KZN Department of Transport takes action: Multiple road contracts at risk of cancellation
Image: Doctor Ngcobo / Independent Newspapers
The KwaZulu-Natal Department of Transport has cancelled two contracts, one of which was valued at over R80 million, and is on the verge of cancelling several other contracts due to poor contractor performance.
These contractors could also face penalties and recoveries for failed projects, the department warned. The department said 30 contracts are at risk of cancellation due to the poor performance of the awarded contractors.
Transport MEC Siboniso Duma warned that the cancellation of contracts is just the beginning for contractors who fail to deliver. The department declined to comment on how much the contractors were paid for the two contracts which have been cancelled. It said it will first need to assess how much work has been done.
'We have projects that are underway, valued at R5 billion. What we want is value for money from those projects,' Duma stated. Duma confirmed the termination of a contract for the construction of road P577-02, which links Cowie's Hill and New Germany to the M13 and M19. The R87.8 million contract was awarded to a contractor on 9 June 2023, with work beginning on 2 August 2023. The project was due to be completed by 24 May 2024.
However, more than 14 months later, Duma said the contractor had failed to make adequate progress.
In his recent budget presentation, the MEC disclosed that over R3.8 billion would be allocated for constructing new infrastructure projects, while over R4.3 billion would be dedicated to maintaining the road network. Duma emphasised the importance of instituting recoveries against companies that fail to deliver.
'The failure is not just disruptive to service delivery; it is very costly to the department. If the contractor fails, we have to start the process of awarding all over again, which is time-consuming and expensive. That's why we must impose penalties and institute recoveries.'
The department stated that the backlog in road infrastructure necessitates a strict approach towards contractors who do not complete projects on time. It believes that naming and shaming these contractors will serve as a deterrent for future contractors.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
Currently, the department has a total of 39 active construction projects and 44 rehabilitation/resealing projects. 'There are 30 contractors from the Construction Industry Development Board (CIDB) grade 6 to grade 9 who are failing to complete capital projects on time across the province. Some projects have stalled, while others have been abandoned, with instances where site establishment has not even commenced.
'Engagements with these contractors have revealed that many face resource challenges, particularly cash flow issues. Other cited challenges include scope creep, which tends to increase once contractors are established on-site. Surprisingly, even long-established contractors with years of experience are among those failing to deliver,' the MEC stated.
Duma added that these established contractors often take on too many projects simultaneously, which negatively impacts all their ongoing projects. When cash flow problems arise in one project, it affects other projects they are managing for the department.
'Contractors who fail to adhere to the new timelines will be terminated. The department has already identified contractors who are unlikely to complete their projects in the foreseeable future, necessitating their termination.
'Furthermore, the department will follow the necessary legal procedures to blacklist these contractors from future work with the department, which could last up to ten years. In addition, the department will take steps to recover funds due to the failures of these service providers. The MEC has directed that the supply chain management process be strengthened, including thorough vetting of contractors before hiring to ensure they have the requisite capacity. In some cases, contractors lack essential equipment, such as fleet (plant equipment),'Duma concluded.
Professor Pundy Pillay of the Wits School of Governance stated that the government was justified in terminating contracts of individuals who are not performing.
'You can't have a situation where people are paid when they have not done the work. Everyone will take the money and not do the work,' he remarked. He added that the government complicates matters by not paying contractors on time. There should be a structured arrangement for payments, and these payments should be linked to the progress that has been made.
Pillay expressed concerns about the recoveries threatened by the province, suggesting they are unlikely to yield results. 'That money spent on contractors is taxpayer money down the drain,' he concluded.
Riona Gokool, the DA KZN spokesperson on Transport, raised concerns that the department has not been paying contractors on time, which has contributed to their negative performance.
She said the department's failure to honour contractor payments has a devastating impact not only on small businesses and emerging contractors but also on job creation and community development, which are key pillars of its mandate.
Mncedisi Maphisa, the chairperson of the Transport Portfolio Committee, said that the actions of the MEC have the committee's full support.
'Our job is to ensure service delivery, not to please service providers. If the MEC has done all he can to capacitate the contractor and that contractor still fails, we support the termination of such contracts. That must not only end in this field; all service providers in the department that are not performing should be dealt with,' he stated.
THE MERCURY
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

IOL News
10 hours ago
- IOL News
Public Works makes strides in reducing rental payments owed to landlords
Public Works and Infrastructure Minister Dean Macpherson says his department has put in controls that were monitored daily and were aimed to improve the functioning of their payment systems. Image: Henk Kruger / Independent Newspapers Public Works and Infrastructure Minister Dean Macpherson said his department has managed to reduce to R20 million outstanding rentals owed to landlords that dated back three months ago. Macpherson said the department has put controls that are monitored daily and is looking at systems to improve the functioning of its payment systems. 'As at 6 June 2025, the outstanding rental amount is R2,540,382.42 (0.5%) and R19,897,707.26 (4.1%) for April and May, respectively,' he said. Macpherson was responding to parliamentary questions from Build One South African leader Mmusi Maimane, who enquired about the Information and Communication Technology outages that affected the ability of the Property Management Trading Entity to process rental payments to landlords in April. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Maimane enquired about the current status of rental payments, the total number of landlords that remained, the total monetary value of outstanding rental payments, and steps his department has taken to ensure that such delays do not recur. Macpherson said there were 1,991 leases for 1,274 landlords valued at R484,425,687.62 in the lease administration system and the payment system for April rental payments as of June 6. 'Forty-four leases (2.2%) affecting 26 landlords (2%) amounting to R2,540,382.42 (0.5%) failed Central Supplier Database (CSD) verification and therefore were not paid.' He also said there had been 1,995 leases for 1,269 landlords valued at R483,952,863.48 for May. At least 89 leases (4.5%) affecting 75 landlords (5.9%), amounting to R19,897,707.26 (4.1%) were not verified and were not paid. Macpherson said the payment system was still processing the June rental payments. 'The outstanding rental payments for April 2025 are 44 leases (2.2%) affecting 26 landlords (2%). The outstanding lease payments for May are 89 leases (4.5%) affecting 75 landlords (5.9%),' he said. 'It must be noted that the non-payment of transactions submitted on the payment system is primarily due to landlords not being compliant with CSD. In addition, 33 CSD non-compliant landlords from April are included in the May figure.' Meanwhile, the Independent Development Trust (IDT) has collected R882 million in payments in just three months from 15 departments that owed for infrastructure projects it implemented on their behalf. 'The IDT has been able to collect R882,374,561 between 01 April 2025 and 30 June 2025,' Macpherson said. The entity has paid a total of 1,366 service providers to the tune of R648,167,277. 'As at 30 June 2025, 790 service providers remained unpaid an amount of R1,394,036,545. The variance in the amount is due to additional invoices that would have been received between 01 April 2025 and 30 June 2025,' he said. Macpherson was responding to ActionSA MP Malebo Patricia Kobe, who enquired about the department's obligation to pay contractors after receiving money due from client departments. The IDT had informed the portfolio committee in June that it was owed R1.2 billion by client departments. It informed Parliament four months ago that it had been unable to pay service providers due to delays in payment by client departments. The entity has incurred R47m in total expenditure on legal costs and owed creditors for more than 12,000 invoices that could not be paid within the 30-day deadline as of the end of March last year.

IOL News
11 hours ago
- IOL News
SA's rate cut: a move to boost the economy and property market
Announcing the July MPC interest rate decision, South African Reserve Bank (SARB) Governor Lesetja Kganyago says South Africa has an opportunity now to lock in low inflation and clear the way for sustainably lower interest rates. Image: SARB/Facebook The recent interest rate cut sends a strong signal to investors that South Africa is intent on driving economic growth despite global challenges. On Thursday, South African Reserve Bank governor Lesetja Kganyago announced that the Monetary Policy Committee (MPC) decided to reduce the policy rate by 25 basis points, to 7%, with effect from the 1st of August. He said this decision was unanimous. South Africa's move is aligned with a cautious global trend toward stimulating consumer spending and investment, says Bradd Bendall, the national head of sales at BetterBond. "Homeowners will welcome today's decision to drop the prime lending rate to 10.5% - a level last seen in 2022,' Bendall said. He added that a lower prime lending rate provides much-needed relief to consumers and homeowners struggling to balance their monthly obligations with rising living expenses. 'For the average homeowner with a bond, this reduction could translate to meaningful monthly savings. On a R2 million home, for example, the monthly bond repayments will drop by R337 from R20 305 to R19 968. It will also reduce the amount payable over a 20-year period by R80 876.' BetterBond said they expect this cut will further invigorate the housing market, which has already shown remarkable signs of recovery in recent months. Its July data shows that bond applications rose by 7.4% for the 12 months to May 2025, with home loans granted up by an impressive 13.6%, the mortgage broker said. Bendall said these volumes point to renewed buyer confidence and a more stable market environment that should encourage more aspirant first-time buyers to enter the property market. "The lower interest rate environment will benefit the local property sector going forward as property companies will be able to reduce their average financing costs through the refinance of upcoming debt maturities at lower rates, and the downward rebasing of their ZAR variable debt component's reference rate," says Unathi Hewana, the co-portfolio manager at Mergence Investment Managers. 'The local property market is heavily exposed to retail, so any improvement in consumer sentiment, driven by the lower interest rate environment and the consumer's own ability to better manage their debt financing costs will benefit the sector as well, as that can lead to more retail spend. "An improvement in general business sentiment, on account of the lower interest rates, should also benefit the property sector, if that improvement in sentiment translates to an increase in demand for space. "These instances can lead to positive property revaluations and better total return generation as they are supportive of both an increase in rental growth and a decrease in capitalisation rates,' Hewana said. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ Standard Bank said this interest rate cut was expected, given the prevailing low inflation and muted economic growth in the first quarter of this year. The bank said South Africa's GDP grew by only 0.1% in the first quarter, while inflation remained at the lower end of the SARB's target range, at 3% in June. The odds were tilted in favour of another rate cut, it said. However, the bank said the SARB is now targeting a 3% inflation rate, lower than the previous midpoint of 4.5%. 'This move could reshape the outlook for future interest rate decisions, and some homeowners may now be asking: Should I fix my bond rate now? The answer depends on your financial outlook," says Toni Anderson, the head of Home Services at Standard Bank. 'If you fix your rate now and the SARB starts hiking again, you've shielded yourself from future increases, which can bring much-needed predictability to your monthly expenses,' she explains. 'This could be a smart move if inflation remains sticky or if the target range is lowered, as such developments could affect future interest rate decisions.' However, she warned that there is also a downside. 'If rates continue to fall or stay low for longer, fixing your rate could mean you end up paying more than you would on a variable rate,' Anderson adds. 'That's why we encourage customers to consider their financial goals, risk tolerance, and how long they plan to stay in their home.' The head said as the economic outlook remains uncertain, the decision to fix or float should be based on personal risk tolerance and how long one plans to stay in their home. Independent Media Property

IOL News
14 hours ago
- IOL News
Khanya College faces eviction: A threat to Johannesburg's last public space for the working class
An audience sits in a darkened room covered in blankets at the Workers Museum in Newtown, Johannesburg. The City of Johannesburg plans to evict Khanya College from the historic Workers Museum Cottage to make way for administrative offices. Image: Boxer Ngwenya / Independent Newspapers The historic Khanya College could soon be forced to stop operating as the City of Johannesburg is planning to evict the institution from the Workers Museum Cottage. According to Khanya, the city wants to turn the cottage into an administrative office. The college said this decision threatens the closure of the city's last remaining public space that serves working people and communities in Johannesburg. On the other hand, the city said the agreement ended more than a year ago. The metro said this agreement was that Khanya College would use and occupy a particular building, in East Cottage, for a period of three years from 2021 to 2024. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ Khanya College was established in 1986, when the apartheid system was starting to unravel. It allowed students who were classified as 'black' by apartheid legislation the chance to gain access to universities classified as 'white'. Its history as a college that opened the doors of white universities to black students during apartheid holds three key lessons for higher education in South Africa today. These relate to empowering students through an African and global curriculum, encouraging critical thinking, and transforming universities and society. Today, the college has become a non-profit organisation rather than a formal college, with the primary goal of assisting the working-class and poor communities to respond to the challenges posed by the forces of economic and political globalisation. In 2006, Khanya, together with society organisations, successfully campaigned to save the workers' compound from demolition, and it was transformed into the Workers Museum. The museum is a rare public space that honours the lives and struggles of migrant black workers under apartheid capitalism. The college said given the depth and volume of its educational and cultural work with communities at the museum, in 2021, the City of Johannesburg gave it the East Cottage of the museum for use. The college said the space was a vibrant hub for communities and workers from across the city's townships, for debates and cultural engagements. This includes poetry, theatre, music, book launches, art exhibitions, seminars, and study groups. 'The Workers Museum cottages were never meant to be office space, and a form of living part of Joburg's social memory, a site for cultural work that challenges inequality, promotes community dialogue, and keeps working class history alive. Khanya College believes that the proposed eviction reflects a disregard for working-class public spaces and cultural life,' the institution said. City of Johannesburg spokesperson, Nthatisi Modingoane, said as the agreement ended in 2024, Khanya College was requested to vacate the cottage. Modingoane said consultations were held with the college and other stakeholders, and the college was offered alternative spaces for hosting meetings and programmes. 'Unfortunately, they turned them down. The city is still committed to accommodating the programmes that Khanya indicated would be affected by vacating the one cottage they use,' he said. Modingoane added that the city remains committed to the ongoing preservation of the Workers Museum Complex, including the black municipal compound and the associated cottages. 'Based around the historic compound dating from 1913, the Workers Museum will continue to operate as a public facility, with the original dormitories and exhibitions showing the harsh conditions faced by black migrant workers. 'Together with the main compound, the workers' cottages will be maintained, conserved, and sustainably used, in keeping with their heritage character and status,' Modingoane said. Meanwhile, the Khanya director, Dr Maria van Driel, said the college had a meeting with 18 organisations on July 19, and it was agreed that the space belongs to the working class and, therefore, Khanya needs to fight for the space. 'Therefore, suggestions were made that we need to work out an events programme for all the events that will take place at the cottages, do a petition and statement, and open the space for organisations who wish to use the space through Khanya, which currently acts as its custodian,' she said.