MTA project to modernize subway line could be millions over budget and years late: report
The project for the crosstown train, or G line, could be as much as two years behind schedule as the beleaguered Big Apple transit system works to upgrade its signal system across numerous routes that even include newer trains.
The latest 5G technology for the communication-based train control (CBTC) would provide faster and more dependable service, MTA officials have said – as riders face a possible fare hike next year.
Advertisement
3 The Metropolitan Transportation Authority is a whopping $77 million over budget to modernize a crucial subway line, an independent agency insisted this week — as the technology on newer trains is already becoming useless.
Luiz C. Ribeiro for New York Post
'Not every project that we've done in the last five years has been on time and on budget,' MTA chief Janno Lieber said during a press conference Wednesday about the possible additional expenses and delays.
Costs attached to the G line could balloon to as high as $715 million instead of the $624 million pegged by the MTA, an independent engineering consultant stated in a report delivered to the MTA board Monday.
Advertisement
But that estimation from the IEC is in sharp contrast with the MTA's own internal projections, which still has it running on budget.
The F line in Brooklyn is expected to overrun costs by $22 million while the Queens Boulevard line could blow roughly $28 million past budget, according to the report.
But the MTA stated it believes those projects are either under budget or in line with the spending plan, when using its own projections.
3 The plan to revolutionize the G line is currently two years behind schedule.
Robert Miller
Advertisement
The independent consultant also stated all of the revamped lines won't be wrapped up on schedule.
The G line could be done by 2029 instead of 2027 with MTA construction head Jamie Torres-Springer stating any extended timeline can be attributed to the CBTC technology that needs to replace 4G tech that are even on newer trains.
'While all of the physical work to outfit the G train is going smoothly and is on time, a new technology that we need to adopt for CBTC across all of our subway lines,' he said, 'not just for the G train, but starting with the G train, it's a 5G radio that would be on subway cars to replace obsolete radio equipment, and that will take longer than the work that we're doing on the G itself.'
3 MTA officials said that with 5G technology for the communication-based train control (CBTC), it should result in faster and more reliable services for subway lines such as the G and other train lines across the system.
Annie Wermiel / NYPost
Advertisement
Work on the G line has led to some travel headaches for commuters this summer after disruptions were even worse last year, though further outages were not expected to handle the signal swap, Torres-Springer.
The F line in Brooklyn would be done by September 2025 – three years later than the initial completion date while the A, C, E lines on Eighth Avenue will be finished by 2027 and the Queens Blvd line won't be done before 2028 – that would make both projects two-years late, according to the report.
Lieber, in his Wednesday press conference, said the agency was not shying away from the delays while stressing the pushing out the projects will lead to more benefits.
'But we own every time we run late or we run over budget, we'll always highlight the fact that we've made a lot of progress on big projects on that,' the MTA chief said in response to the independent report.
'And we will continue to push forward on these projects that are really important. And you see, we funded a lot more signal work in the coming capital plan.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


New York Post
2 hours ago
- New York Post
Long-promised Brooklyn-Queens rail link is finally moving forward — but won't be complete till the 2030s
It's finally getting on track. The long-awaited light rail connection between Brooklyn and Queens has now moved into active development, Gov. Kathy Hochul announced Friday — but the project won't be complete until at least the 2030s. Hochul, during an event along the abandoned rail line that will become the Interborough Express, or IBX, celebrated the MTA's board this week advancing the expected $5.5 billion project into its design phase. 'We're turning these old tracks into something remarkable,' she crowed. 'A clean, fast, 14-mile light rail line – a connection between Brooklyn and Queens like never before.' 5 Gov. Kathy Hochul announced Friday that a long-promised Brooklyn-Queens rail link is now in its design phase. James Messerschmidt She also highlighted estimates that an end-to-end trip along the line will only be 32 minutes. 'Riders will save 30 minutes each way. If you're a round-trip commuter, guess what? That's an hour back in your life.' Proposals to build a Brooklyn-Queens rail service have percolated for nearly three decades, but only seriously advanced when Hochul announced in 2022 that an underused freight line would be converted into the Interborough Express. The planned line would create 19 stations, connect 17 subway lines, 50 bus routes and two Long Island Rail Road hubs along its track from Sunset Park, Brooklyn to Jackson Heights, Queens, officials envision. The IBX would also be the Big Apple's first light rail line, as well the first end-to-end rapid transit built entirely in the city since the line that became the G train opened in 1937, officials said. 5 The Interborough Express will run from Sunset Park to Jackson Heights. MTA/ Governor Hochul 5 The IBX will run from Brooklyn Army Terminal to Roosevelt Avenue. MTA 5 The project is expected to cost $5.5 billion and be the city's first light rail line. MTA Drone footage and photos released by MTA officials Friday give a bird's-eye view of the proposed route, including the LIRR-owned Bay Ridge Branch and the CSX-owned rail line Fremont Secondary. The route winds through tree-lined, largely forgotten rail beds in both boroughs, with several bridges and tunnels that could present design difficulties, officials said. But beyond broad strokes and a $2.75 billion commitment so far by Hochul, no serious engineering and design work had been done on the project – until MTA board members Wednesday selected Jacobs and HDR to be design and engineering team, with a $166 million contract. 'Thanks to $166 million dollar state investment, that means a lot of planning is going to occur – looking at the stations, tracks, vehicles signals – so we can get shovels in the ground and make this become a reality,' Hochul said. 5 The route follows an existing, although largely forgotten rail line. MTA / Trent Reeves The design phase will be the last before construction begins, officials said. The project is expected to be completed in the 2030s. Hochul promised that whenever it's finished that New Yorkers will have fewer travel hassles flitting between Brooklyn and Queens. 'The outer boroughs are now joined so that there's not a requirement that if you want to go see your mother in Queens from Brooklyn that you won't have to go into Manhattan first,' she said.
Yahoo
3 hours ago
- Yahoo
Metalla Royalty & Streaming Ltd. (MTA) is a Great Momentum Stock: Should You Buy?
Momentum investing is all about the idea of following a stock's recent trend, which can be in either direction. In the "long context," investors will essentially be "buying high, but hoping to sell even higher." And for investors following this methodology, taking advantage of trends in a stock's price is key; once a stock establishes a course, it is more than likely to continue moving in that direction. The goal is that once a stock heads down a fixed path, it will lead to timely and profitable trades. Even though momentum is a popular stock characteristic, it can be tough to define. Debate surrounding which are the best and worst metrics to focus on is lengthy, but the Zacks Momentum Style Score, part of the Zacks Style Scores, helps address this issue for us. Below, we take a look at Metalla Royalty & Streaming Ltd. (MTA), which currently has a Momentum Style Score of B. We also discuss some of the main drivers of the Momentum Style Score, like price change and earnings estimate revisions. It's also important to note that Style Scores work as a complement to the Zacks Rank, our stock rating system that has an impressive track record of outperformance. Metalla Royalty & Streaming Ltd. currently has a Zacks Rank of #2 (Buy). Our research shows that stocks rated Zacks Rank #1 (Strong Buy) and #2 (Buy) and Style Scores of "A or B" outperform the market over the following one-month period. You can see the current list of Zacks #1 Rank Stocks here >>> Set to Beat the Market? In order to see if MTA is a promising momentum pick, let's examine some Momentum Style elements to see if this company holds up. Looking at a stock's short-term price activity is a great way to gauge if it has momentum, since this can reflect both the current interest in a stock and if buyers or sellers have the upper hand at the moment. It's also helpful to compare a security to its industry; this can show investors the best companies in a particular area. For MTA, shares are up 10.85% over the past week while the Zacks Mining - Miscellaneous industry is up 1.38% over the same time period. Shares are looking quite well from a longer time frame too, as the monthly price change of 2.33% compares favorably with the industry's 0.71% performance as well. Considering longer term price metrics, like performance over the last three months or year, can be advantageous as well. Over the past quarter, shares of Metalla Royalty & Streaming Ltd. have risen 33.33%, and are up 39.44% in the last year. In comparison, the S&P 500 has only moved 14.12% and 16.19%, respectively. Investors should also take note of MTA's average 20-day trading volume. Volume is a useful item in many ways, and the 20-day average establishes a good price-to-volume baseline; a rising stock with above average volume is generally a bullish sign, whereas a declining stock on above average volume is typically bearish. Right now MTA is averaging 360,833 shares for the last 20 days.. Earnings Outlook The Zacks Momentum Style Score encompasses many things, including estimate revisions and a stock's price movement. Investors should note that earnings estimates are also significant to the Zacks Rank, and a nice path here can be promising. We have recently been noticing this with MTA. Over the past two months, 1 earnings estimate moved higher compared to none lower for the full year. This revision helped boost MTA's consensus estimate, increasing from -$0.01 to $0.00 in the past 60 days. Looking at the next fiscal year, 1 estimate has moved upwards while there have been no downward revisions in the same time period. Bottom Line Given these factors, it shouldn't be surprising that MTA is a #2 (Buy) stock and boasts a Momentum Score of B. If you're looking for a fresh pick that's set to soar in the near-term, make sure to keep Metalla Royalty & Streaming Ltd. on your short list. Want the latest recommendations from Zacks Investment Research? Today, you can download 7 Best Stocks for the Next 30 Days. Click to get this free report Metalla Royalty & Streaming Ltd. (MTA) : Free Stock Analysis Report This article originally published on Zacks Investment Research ( Zacks Investment Research Error in retrieving data Sign in to access your portfolio Error in retrieving data Error in retrieving data Error in retrieving data Error in retrieving data
Yahoo
3 hours ago
- Yahoo
NextNav and Oscilloquartz Partner to Advance 5G Based Timing Solutions for Critical Infrastructure
New collaboration to demonstrate how terrestrial 5G-based timing can provide scalable solutions to complement and backup GPS RESTON, Va., August 01, 2025--(BUSINESS WIRE)--NextNav, a leader in resilient Positioning, Navigation, and Timing (PNT) technologies, today announced a strategic partnership with Oscilloquartz, an Adtran company and global leader in time synchronization solutions. The companies will showcase how 5G-powered terrestrial PNT and Oscilloquartz's proven timing technology could enable a scalable complement and backup to GPS capable of keeping critical systems like data centers, utilities, and emergency services running during outages. This collaboration is intended to lead to a complementary and backup timing service layer to GPS, leveraging existing 5G infrastructure to distribute accurate, UTC-aligned time both indoors and outdoors. By fusing Oscilloquartz's best-in-class synchronization equipment with NextNav's terrestrial 5G PNT solution, the partnership will enable greater resiliency by adding an additional timing source to ensure end users are not dependent on a single timing source. "This partnership is a foundational step toward realizing a systems-of-systems approach to PNT resiliency that helps address an urgent national security and public safety need," said Sidd Chenumolu, Chief Business Development Officer. "Together with Oscilloquartz, we're enabling diverse, standards-based timing sources to ensure continuity and security for critical applications — from emergency services to utilities." This joint effort responds to a growing market demand for secure, redundant timing solutions amid real-world threats to GPS. By aligning with the ongoing FCC efforts to identify complementary PNT technologies, NextNav and Oscilloquartz are setting the stage to enable a terrestrial 5G-powered 3D PNT solution that advances both private-sector innovation and supports national security priorities. "Our expertise in delivering resilient synchronization solutions built on diverse cPNT sources makes this collaboration with NextNav a natural fit," commented Gil Biran, GM of Oscilloquartz, Adtran. "Together, we're helping to strengthen national infrastructure with secure, GPS-independent timing that supports continuity even in the face of GNSS disruption." The demonstration of integrated terrestrial timing will serve as a proof point for 5G-based timing synchronization and serves as a template for future widescale deployments. It's a forward-looking example of how the timing industry and NextNav can work together to reduce reliance on a single source of timing from GPS and increase national PNT resilience. About NextNav NextNav Inc. (Nasdaq: NN) is a leader in next-generation 3D Positioning, Navigation, and Timing (PNT) solutions. As the nation's largest license holder in a spectrum band expressly designated for terrestrial positioning services, NextNav is uniquely positioned to enable a widescale terrestrial complement and backup to GPS. Leveraging licensed low-band spectrum and the global 5G ecosystem, NextNav is focused on delivering an accurate, reliable, and resilient 3D PNT solution to protect national security, public safety, and the economy. Learn more at For more information, please visit or follow NextNav on X at or LinkedIn at About Adtran ADTRAN Holdings, Inc. (NASDAQ: ADTN and FSE: QH9) is the parent company of Adtran, Inc., a leading global provider of open, disaggregated networking and communications solutions that enable voice, data, video and internet communications across any network infrastructure. From the cloud edge to the subscriber edge, Adtran empowers communications service providers around the world to manage and scale services that connect people, places and things. Adtran solutions are used by service providers, private enterprises, government organizations and millions of individual users worldwide. ADTRAN Holdings, Inc. is also the majority shareholder of Adtran Networks SE, formerly ADVA Optical Networking SE. Find more at Adtran, LinkedIn and X. View source version on Contacts Investor Contact:IR@ Media Contact:NNmedia@