logo
Kaiga nuclear plant units 5 & 6 to be fully operational by 2030

Kaiga nuclear plant units 5 & 6 to be fully operational by 2030

Time of Indiaa day ago
Karwar: The 5th and 6th units of the Kaiga Generating Station (KGS) in Kaiga, Karwar, are expected to be fully operational by 2030, with construction activities already in progress, said B Vinod Kumar, site director of KGS.
He told that excavation at the site is complete, and contracts for major components have been awarded. The turbine package went to Bharat Heavy Electricals Limited (BHEL), and the nuclear package was awarded to Megha Engineers and Infrastructure Limited (MEIL). The first pour of concrete is expected to begin after te monsoon. Kaiga is the sixth nuclear site of NPCIL and currently, houses four operational Pressurised Heavy Water Reactor (PHWR) units (KGS-1 to 4), each with a capacity of 220 MWe.
Two additional PHWR units (KGS-5 and 6), each with a capacity of 700 MWe, are being developed, bringing the total capacity to 2280 MWe.
Vinod noted that the existing units set international benchmarks in operational efficiency and safety. Since their commissioning, the Kaiga site generated over 1.3lakh million units of electricity and helped avoid around 1.2 lakh tonnes of CO₂ emission.
Kaiga's safety record earned numerous accolades, including Sarvashrestha Suraksha Puraskar, Unnata Suraksha Puraskar, Prashamsa Patra from National Safety Council, and safety awards from the Atomic Energy Regulatory Board (AERB), NPCIL, and DGFASLI.
KGS Unit-1 set a global record for continuous operation, running for 962 days, from May 13, 2016, to Dec 31, 2018, before being shutdown for maintenance. On March 16, Unit-2 completed 25 years of commercial operation. Units 3 and 4 were constructed and commissioned in a record time of 59 months.
Currently, KGS-1 is undergoing En-Masse Coolant Channel Replacement (EMCCR) and En-Masse Feeder Replacement (EMFR) as part of its life extension, a process expected to take 18 months. Once completed, similar activities will be carried out on KGS-2.
Under its CSR initiatives, NPCIL Kaiga supports developmental activities in nearby villages. It spent around ₹20 crore on wildlife conservation efforts in Kali Tiger Reserve.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Kaiga nuclear plant units 5 & 6 to be fully operational by 2030
Kaiga nuclear plant units 5 & 6 to be fully operational by 2030

Time of India

timea day ago

  • Time of India

Kaiga nuclear plant units 5 & 6 to be fully operational by 2030

Karwar: The 5th and 6th units of the Kaiga Generating Station (KGS) in Kaiga, Karwar, are expected to be fully operational by 2030, with construction activities already in progress, said B Vinod Kumar, site director of KGS. He told that excavation at the site is complete, and contracts for major components have been awarded. The turbine package went to Bharat Heavy Electricals Limited (BHEL), and the nuclear package was awarded to Megha Engineers and Infrastructure Limited (MEIL). The first pour of concrete is expected to begin after te monsoon. Kaiga is the sixth nuclear site of NPCIL and currently, houses four operational Pressurised Heavy Water Reactor (PHWR) units (KGS-1 to 4), each with a capacity of 220 MWe. Two additional PHWR units (KGS-5 and 6), each with a capacity of 700 MWe, are being developed, bringing the total capacity to 2280 MWe. Vinod noted that the existing units set international benchmarks in operational efficiency and safety. Since their commissioning, the Kaiga site generated over 1.3lakh million units of electricity and helped avoid around 1.2 lakh tonnes of CO₂ emission. Kaiga's safety record earned numerous accolades, including Sarvashrestha Suraksha Puraskar, Unnata Suraksha Puraskar, Prashamsa Patra from National Safety Council, and safety awards from the Atomic Energy Regulatory Board (AERB), NPCIL, and DGFASLI. KGS Unit-1 set a global record for continuous operation, running for 962 days, from May 13, 2016, to Dec 31, 2018, before being shutdown for maintenance. On March 16, Unit-2 completed 25 years of commercial operation. Units 3 and 4 were constructed and commissioned in a record time of 59 months. Currently, KGS-1 is undergoing En-Masse Coolant Channel Replacement (EMCCR) and En-Masse Feeder Replacement (EMFR) as part of its life extension, a process expected to take 18 months. Once completed, similar activities will be carried out on KGS-2. Under its CSR initiatives, NPCIL Kaiga supports developmental activities in nearby villages. It spent around ₹20 crore on wildlife conservation efforts in Kali Tiger Reserve.

Construction of KGS Units 5, 6 picks pace; first pour of concrete to commence by November
Construction of KGS Units 5, 6 picks pace; first pour of concrete to commence by November

The Hindu

timea day ago

  • The Hindu

Construction of KGS Units 5, 6 picks pace; first pour of concrete to commence by November

As the excavation has been completed, the construction activities of the Kaiga Generating Station Units 5 and 6 (KGS 5 and 6) Pressurised Heavy Water Reactor units with a total capacity of 1,400 MW have gained momentum, and the first pour of concrete is expected to commence by November. Briefing the press at the Media Outreach Programme at Kaiga site of Nuclear Power Corporation of India Limited (NPCIL) in Uttara Kannada district on Tuesday, Kaiga Site Director B. Vinod Kumar said that the project cost of ₹21,000 for KGS Units 5 and 6 was to be released over a period of five years. He said that KGS Unit-1, which was under shutdown owing to En Masse Coolant Channel Replacement (EMCCR) and En Masse Feeder Replacement (EMFR) exercises, would last for 18 months and is scheduled to resume operation on October 30, 2026. Mr. Vinod Kumar said that the four units at the Kaiga site had set benchmarks comparable with international standards, and ever since the commercial operation of the units began, the Kaiga site had generated a total of 1.3 lakh million units of power and had avoided the generation of about 1.2 lakh tonnes of carbon dioxide. CSR 'As part of its Corporate Social Responsibility initiatives, so far, ₹110 crore has been spent by NPCIL-Kaiga. Additional ₹20 crore has been spent towards conservation of wildlife at Kali Tiger Reserve,' he said. Refuting the allegation of locals not being given preference, Mr. Vinod Kumar clarified that out of the 2,057 contract workers, 1,759 (84%) belonged to Karnataka, and of them, 1,601 were from Uttara Kannada district. And of the 595 Group B and C employees, 483 (81.3%) were from Karnataka, he said. Coaching Regarding the recruitment notification of 390 vacancies, he told the press that as it was an all-India examination, they would be offering coaching to the local youths to prepare for the competitive examination. He also clarified that they had taken steps as per the direction of the National Green Tribunal (NGT) and were expecting approval for KGS Units 5 and 6. In response to a query, Head of Corporate Communication of NPCIL, Umed Yadav, said that after the commissioning of KGS Units 5 and 6, 50% of the power generated would go to Karnataka. Senior officials of various KGS units, K. Sriram, Jawahar Singh, S.K. Ojha, Umedkumar Yadav, Suvarna Gaonkar and others were present.

RRB NTPC Admit Card 2025: How to download when released?
RRB NTPC Admit Card 2025: How to download when released?

Indian Express

time5 days ago

  • Indian Express

RRB NTPC Admit Card 2025: How to download when released?

The Railway Recruitment Boards (RRBs) are expected to release the RRB NTPC Admit Cards 2025 soon for the upcoming Computer-Based Test (CBT-1) for Non-Technical Popular Categories (Under Graduate). As per the official notice, the admit cards or e-call letters will be made available for download four days prior to the respective exam dates. Once released, candidates will be able to download their admit cards from the regional RRB websites such as and others. The first stage CBT for CEN 06/2024 is scheduled to be held from August 7 to September 9, over a period of 19 days. The link to view the exam city and date along with the facility to download travel authority for SC/ST candidates is already active on the official websites of all RRBs. Step 1: Visit the official Railway Recruitment Board website or the regional RRB portal through which you applied. Step 2: On the homepage, click on the link titled CEN 06/2024 (NTPC-UG): CBT-1 City-Intimation & E-Call Letter. Step 4: Enter your Registration Number (User ID), Password (Date of Birth in DD-MM-YYYY format), and the Captcha Code. Step 5: Click on the submit button. Your admit card will appear on the screen. Step 6: Download and print at least two copies of the admit card. Carry a hard copy to the examination centre on the day of the test. The RRB, in one of its notice has stated that for candidates who do not remember their registration credentials, the regional website also provides an option to retrieve the application number or reset the password using the 'Forget Password' link on the login page. The RRB NTPC CBT-1 exam will be a computer-based test comprising 100 multiple-choice questions for a total of 100 marks. The exam will be conducted over 90 minutes and will include three sections: General Awareness (40 questions for 40 marks) Mathematics (30 questions for 30 marks) General Intelligence and Reasoning (30 questions for 30 marks) There will be a negative marking of 1/3 mark for every incorrect answer. The test is designed to assess the candidate's aptitude, reasoning ability, and awareness of general subjects relevant to the NTPC roles.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store