Latest news with #SKKunakJaya


Daily Express
16-07-2025
- Business
- Daily Express
Works Ministry hopes new SK Kunak Jaya can be completed ahead of time
Works Ministry hopes new SK Kunak Jaya can be completed ahead of time KUNAK: The Works Ministry has reminded the contractor handling the new SK Kunak Jaya project to complete construction according to schedule. Deputy Works Minister Datuk Seri Ahmad Maslan said the project, currently at 18 per cent physical progress, must meet all specifications, cost limits and timelines. Advertisement He expressed hope that the RM24.29 million project might even be completed ahead of time during his visit to the site on Wednesday. Scheduled to be completed in 126 weeks by 9 November 2026, the design-and-build project includes 12 classrooms, an administrative block, science and computer labs, a canteen, surau, special needs facilities and supporting infrastructure. SPONSORED CONTENT The main contractor, Merak Sutra Sdn Bhd, is carrying out the project under the close supervision of the Public Works Department and its Special Project Team 2, with the Ministry confident the new facility will benefit over 500 pupils and school staff in Kunak.


The Star
16-07-2025
- Business
- The Star
Over 200 JKR-supervised construction projects ahead of implementation schedule
KUNAK: More than 200 of the 800 construction projects supervised by the Public Works Department (JKR) nationwide are currently ahead of schedule or Ahead of Time (AOT). Deputy Works Minister Datuk Seri Ahmad Maslan ( pic ) said this took into account projects that were ahead of schedule by more than a week to 10 days. "But this 200 is still not enough, while the remaining construction projects are not on schedule and late projects, and with three per cent being sick projects. "It must be ensured that any project, especially in Sabah, be completed on schedule or AOT. When the project is late, among the plans that the contractor should do is to create extra work time, for example on weekends, including creating double shifts of work per day," he said. He said this to reporters after reviewing the progress of the new building construction project covering 12 classrooms and other facilities at SK Kunak Jaya here Wednesday (July 16). Ahmad also suggested that relevant public works officers visit and learn about construction aspects abroad, such as China and India, which complete construction projects quickly using the latest technology, including the 'prefabricated modular system'. In Sabah, ahead of schedule are five dilapidated school projects, including two in Semporna and one each in Tawau, Kota Belud and Pensiangan. Meanwhile, Ahmad said there is a project to build a new building at SK Kunak Jaya, costing RM24.3mil, and expected to be completed in November, has now reached 18 per cent of the physical progress. He added that the project, which began in June 2024, involves the construction of 12 classrooms, an administration block, a science room, workshop, computer laboratory, surau and canteen, and will benefit more than 500 students at the school. - Bernama


The Star
16-07-2025
- Business
- The Star
Construction of new block, amenities at SK Kunak Jaya on track, will benefit 500 pupils, says Ahmad Maslan
KOTA KINABALU: The construction of a new classroom block and other amenities at SK Kunak Jaya is expected to benefit 500 pupils once works are completed. From a site visit by the Deputy Works Minister Datuk Seri Ahmad Maslan on Wednesday (July 16), it was found that physical construction works have gone up by 18%, with completion expected by November next year. The ministry issued a statement stating that this new block will house 12 classrooms, while another block will house the administrative office, science room, computer lab, surau, canteen and even disabled-friendly amenities as well as other supporting infrastructure. Started on Jun 11, 2024, this project worth RM24.9mil is handled by the federal Works Ministry as the implementing agency, with strict monitoring by the Special Projects 2 Team, under JKR Malaysia, it said. Among the monitored scopes would include project progress, cost and quality specifications, it added. This project is important to cater to the growing number of students enrolling into the school as well and to provide a conducive study and work environment for students and teachers alike.