Concreting bow-string steel bridge surface begins at Indrali in Udupi
The National Highways Division of the Karnataka Public Works Department (NH-PWD) had completed the erection of the bow-string steel bridge on May 13.
Subsequent heavy rains, however, did not allow the department to concrete the surface of the bridge. With rains abating for a week on the coast, the NH-PWD commenced the concreting work.
Mr. Poojary told reporters that the concreting work might get completed in about 10 days if it does not rain heavily. About 25 more days are required for curing the laid concrete. If everything goes well, the additional RoB should open for traffic by the end of the month, the MP said.
NH-PWD Assistant Executive Engineer Manjunath Naik and others accompanied the MP.
The commissioning of the additional RoB would eliminate the bottleneck on the four-lane highway between Udupi and Manipal on NH 169A, which experiences heavy traffic. Time and again, the public had voiced their anguish over the delay in the completion of the RoB, because of which many accidents had happened and lives were lost.
Started in 2018
Work on the Indrali additional RoB commenced in 2018 when a part of NH 169A between Udupi and Manipal was expanded to four lanes. The work moved at a snail's pace due to changes in design, bureaucratic delays and other issues, testing the patience of people.
As vehicles had to change lanes from the four-lane highway and move on the two-lane existing RoB, many accidents were reported on the stretch, prompting the district administration to threaten criminal action against the departments and the contractor concerned.
The then MP for Udupi-Chikkamagaluru, Shobha Karandlaje, and the incumbent Mr. Poojary visited the site several times to follow up with officials in a bid to speed up the project.
The total project cost was pegged at ₹9 crore when it was launched.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Hindu
a day ago
- The Hindu
Concreting bow-string steel bridge surface begins at Indrali in Udupi
Concreting the surface of Railway Over Bridge (RoB) atop Mangaluru-Mumbai Railway line on Malpe-Tirthahalli National Highway 169 at Indrali in Udupi began on Sunday, in the presence of MP for Udupi-Chikkamagaluru, Kota Srinivas Poojary. The National Highways Division of the Karnataka Public Works Department (NH-PWD) had completed the erection of the bow-string steel bridge on May 13. Subsequent heavy rains, however, did not allow the department to concrete the surface of the bridge. With rains abating for a week on the coast, the NH-PWD commenced the concreting work. Mr. Poojary told reporters that the concreting work might get completed in about 10 days if it does not rain heavily. About 25 more days are required for curing the laid concrete. If everything goes well, the additional RoB should open for traffic by the end of the month, the MP said. NH-PWD Assistant Executive Engineer Manjunath Naik and others accompanied the MP. The commissioning of the additional RoB would eliminate the bottleneck on the four-lane highway between Udupi and Manipal on NH 169A, which experiences heavy traffic. Time and again, the public had voiced their anguish over the delay in the completion of the RoB, because of which many accidents had happened and lives were lost. Started in 2018 Work on the Indrali additional RoB commenced in 2018 when a part of NH 169A between Udupi and Manipal was expanded to four lanes. The work moved at a snail's pace due to changes in design, bureaucratic delays and other issues, testing the patience of people. As vehicles had to change lanes from the four-lane highway and move on the two-lane existing RoB, many accidents were reported on the stretch, prompting the district administration to threaten criminal action against the departments and the contractor concerned. The then MP for Udupi-Chikkamagaluru, Shobha Karandlaje, and the incumbent Mr. Poojary visited the site several times to follow up with officials in a bid to speed up the project. The total project cost was pegged at ₹9 crore when it was launched.


New Indian Express
2 days ago
- New Indian Express
4,398 nominations from PwDs for rural local body seats in Tamil Nadu
CHENNAI: In the first phase of nominating a person with disability (PwD) to rural local bodies, the Rural Development and Panchayat Raj department has received a total of 4,398 nomination applications from 2,901 village panchayats in nine districts of the state. The Tamil Nadu Panchayats (Second Amendment) Act, 2025, was amended recently to nominate a person with disability in every village panchayat, panchayat union council and district panchayat. The deadline for submission of applications ended on July 31. In the nine district panchayats, 63 nomination applications have been received, an average of seven per district panchayat. For the 74 panchayat unions where nominations were called for, 462 applications were received, an average of six per panchayat union. In the first phase, the state is in the process of filling 2,985 nominations in rural local bodies. As the next step, the district level committee, chaired by the personal assistant (development) to the collector, will scrutinise the applications and based on the 'service and qualification' of the applicants, it will forward its recommendations to the collector. The collector will be issued with a standard operating procedure for the nominations. As per the government order issued by the department on June 26 for the nomination of persons with disabilities, equal representation is to be provided 'as far as possible' for persons with all types of disabilities and for women as well. 'The number of applications has exceeded our expectations in the first phase. We'll call for nominations in the remaining local bodies in the subsequent phases,' an official said.


Time of India
2 days ago
- Time of India
Bethora road fixed after saplings-in-potholes threat
Ponda: Days after the residents of Bethora, in Ponda taluka, threatened to plant saplings in potholes if the village road is not repaired within a week, the PWD resurfaced the road facing the industrial estate. At the Bethora-Nirankal-Conxem-Codar panchayat gram sabha last Sunday, the villagers had raised the issue of washed-away roads. They had threatened to protest against the authorities by planting the saplings. Sarpanch Madhu Khandeparkar had said that the panchayat is aware of the condition of the main road connecting the village to Ponda town. The road has now been tarred by the PWD. The road had developed several potholes and had become life-threatening to commuters. Get the latest lifestyle updates on Times of India, along with Friendship Day wishes , messages and quotes !