6 months on, no work in sight at Venjaramoodu flyover site

6 months on, no work in sight at Venjaramoodu flyover site

Time of India13-06-2025
T'puram: Six months after inauguration of the construction of Venjaramoodu flyover, not a single brick was laid. The project, envisioned to ease congestion at one of the busiest junctions on the MC Road, was caught in a tangle of bureaucratic delays, primarily due to the failure to shift overhead electric lines and remove power poles from the proposed construction site.
As a result, daily commuters, pedestrians and local business owners are bearing the brunt of mounting traffic bottlenecks and prolonged uncertainty. The flyover project, awarded to Uralungal Labour Contract Cooperative Society (ULCCS), was seen as a vital infrastructure upgrade for the region. But since the formal inauguration, the ground reality remains unchanged.
"The delay in relocating electric cables underground and removing electric posts stalled the actual commencement of construction," confirmed a senior PWD official.
"We cannot proceed with piling or excavation until KSEB completes the necessary utility shifting. The coordination has taken longer than expected," the official added.
The flyover was expected to be a game-changer for traffic movement between
Thiruvananthapuram
and Kottarakkara. Vehicles pile up during peak hours, especially at the congested four-way intersection, leading to frequent gridlocks and safety concerns.
Locals and daily commuters are growing increasingly frustrated by the lack of visible progress.
"Every day it's the same chaos," said Sunitha Raj, a schoolteacher who commutes from Kilimanoor to Venjaramoodu. "They held an inauguration with great fanfare. Now it is just barricades and dust," she added.
Meanwhile, Vamanapuram MLA D K Murali, under whose constituency the project falls, told TOI that the delays were unfortunate but assured the public that the issue is being addressed. "This is a critical project for Venjaramoodu and the surrounding areas.
I have taken up the matter with both PWD and KSEB. We hope to resume the construction works by next month and the utility works will be completed within two weeks," he said.
He also added that the KSEB has to call a tender for the utility shifting works.
According to sources, the initial utility relocation proposal was caught in a back-and-forth between the PWD and KSEB regarding funding and clearances. Though officials insist that coordination meetings have been held, no clear timeline for commencement has been announced.
Follow more information on
Air India plane crash in Ahmedabad here
. Get
real-time live updates
on rescue operations and check
full list of passengers onboard AI 171
.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Stalin launches scheme for doorstep delivery of rations
Stalin launches scheme for doorstep delivery of rations

Time of India

time5 hours ago

  • Time of India

Stalin launches scheme for doorstep delivery of rations

Chennai: Chief minister M K Stalin on Tuesday launched 'Thaayumanavar Thittam' to deliver ration supplies directly to the homes of senior citizens aged above 70 years and persons with disabilities (PwD). Stalin visited beneficiaries' homes at Tondiarpet, Gopal Nagar, and Annai Sathya Nagar, to hand over rations and flagged off delivery vehicles, fitted with electronic weighing scales and e-PoS machines. Deputy CM Udhayanidhi Stalin flagged off vehicles in Chepauk and Triplicane and delivered rations to beneficiaries. When Meenakshi, an elderly woman, told Stalin that standing in a queue for an hour and carrying the weight back home made them dependent on others, Stalin said the trouble is set to end. "From now on, it will come to your doorstep," he assured her. Calling it a scheme close to his heart, he said it was designed to remove the last-mile barrier for those unable to visit ration shops. About 20 lakh senior citizens and 1.2 lakh PwD will get essential commodities such as rice and sugar delivered on the second Saturday and Sunday of every month. Govt will spend 35.92crore annually. "We believe our duty does not end with the announcement of a scheme; it extends to ensuring that every intended beneficiary receives its full benefits," Stalin said, urging the staff of the cooperative dept to ensure that the implementation is flawless. You Can Also Check: Chennai AQI | Weather in Chennai | Bank Holidays in Chennai | Public Holidays in Chennai | Gold Rates Today in Chennai | Silver Rates Today in Chennai Economic policy experts say the scheme's impact could extend well beyond convenience. "Doorstep delivery of essential commodities for vulnerable groups will indirectly boost household nutrition security, especially in low-income elderly households, and reduce health risks associated with irregular rations," said economist R Sivarajan. Earlier in the day, Stalin inaugurated fisheries infrastructure projects worth 177.16crore aiming to boost fish production, promote sustainable fishing, and ensure hygienic handling from catch to consumption while providing safe berthing for boats Stay updated with the latest local news from your city on Times of India (TOI). Check upcoming bank holidays , public holidays , and current gold rates and silver prices in your area.

Heritage buildings in Coimbatore get a makeover
Heritage buildings in Coimbatore get a makeover

Time of India

time2 days ago

  • Time of India

Heritage buildings in Coimbatore get a makeover

Coimbatore: Set up by the British in 1853, the Governor's Bungalow, a heritage building behind the highways office on Trichy Road in the city, was in a dilapidated state until recently. Tired of too many ads? go ad free now None would have called it an iconic building. Today, it is being restored to its past glory at a cost of Rs10.25 crore. Another heritage building that houses CCMA Govt Girls Higher Secondary School on Raja Street in the city is also getting a facelift at a cost of Rs7.60 crore. Both the British-era buildings are being renovated by the Heritage Wing of the Public Works Department (PWD) by preserving their original architectural style by employing century-old construction techniques. Both buildings come with the Madras terrace roof consisting of brick, lime mortar layers supported by wooden rafters and steel beams. Teak wood is used for doors, windows and steps. "The design features 2.5ft thick walls for temperature control, ceilings at a minimum height of 15ft and 10ft tall doors and windows for natural light and ventilation. Lime mortar binds the bricks and stones, enhancing durability and weather resistance," a PWD official said. The Governor's Bungalow was initially used by a landlord from Sulur as a rest house. Impressed by its architecture and location near Valankulam, Sir Arthur Lawley, then Governor of the Madras Presidency, stayed there during his visits to the region with the landlord's consent. The building was finally occupied by the Forest department until shifting to new premises in 2011. The record room remained there until 2013, and the building was vacated completely in 2016. Tired of too many ads? go ad free now Since then, it has been unused. "Over time, the building suffered severe damage. The Madras terrace roof lost strength, and wooden rafters decayed due to dampness. The ground floor roof partially collapsed. We are restoring the structure to its original form, strength and resilience," the official said. Constructed using locally sourced red bricks and stones, with steel imported from London, the heritage building that houses the school had structural issues such as seepage and crack. Its windows and doors were too not in proper use, the official said. "We completely replaced the roof, and the windows and doors were replaced with teak wood. The restoration involved traditional techniques, including Mughal-style smooth lime plaster and heritage-patterned tile flooring," he said. According to a school education department official, the heritage school building remains a symbol of Coimbatore's contribution to women's education. Though the exact year of construction is unknown, it once housed the Coimbatore Collector's office administrative building and a court. The institution began as a female normal school in January 1885, was upgraded to a high school in 1894, and later underwent several transformations before becoming a govt higher secondary school in 1978. The PWD official said the restoration of both buildings was expected to be completed within a month. "Now, the final finishing work is in progress."

Trees transplanted for flyover construction sprout new leaves
Trees transplanted for flyover construction sprout new leaves

Time of India

time5 days ago

  • Time of India

Trees transplanted for flyover construction sprout new leaves

1 2 3 4 5 6 Guwahati: Fresh leaves have emerged on several trees recently translocated from Ambari to Lachit Ghat along Mahatma Gandhi Road, as part of the flyover construction project connecting Noonmati to Ambari. The Public Works Department, in collaboration with a Delhi-based firm, started translocation of over 70 trees two months ago. Dimpal Saikia, PWD executive engineer, said during this phase, the trees will receive regular watering to keep the carved root zone moist and also organic manure to keep pests and insects away. "Additionally, the soil will be covered with a protective layer, so that its moisture can be retained, helping in their growth. A party has been given the contract of maintaining the trees for three years," she said. The Rs 25-lakh project, managed by DIMTC Services, aims for a 95% survival rate, despite public skepticism over the translocation's scientific basis and survival odds. Zakir Alam of DIMTC said, "If the maintenance is done right, significant growth can be seen." The translocation of these trees come under fire from critics who argue the process was executed unscientifically. They said future relocations must be preceded by comprehensive studies. Stay updated with the latest local news from your city on Times of India (TOI). Check upcoming bank holidays , public holidays , and current gold rates and silver prices in your area. Get the latest lifestyle updates on Times of India, along with Raksha Bandhan wishes , messages and quotes !

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store