keep discussions respectful and constructive. Abusive, defamatory, or illegal comments will be removed. News18 may disable any comment at its discretion. By posting, you agree to our Terms of Use and Privacy Policy.

Passenger wins ₹1.5 lakh in compensation after unhygienic seat on Indigo flight
Passenger wins ₹1.5 lakh in compensation after unhygienic seat on Indigo flight

Economic Times

timean hour ago

  • Economic Times

Passenger wins ₹1.5 lakh in compensation after unhygienic seat on Indigo flight

Synopsis Indigo Airlines has been found guilty of service deficiency by a Delhi consumer forum for providing a passenger with an unhygienic and stained seat on a flight from Baku to New Delhi. The forum has ordered the airline to compensate the woman ₹1.5 lakh for the discomfort, pain, and mental distress she experienced. Agencies The Delhi consumer forum has found Indigo Airlines guilty of deficiency in service for allotting an unhygienic and stained seat to a woman passenger, ordering the airline to pay ₹1.5 lakh as compensation for the discomfort, pain, and mental distress New Delhi District Consumer Disputes Redressal Commission — comprising president Poonam Chaudhry and members Bariq Ahmed and Shekhar Chandra — heard the case filed by Pinki, who claimed she was given an 'unhygienic, dirty and stained' seat while travelling from Baku to New Delhi on January 2 this further alleged that her complaint about the matter was handled in a 'dismissive and insensitive manner.'In response, Indigo said it had addressed the problem by assigning her a different seat, which she accepted and used to complete her journey to New in its order dated July 9, recently made public, the forum stated, 'We hold that the opposite party (Indigo) was guilty of deficiency in service.' 'As regards the discomfort and pain, mental agony suffered by her, we are of the view that she must be compensated. We accordingly direct the opposite party to pay Rs 1.5 lakh as compensation for mental agony, physical pain and harassment to her,' it commission also instructed the airline to pay ₹25,000 towards litigation its observations, the forum noted that Indigo had failed to produce the Situation Data Display (SDD) report, a part of its internal operational records maintained under standard aviation protocols.'There is no reference to this report in the written statement or in the evidence filed by the opposite party. The SDD is a crucial document used for flight operation monitoring and to record passenger-related incidents. The absence of this document significantly weakens the opposite party's defence,' the order said. [With PTI inputs]

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store