Plans afoot to resume SLBC tunnel work soon as Irrigation Dept. ropes in experts from Army

Plans afoot to resume SLBC tunnel work soon as Irrigation Dept. ropes in experts from Army

The Hindu2 days ago
HYDERABAD
The Irrigation Department is planning to resume work at the earliest on the Srisailam Left Bank Canal (SLBC) tunnel, which was halted on February 22 following collapse of the tunnel roof, about 14 km inside from the mouth, near Domalapenta, in Nagarkurnool district, burying 8 workers alive. Another 10 km tunnel is to be excavated to meet the work done from the other side.
This was decided at a meeting held here on Saturday by Minister for Irrigation and Civil Supplies N. Uttam Kumar Reddy for an in-depth review of the pending work. The 43.931 km tunnel work was taken up from two sides – from Srisailam reservoir side near Domalapenta, and from Dindi balancing reservoir on the other side.
The work was stopped in 2023 following a problem in the tunnel boring machine (TBM) from Dindi reservoir side. It was stopped in the Domalapenta side much earlier, again due to some problems in the TBM. It was resumed on February 22 after replacing some parts of the TBM in the Domalapent end, but within four days, the roof collapse incident took place.
Only two of the 8 bodies were recovered before the rescue operation was abandoned in April-end, following the advice of the experts over the danger in taking up debris removal in the last 50 meters of the tunnel excavated from Domalapenta side.
The Minister stated that drilling and blasting (excavation) was to be taken up in an estimated 10 km length for completing the tunnel. Terming SLBC lifeline for Southern parts of Telangana, he said its completion must be treated as a top priority and executed with urgency.
He explained that the SLBC tunnel would be taken up/resumed using the latest electromagnetic survey technology in collaboration with the National Geophysical Research Institute (NGRI) and the Geological Survey of India (GSI). To ensure precise planning and seamless execution, he instructed the officials to expedite the (aerial) LiDAR survey.
Earlier in the day, he had a meeting with a team of NGRI scientists to finalise the technical modalities of the survey. He reiterated that cost would not be a constraint, but highest quality and speed must be maintained at every level.
The meeting also marked the first formal interaction with Col. Parikshit Mehra, an acclaimed tunnel engineering expert who recently joined the Irrigation Department on deputation. The Minister expressed confidence that Col. Mehra's expertise would help resolve long-pending technical challenges and fast-track completion of the SLBC and other key tunnel projects.
He stated that Gen. Harpal Singh, former Engineer-in-Chief of the Indian Army, too would be appointed as an honorary Advisor in the Irrigation Department soon to strengthen the department's technical capacity and tunnel execution capabilities.
The Minister also reviewed the progress of de-siltation and de-sedimentation works across the Krishna and Godavari basins, which he said were essential to enhance/restore the storage capacity and improve water management. He pointed out that water storage capacity of several irrigation projects had come down drastically due to sedimentation and silt accumulation.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Plans afoot to resume SLBC tunnel work soon as Irrigation Dept. ropes in experts from Army
Plans afoot to resume SLBC tunnel work soon as Irrigation Dept. ropes in experts from Army

The Hindu

time2 days ago

  • The Hindu

Plans afoot to resume SLBC tunnel work soon as Irrigation Dept. ropes in experts from Army

HYDERABAD The Irrigation Department is planning to resume work at the earliest on the Srisailam Left Bank Canal (SLBC) tunnel, which was halted on February 22 following collapse of the tunnel roof, about 14 km inside from the mouth, near Domalapenta, in Nagarkurnool district, burying 8 workers alive. Another 10 km tunnel is to be excavated to meet the work done from the other side. This was decided at a meeting held here on Saturday by Minister for Irrigation and Civil Supplies N. Uttam Kumar Reddy for an in-depth review of the pending work. The 43.931 km tunnel work was taken up from two sides – from Srisailam reservoir side near Domalapenta, and from Dindi balancing reservoir on the other side. The work was stopped in 2023 following a problem in the tunnel boring machine (TBM) from Dindi reservoir side. It was stopped in the Domalapenta side much earlier, again due to some problems in the TBM. It was resumed on February 22 after replacing some parts of the TBM in the Domalapent end, but within four days, the roof collapse incident took place. Only two of the 8 bodies were recovered before the rescue operation was abandoned in April-end, following the advice of the experts over the danger in taking up debris removal in the last 50 meters of the tunnel excavated from Domalapenta side. The Minister stated that drilling and blasting (excavation) was to be taken up in an estimated 10 km length for completing the tunnel. Terming SLBC lifeline for Southern parts of Telangana, he said its completion must be treated as a top priority and executed with urgency. He explained that the SLBC tunnel would be taken up/resumed using the latest electromagnetic survey technology in collaboration with the National Geophysical Research Institute (NGRI) and the Geological Survey of India (GSI). To ensure precise planning and seamless execution, he instructed the officials to expedite the (aerial) LiDAR survey. Earlier in the day, he had a meeting with a team of NGRI scientists to finalise the technical modalities of the survey. He reiterated that cost would not be a constraint, but highest quality and speed must be maintained at every level. The meeting also marked the first formal interaction with Col. Parikshit Mehra, an acclaimed tunnel engineering expert who recently joined the Irrigation Department on deputation. The Minister expressed confidence that Col. Mehra's expertise would help resolve long-pending technical challenges and fast-track completion of the SLBC and other key tunnel projects. He stated that Gen. Harpal Singh, former Engineer-in-Chief of the Indian Army, too would be appointed as an honorary Advisor in the Irrigation Department soon to strengthen the department's technical capacity and tunnel execution capabilities. The Minister also reviewed the progress of de-siltation and de-sedimentation works across the Krishna and Godavari basins, which he said were essential to enhance/restore the storage capacity and improve water management. He pointed out that water storage capacity of several irrigation projects had come down drastically due to sedimentation and silt accumulation.

Godavari water released from SRLIP's first pump house
Godavari water released from SRLIP's first pump house

The Hindu

time12-07-2025

  • The Hindu

Godavari water released from SRLIP's first pump house

To prevent withering of standing crops in the ayacut of the Nagarjuna Sagar Project (NSP) zone II in the erstwhile Khammam district, Godavari water has been released from the Sitarama Lift Irrigation Project (SRLIP)'s first pump house at BG Kothuru village in Bhadradri Kothagudem district on Saturday. According to official sources, the decision has been taken to release water from the SRLIP's first pump house following representations made by several farmers' organisations to save the standing crops in the ayacut under the NSP left canal system, citing early sowing of crops in the current kharif season. The associations representing the NSP ayacutdars sought immediate release of Godavari water to protect the standing crops as Krishna water from the Nagarjunasagar dam is yet to reach the NSP zone II. Sources added that Agriculture Minister Tummala Nageswara Rao apprised Irrigation Minister N. Uttam Kumar Reddy of the situation following which the latter issued direction to the officials to release water from the SRLIP's first pumphouse. The trial run of the SRLIP first pump house was conducted successfully in June last year. The State government has laid special focus on the SRLIP to complete the project on a fast-track mode.

District-Level Training Held for Water Resources Census: Emphasis on Accurate, Paperless Data Collection
District-Level Training Held for Water Resources Census: Emphasis on Accurate, Paperless Data Collection

Hans India

time06-07-2025

  • Hans India

District-Level Training Held for Water Resources Census: Emphasis on Accurate, Paperless Data Collection

Gadwal: Chief Planning Officer Yoganand emphasized that precise and unbiased data collection is essential for effective government policy-making. He instructed officials to ensure that every detail is recorded comprehensively and impartially. Speaking at the district-level training program held on Saturday at the IDOC Video Conference Hall, Yoganand addressed officials as part of the 7th Minor Water Resources Census and the 2nd Water Bodies Census for the agricultural year 2023–2024. He highlighted the importance of these censuses, stating that collecting detailed information on groundwater sources, surface water bodies, ponds, tanks, check dams, dug wells, and other minor irrigation sources in villages would provide a holistic perspective on rural water security. The 2023–24 census stands out for a significant advancement—for the first time, data will be recorded through a 'Mobile App'-based, paperless system, using LGD (Local Government Directory) codes for every village. Yoganand further informed that the census of dug wells will be conducted with the assistance of the Groundwater Department, while the enumeration of medium and major irrigation sources will be carried out under the supervision of the Irrigation Department. Detailed training was provided on schedule filling procedures, technical guidelines, data accuracy, and timely reporting to ensure a smooth enumeration process. Officials from the District Irrigation Department and Groundwater Department attended the program and shared key instructions and suggestions. They emphasized that the training sessions were designed to give clear understanding and guidance to all participants involved in the census. The Chief Planning Officer and associated officials called on all staff to ensure that the data collected meets the quality and accuracy expected by the government. Participants of the training included planning and statistical officers from all mandals, sub-statistical officers, and other relevant field functionaries. This initiative is expected to play a pivotal role in understanding local water resources and contribute meaningfully to water security and sustainable irrigation planning across rural Telangana.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store