2.7 km long continuous tunnel completed with first breakthrough in 21 km tunnel between BKC and Shilphata

2.7 km long continuous tunnel completed with first breakthrough in 21 km tunnel between BKC and Shilphata

India Gazette11-07-2025
Shilphata (Maharashtra) [India] July 11 (ANI): On July 9, the first breakthrough was achieved in the 21 km long tunnel being constructed between Bandra-Kurla Complex (BKC) and Shilphata in Maharashtra, marking the successful completion of a 2.7 km continuous tunnel section.
Out of the total 21 km tunnel, 5 km is being constructed using the New Austrian Tunnelling Method (NATM) between Shilphata and Ghansoli, while the remaining 16 km will be built using Tunnel Boring Machines (TBMs). The tunnel also includes a 7 km long undersea section beneath Thane Creek.
To expedite tunnelling in the NATM portion, an Additionally Driven Intermediate Tunnel (ADIT) was constructed, allowing simultaneous excavation towards Ghansoli and Shilphata sides. So far, about 1.62 km has been excavated from the Shilphata side, and the total progress in the NATM section stands at approximately 4.3 km.
Comprehensive safety measures have been implemented at the site, including ground settlement markers, piezometers, inclinometers, strain gauges, and biometric access control systems to ensure safe and controlled tunnelling activities without disturbing nearby structures.
The work on the Mumbai-Ahmedabad high-speed bullet train project is going on in full swing in Maharashtra, with major structural and tunnelling milestones being achieved, according to the National High-Speed Rail Corporation Limited (NHSRCL) said on Saturday.
According to the NHSRCL, work on all three elevated stations in the state, Thane, Virar, and Boisar, is advancing swiftly, and the first slabs for Virar and Boisar stations have recently been cast. Across the alignment, pier foundations and pier works are underway at various locations, with approximately 44 km of piers cast to date.
In the Palghar district, viaduct construction has also commenced using full-span box girder launching technology, starting from the Dahanu area. Additionally, the excavation of seven mountain tunnels in the Palghar district is actively in progress, demonstrating the project's engineering scale and complexity. Bridge construction has also kicked off at three major rivers: Vaitarna, Ulhas, and Jagani, further contributing to the corridor's critical infrastructure.
An important component of the project is the 21-kilometre-long underground and undersea tunnel connecting the Mumbai Bullet Train station at Bandra-Kurla Complex (BKC) to Shilphata. Of the 21 km tunnel, 16 km is being excavated using Tunnel Boring Machines (TBMs), while 5 km is being executed using the New Austrian Tunnelling Method (NATM). The tunnel includes a 7 km undersea stretch beneath Thane Creek, marking a significant feat in Indian tunnelling history.
So far, approximately 4.1 km of tunnel heading has been achieved through NATM from the Shilphata site, and two concurrent faces have been developed from the ADIT portal. In terms of vertical construction, base slab casting at the Vikhroli shaft (56 meters deep) and Sawli shaft (39 meters deep) has been completed. Additionally, sludge treatment plants are being installed at shaft locations, and the Mahape tunnel lining casting yard is actively producing tunnel lining segments.
For the under-construction Mumbai Bullet Train station at Bandra Kurla Complex, 80% of the excavation work has been completed. Base slab casting at 100 ft below ground level has already started at both ends of the station site, NHSRCL added. (ANI)
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

World Elephant Day observed with a call for human-elephant co-existence
World Elephant Day observed with a call for human-elephant co-existence

News18

time15 hours ago

  • News18

World Elephant Day observed with a call for human-elephant co-existence

Majuli (Assam) [India], August 12 (ANI): World Elephant Day is observed annually on August 12 to promote the conservation and protection of elephants while addressing the growing issue of human-elephant conflict. The day aims to ensure that elephants can thrive without clashes with human an increasing human population, elephant habitats are shrinking, forcing these majestic animals to venture into human settlements in search of food. In Majuli, a herd of about 150 elephants has been roaming across different chars and chaporis for several years. However, unlike many other places, Majuli has not experienced severe human-elephant Majuli Forest Department has taken special measures to monitor the elephants in these areas and ensure that, if they enter human settlements, they are guided back to the forests. On this occasion, the department expressed hope for a future free from human-elephant conflict, fostering peaceful forest officer, Garmur range, Abhijeet Doley said to ANI, 'Not only World Elephant Day, but every day is important for us. Over the past 2-3 months, we have observed a large elephant herd travelling across the Chapori areas in different locations under the Majuli division. We are continuously monitoring the movement of these elephants and working to prevent conflict situations in the Chapori areas." Abhijeet highlighted the reason for the conflict and added, 'The human population in the Chapori areas is increasing, while protected areas are declining. These Chapori areas have belonged to elephants for a very long time. Since humans have now settled in these regions, I request everyone to coexist with the wild animals."'My message to the people is simple — respect wild animals. I understand that sometimes they damage khutis (bamboo structures) or destroy crops, paddy, and other resources. But somehow, we must try to accept these challenges. We are doing everything possible to minimise such losses. Therefore, my appeal to those living in the Chapori areas is: please respect our elephants and rhinos–they are a part of us," he further added. (ANI)

Delhi: 2 of 6 tiger cubs born last week in zoo die; 4 under close watch
Delhi: 2 of 6 tiger cubs born last week in zoo die; 4 under close watch

Time of India

timea day ago

  • Time of India

Delhi: 2 of 6 tiger cubs born last week in zoo die; 4 under close watch

ANI file photo N EW DELHI: Two Bengal tiger cubs have died at the Delhi zoo in the past three days, officials said on Monday, just a week after the birth of six cubs, the largest litter in two decades. The cubs were born to a seven-year-old tigress, Aditi, on August 4. This was her first litter since arriving from the Gorewada rescue centre in Nagpur. The smallest cub in the litter died inside the enclosure on the morning of August 8. Another, too weak to feed, was moved to the zoo hospital on August 9, but died the following night despite treatment. Zoo director Sanjeet Kumar said Aditi is feeding and caring for the remaining four cubs, who are under 24-hour CCTV and manual monitoring. 'Supplements are being given to the mother to support milk production. The remaining cubs are active and feeding well,' Kumar said as quoted by PTI. Before this litter, the zoo had six white tigers and seven Royal Bengal tigers. In 2023, tigress Siddhi from Gorewada gave birth to five cubs, the first Royal Bengal tiger birth at the zoo in nearly 18 years, but only two survived. The last litter of six was in 2005, when two survived. The most recent white tiger birth was in 2022, when tigress Sita delivered three cubs, of which two survived. Officials say survival rates in large litters are often low. The Delhi Zoo, which has housed tigers since its opening in 1959, is recognised under the Central Zoo Authority's conservation breeding programme as a centre for tiger conservation and breeding.

Uttarakhand: About 1278 people rescued in Uttarkashis Dharali
Uttarakhand: About 1278 people rescued in Uttarkashis Dharali

News18

time2 days ago

  • News18

Uttarakhand: About 1278 people rescued in Uttarkashis Dharali

Uttarkashi (Uttarakhand) [India], August 11 (ANI): About 1,278 people have been rescued in operations in Uttarakhand's Dharali, Garhwal Commissioner Vinay Shankar Pandey said on Vinay Shankar Pandey told ANI, 'Following a disaster in Dharali, about 1,278 people, including those from other states, stranded at Gangotri Dham, were evacuated. The operation is now complete. Electricity and mobile networks have been added that the Valley Bridge and road connectivity have been restored, and the district officials are monitoring the distribution of Rs 5 lakh assistance announced by Chief Minister Pushkar Singh Dhami.'The Valley Bridge has been restored, and road connectivity should be fully restored by evening. Essential supplies like food, warm clothing, and daily items have arrived for distribution. District officials monitor the situation as the distribution of Rs 5 lakh assistance, announced by the CM, begins," he Commissioner added, 'A three-member committee appointed by the CM has arrived to assess relief and rehabilitation packages. They will submit an initial report in a week and a final report within a month."He said that a list of 43 missing individuals has been released, which includes 13 locals, nine army personnel, 13 individuals from Bihar and six from Uttar Pradesh.'A list of 43 individuals has been released, which includes 13 locals, nine army personnel, 13 from Bihar, and six from UP. The number of missing Nepali workers has dropped from 29 to 24 as five have been located, and additional information is being sought to further reduce the list. Updates will be provided as more information becomes available," he told today, the construction of the Bailey Bridge at Limchigad was completed and is now open for public use, CM Dhami relief materials for the flash-flood-affected Dharali are also being sent through this a post on X, Uttarakhand CM said, 'The construction work of the Bailey Bridge at Limchigad has been completed, and the bridge has been opened for traffic. Now, through this bridge, not only are relief materials and machinery being sent forward quickly, but the movement of local people has also resumed smoothly. In this difficult time of disaster, our government is working with full commitment to normalise public life." (ANI)

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store