Need 2 weekend night blocks at Kolkata's Chingrighata to bridge viaduct gap: RVNL
Rail Vikas Nigam Ltd (RVNL) is awaiting Kolkata Police's approval for traffic blocks at Chingrighata to bridge a crucial gap in the New Garia-Airport Orange Line
KOLKATA: Rail Vikas Nigam Ltd (RVNL), which is constructing the
New Garia-Airport Orange Line
, has made a fresh plea to Kolkata Police to allow traffic blocks at Chingrighata on two weekend nights. This is necessary to plug the 366-metre gap in the 8 km viaduct between Ruby and Sector V.
Senior officers of Kolkata Police, led by the commissioner Manoj Verma, inspected the Chingrighata and Metropolitan sites over a fortnight ago. They indicated that the traffic block for the latter would be handed over soon for construction of a foot-overbridge (FOB) to access the Beleghata station. However, with no progress on the issue so far, RVNL has urged cops to either give the traffic block at Chingrighata first or provide it along with the one at Metropolitan so that the long-overdue work can be completed.
Once the Chingrighata gap is bridged, Orange Line's services can be extended from Ruby. At Sector V, the Orange Line has an interchange with the Green Line, to allow those living along the Bypass to travel to Esplanade and Howrah by metro.
RVNL has reasoned with the cops that while it will take 40 days to complete the FOB to connect Beleghata Metro station at Metropolitan with the other side of EM Bypass, launching the two spans (28m and 34m) across the Chingrighata crossing can be done in two weekend nights.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Upto 15% Discount for Salaried Individuals
ICICI Pru Life Insurance Plan
Get Quote
Undo
"RVNL proposes to complete the main girder-launching activity of each span in three nights - from Friday to Sunday, between 10 pm and 7 am, during two weekends," a Railways official said.
On Feb 2, girder-launching between piers 317, 318, and 319 atop Chingrighata was supposed to begin. RVNL has built a 600-metre lane for traffic diversion while the Ultandanga-bound flank is closed.
TOI reported on April 1 that RVNL is incurring an idling cost of Rs 9 lakh daily due to the stalled Metro construction at Chingrighata.
"Girder-launching at the busy Chingrighata crossing will become more complex if RVNL misses the ongoing dry spell," the Railways official said.
Lalbazar said "certain modifications in traffic furniture and some permissions were pending" regarding the Chingrighata site handover. "KMC must certify that the newly built road is fit for traffic movement," a senior officer said. Officers said the site can be given if Metro agrees to stick to deadlines. Joint CP (traffic) Rupesh Kumar has also urged RVNL to start construction of the underpass at Chingrighata.
The Orange Line, which now runs 5.4 km from New Garia to Ruby, will eventually link New Garia-Airport across 29 km.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
5 hours ago
- Time of India
Mumbai megablock alert: Western Railway slow line services hit today; night block for Metro 9 work between Mira Road-Bhayander
MUMBAI: For those travelling by the Western Railway suburban section, there is a megablock being undertaken on slow lines from 10.30 am to 3.35 pm between Churchgate and Mumbai Central stations today. During the block period, all slow line trains will run on fast lines between Churchgate and Mumbai Central station. Due to the block, some Up and Down local trains will remain cancelled, and some Churchgate-bound trains will be short-terminated or reversed from Bandra or Dadar. The WR will also undertake a major block on all lines between Mira Road and Bhayander stations in connection with the work of launching girders for Metro Line 9 during late-night hours. On the intervening night of Saturday and Sunday, a block of 1.45 hours was undertaken from 1.30 am to 3.15 am on Sunday. Similarly, on the intervening nights of Sunday and Monday, and Monday and Tuesday, a block will be undertaken from 1.45 am to 3 am on both days, a senior official said on Sunday.


Economic Times
7 hours ago
- Economic Times
Mumbai: Western Railways cracks down on ticketless travellers in AC locals, improves punctuality of trains
Live Events (You can now subscribe to our (You can now subscribe to our Economic Times WhatsApp channel A 15-member squad dedicated to AC local trains in Mumbai has been keeping a check on ticketless travellers for the past one far, 709 ticketless passengers have been fined in AC trains and the squad has collected Rs 2.30 lakh from May 30 to June 5. The squad will be further expanded as the officials believe the move has contributed in improving punctuality of locals, which cost about five times more than regular locals, have become crowded in peak hours due to ticketless commuters. This prevents the doors from closing and in turn there is a delay at the platforms. At least 10 per cent of the 40-50 local trains that are delayed on a daily basis are due to AC trains being stuck at various doors of AC trains are controlled by the guard, who gives a command from a panel in his cabin. The doors open and shut in a synchronised manned. An objection in the way of this process prevents the train from starting, causing average delays of 10 minutes to overall punctuality of trains during peak Western Railway operates 1,406 trains daily, of which 109 are of AC locals. On weekends, the railway operates 65 AC services.


Time of India
8 hours ago
- Time of India
Mumbai: Western Railways cracks down on ticketless travellers in AC locals, improves punctuality of trains
Live Events (You can now subscribe to our (You can now subscribe to our Economic Times WhatsApp channel A 15-member squad dedicated to AC local trains in Mumbai has been keeping a check on ticketless travellers for the past one far, 709 ticketless passengers have been fined in AC trains and the squad has collected Rs 2.30 lakh from May 30 to June 5. The squad will be further expanded as the officials believe the move has contributed in improving punctuality of locals, which cost about five times more than regular locals, have become crowded in peak hours due to ticketless commuters. This prevents the doors from closing and in turn there is a delay at the platforms. At least 10 per cent of the 40-50 local trains that are delayed on a daily basis are due to AC trains being stuck at various doors of AC trains are controlled by the guard, who gives a command from a panel in his cabin. The doors open and shut in a synchronised manned. An objection in the way of this process prevents the train from starting, causing average delays of 10 minutes to overall punctuality of trains during peak Western Railway operates 1,406 trains daily, of which 109 are of AC locals. On weekends, the railway operates 65 AC services.