Early monsoon affects bridge construction across Sharavathi River

Early monsoon affects bridge construction across Sharavathi River

Time of India27-05-2025

Shivamogga: Early monsoon rains have affected the construction of minor and major bridges across Sharavathi River in Hosanagar and Sagar taluks. The authorities did not anticipate that their crucial time at the end of May would be impacted by rainfall.
The nearly completed Sigandur Bridge (Ambaragodlu-Kalasavalli) across the Sharavathi River in Sagar taluk awaits inauguration. While civil works are finished, it needs to be asphalted, which the engineers planned to complete before June 1. The early rain and winds hindered progress.
A bridge project of National Highways Authority of India (NHAI), valued at Rs 423 crore on the newly added NH stretch (369E) connecting Sagar to Byndoor highway at Marakutika, was scheduled to open in late May or early June.
Following delays, Shivamogga MP BY Raghavendra announced a mid-June inauguration. Current weather conditions might further postpone the event.
Speaking to TOI, NH senior engineer Peer Pasha said despite exceeding the stipulated handover time due to various reasons, particularly rain preventing asphalt drying, the authority would ensure completion by the end of June.
The NHAI has also undertaken a multi-crore bridge project at Bekkodi village across Sharavathi River's backwater, on the Ranebennur-Byndoor (766C) highway. Rising river levels forced workers to relocate vehicles to the bank.
Additionally, the state govt's two major bridge projects on the Sharavathi — one at Hasirumakki Dam near Sigandur and another at Bilsagar in Hosanagara — have been suspended, officials said.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

May rain caused 35cr farm loss in Nashik
May rain caused 35cr farm loss in Nashik

Time of India

time2 hours ago

  • Time of India

May rain caused 35cr farm loss in Nashik

Nashik: Over 35,000 farmers across 1,469 villages in Nashik district have reported crop losses covering 12,156 hectares, resulting in a combined estimated loss of Rs35 crore due to unseasonal rain in May. According to a senior officer from the district administration, a report was prepared based National Disaster Response Funds (NDRF) guidelines and the estimated damage was sent to state govt for further action. "A total of 35,757 farmers were affected due to unseasonal rain that wreaked havoc in Nashik district. The worst-hit talukas were Surgana, followed by Peth, Satana, Dindori, and others. The loss of crops that were damaged by 33 % or more was estimated at Rs 35 crore," said the officer. Among horticultural crops, 21,084 farmers from 957 villages suffered losses on 9,494 hectares, with a total loss of Rs25.6 crore. In Satana, 3,719 farmers in 145 villages lost crops over 3,069 hectares (including 3,042 hectares of onions and 27 hectares of other crops), resulting in a loss of Rs8.3 crore. In Dindori, 3,428 farmers across 137 villages faced losses on 1,576 hectares (1,560 hectares of onions and 16 hectares of other crops), with damages of Rs4.3 crore. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với sàn môi giới tin cậy IC Markets Tìm hiểu thêm Undo In Chandwad, 3,417 farmers from 44 villages saw losses across 444 hectares (430 hectares of onions and 14 hectares of other crops), amounting to Rs1.2 crore in damages. Igatpuri reported damage across 1,087 hectares (169 hectares of onions and 918 hectares of other crops), affecting 2,919 farmers in 100 villages, with an estimated loss of Rs2.9 crore. In Niphad, 1,968 farmers from 110 villages lost crops across 964 hectares (636 hectares of onions and 328 hectares of other crops), with total losses of Rs2.6 crore. Farmers cultivating multi-year crops like mango and pomegranates also suffered major losses. A total of 14,673 farmers from 512 villages reported losses over 2,662 hectares, with damages worth Rs9.6 crore. In Surgana, 8,325 farmers across 178 villages lost 1,337 hectares of mango plantations, resulting in Rs4.8 crore in damages. Peth taluka saw losses of Rs3.5 crore, with 5,391 farmers from 138 villages reporting damage to 975 hectares of mango crops. Overall, 2,442 hectares of mango and 220 hectares of other multi-year crops were affected. The officer said as per recommendations of NDRF farmers will get compensation at the rate of Rs 27,000 per hectare for damage to horticulture crops and Rs 36,000 per hectare for multi-year crops.

Hazaribag village braces for annual monsoon ‘lockdown'
Hazaribag village braces for annual monsoon ‘lockdown'

Time of India

timea day ago

  • Time of India

Hazaribag village braces for annual monsoon ‘lockdown'

1 2 Hazaribag: A total of 100 houses with around 600 residents in Pachanda, located in the Barkagaon block of Hazaribag district, are preparing a list of grocery items and medicines to store for the next three months as their village will be on a "lockdown" because of the monsoon. Pachanda villagers will be forced inside their area for the next three months until the water level of the rain-fed Haharo River decreases, allowing the path to connect with the rest of the world, to resurface. The villagers have been demanding a bridge for decades but their pleas went in vain. Binod Besra, a resident, said, "Pachanda is a village of farmers and daily wage labourers. It has a school named Utkarmit Madhya Vidyalaya Pachanda where students study up to Standard 8. From Class 9 and onwards, one has to go to Ango, 5 km away, crossing the rain-fed Haharo river. In case of any medical emergency, one has to take the risk of carrying the patients across the swollen river. Luckily, no untoward incident has taken place, so far. " Mahendra Manjhi, the local mukhiya's representative, said the villagers get locked in the village during the monsoon. "We have another route through the forest area, but it is also blocked by the rain-fed Jhinjhor river during the monsoon, too," he said. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like This Device Made My Power Bill Drop Overnight elecTrick - Save upto 80% on Power Bill Pre-Order Undo Mukhiya Neelam Minz said she has taken up the matter regularly with the administration. "It's true that villagers are facing problems, especially during monsoon," she said. Students Birji Kumari (Class 8) and Anu Besra (Class 4), said for three months during the monsoon, their school remains closed. "Teachers fail to come due to the swollen river. So, we have a monsoon vacation for three months," they said. Former Barkagaon MLA Amba Prasad laid the foundation for a bridge last year in August but the project is still to see the light of the day. "I will look into the delay and coordinate with the department to ensure that the work starts at the earliest," Prasad responded when TOI asked her about the status of the bridge. Barkagaon BDO Jitendra Kumar said, "It is not clear why the bridge work has not started yet. But I will look into the matter." Get the latest lifestyle updates on Times of India, along with Eid wishes , messages , and quotes !

Promises unfulfilled, flooded KSRTC bus station cries for crucial makeover
Promises unfulfilled, flooded KSRTC bus station cries for crucial makeover

New Indian Express

time2 days ago

  • New Indian Express

Promises unfulfilled, flooded KSRTC bus station cries for crucial makeover

KOCHI: Another monsoon season is here and it's the same old story at the Ernakulam KSRTC bus station. Located in the heart of the burgeoning city, the dilapidated bus station has remained susceptible to waterlogging for over a decade. While the demolition of the five-decade-old building that houses the station and the construction of a new terminal have hit a roadblock, the repeated promises of the KSRTC authorities to address the issue mostly remain on paper. The last of the assurances was delivered nearly two months back, when the authorities said the work to raise the floor-level of the building and the station premises and the setting up of new drains would be completed before the onset of monsoon. In fact, Ernakulam MLA T J Vinod allotted Rs 50 lakh for the purpose from the legislative assembly constituency asset development fund. The work has kicked off for sure, but is progressing at a tardy pace. 'The activities have been hampered by intermittent rain. The good thing is that the scope of the project has broadened with BPCL (Bharat Petroleum Corporation Ltd) contributing Rs 99 lakh. A tripartite agreement will soon be signed between BPCL, KSRTC and the PWD to implement the Rs 1.5-crore project,' the MLA told TNIE. Swanky terminal a distant dream The plan to set up a new swanky bus terminal -- modelled after the Vyttila Mobility Hub -- on 2.9 acres in Karikkamury has suffered a setback. The project was initially mooted to be implemented with the Rs 12-crore fund promised by Cochin Smart Mission Ltd (CSML). But the KSRTC backed out following a difference over the terms and conditions that included toll for the entry of KSRTC buses into the proposed terminal. 'Despite giving land, they wanted to levy a toll on our buses. That can't be justified,' a senior KSRTC official said. Earlier, the plan was to construct a bus terminal that can be accessed by both private and KSRTC buses. The project was in the doldrums and the CSML term ended in March. While the agency's term has been extended by another year, a fresh nod from the ministry of housing and urban affairs needs to be obtained to avail funding.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store