GMRL plans to revise cost of Gurugram Metro project to ₹10,000 crore
Gurugram: The Gurugram Metro Rail Limited (GMRL) has proposed to revise the cost of the Gurugram Metro project from the already approved ₹5,452 crore to double the amount at over ₹10,000 crore. The proposal to be submitted in the next GMRL board meeting, indicates that the cost revision is being done since the sanctioned project cost was based on 2019 rates and six years have elapsed, officials said.
The provisions of the detailed project report (DPR) allow 5 per cent per annum escalation in the project, GMRL officials added.
GMRL has also reworked estimates for the cost of setting up stations, adding the rolling stacks and change in GST rates.
The Gurugram Metro project is now likely to be completed for over ₹10,000 crore instead of the earlier approved ₹5,452 crore, according to the revised estimate proposed by GMRL. The additional costs being proposed by the metro corporation are on account of changes in the cost of alignment and formation from the sanctioned ₹1100 crore to over ₹1700 crore, increase in cost of station buildings from the sanctioned ₹756 crore to over ₹1350 crore. The cost of building the depot has increased from the sanctioned ₹80 crore to over ₹200 crore. Another major increase is the cost of acquiring the rolling stock from the sanctioned ₹480 crore to ₹1250 crore, officials said.
According to the GMRL proposal, the sanctioned cost of the project is ₹5,452 crore while the revised cost of the project will be over ₹9,800 crore, with an additional spur to the Gurugram railway station that will cost over ₹400 crore, taking the total cost of the project to over ₹10,000 crore.
'The proposal is likely to be submitted for the next GMRL board meeting scheduled to be held on June 16,' a senior government official, requesting anonymity said.
The metro corporation's proposal has justified the increase in the project cost stating that there has been price escalation in the last six years since 2019, when the price was set for the project estimate. It added that GST rates have been increased from 12% to 18% since then.
The proposal further said that another reason for the increase in the cost of the metro project is the non-availability of rapid metro infrastructure which was considered while calculating the original cost. There is also an increase in the requirement of coaches for the Gurugram metro project, while the approved DPR took into account only 60 coaches. A new spur has been added to connect the Gurugram railway station with the Sector 5 metro station, the proposal said.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Hindustan Times
4 hours ago
- Hindustan Times
GMRL seeks utilities shifting for Metro rail near Hero Honda Chowk
The Gurugram Metro Rail Ltd (GMRL) has asked the Gurugram Metropolitan Development Authority (GMDA) to expedite shifting of utilities and structures on the road stretch between Hero Honda Chowk and Umang Bhardwaj Chowk at the earliest, as the construction of Metro project is likely to commence soon. The metro corporation has urged for early handing over of the land since any delay could hamper the metro construction. The metro route will pass through the left side of this road at elevated levels, according to the project plan. A June 9 letter by a senior GMRL official said that the construction work of the metro corridor priority-1 from Millennium City Centre to Sector 9, Gurugram with an extension spur to Dwarka Expressway is likely to start immediately. Therefore, delayed construction of road from Hero Honda Chowk to Umang Bhardwaj Chowk flyover by NHAI is a point of deep apprehension to GMRL because of encumbrances that include shifting of electric sub- station, clearance of Himgiri Ashram site and Bikaner Mishtaan Bhandhar, removal of electrical lines by Dakshin Haryana Bijli Vitran Nigam (DHBVN) & NHAI, and dismantling of CNG pump and shifting it to new location, it said. 'It is once again requested to resolve the bottlenecks and hand over part of the ROW (right of way) in the Utility Corridor to GMRL free from all obstructions. In case, the ROW under Metro alignment is not handed over in time, the project can miss the deadline targeted to be completed in November 2028. The contractor can also raise claim for delay and demand escalation charges,' the letter added. For a metro project, 'right of way' (ROW) means the legal right to use a specific piece of land for the construction and operation of the metro line. This includes the land occupied by tracks, stations, and other related infrastructure. In Gurugram, the existing and planned metro lines are using the existing right of way on roads after getting requisite permissions from the land owning departments such as HSVP and GMDA. To be sure, the National Highways Authority of India (NHAI) is building a six-lane surface road on the stretch between Hero Honda Chowk and Umang Bhardwaj Chowk at a cost of ₹160 crore, with ₹100 crore earmarked for shifting the utilities and around ₹60 crore will be spent on building this road. The Gurugram Metro line, likely to witness construction soon, will also be built on the left side of this highway road stretch on the extreme left side. A senior GMDA official, meanwhile, said that steps have been initiated to shift high tension towers and feeders of DHBVN to another place under utility shifting on the route of the existing project. Along with this, an agreement has been reached with the concerned with other agencies (DHBVN, NHAI, HVPNL) at 5 other major points regarding shifting of the existing structures, the official added.


Hindustan Times
a day ago
- Hindustan Times
GMRL plans to revise cost of Gurugram Metro project to ₹10,000 crore
Gurugram: The Gurugram Metro Rail Limited (GMRL) has proposed to revise the cost of the Gurugram Metro project from the already approved ₹5,452 crore to double the amount at over ₹10,000 crore. The proposal to be submitted in the next GMRL board meeting, indicates that the cost revision is being done since the sanctioned project cost was based on 2019 rates and six years have elapsed, officials said. The provisions of the detailed project report (DPR) allow 5 per cent per annum escalation in the project, GMRL officials added. GMRL has also reworked estimates for the cost of setting up stations, adding the rolling stacks and change in GST rates. The Gurugram Metro project is now likely to be completed for over ₹10,000 crore instead of the earlier approved ₹5,452 crore, according to the revised estimate proposed by GMRL. The additional costs being proposed by the metro corporation are on account of changes in the cost of alignment and formation from the sanctioned ₹1100 crore to over ₹1700 crore, increase in cost of station buildings from the sanctioned ₹756 crore to over ₹1350 crore. The cost of building the depot has increased from the sanctioned ₹80 crore to over ₹200 crore. Another major increase is the cost of acquiring the rolling stock from the sanctioned ₹480 crore to ₹1250 crore, officials said. According to the GMRL proposal, the sanctioned cost of the project is ₹5,452 crore while the revised cost of the project will be over ₹9,800 crore, with an additional spur to the Gurugram railway station that will cost over ₹400 crore, taking the total cost of the project to over ₹10,000 crore. 'The proposal is likely to be submitted for the next GMRL board meeting scheduled to be held on June 16,' a senior government official, requesting anonymity said. The metro corporation's proposal has justified the increase in the project cost stating that there has been price escalation in the last six years since 2019, when the price was set for the project estimate. It added that GST rates have been increased from 12% to 18% since then. The proposal further said that another reason for the increase in the cost of the metro project is the non-availability of rapid metro infrastructure which was considered while calculating the original cost. There is also an increase in the requirement of coaches for the Gurugram metro project, while the approved DPR took into account only 60 coaches. A new spur has been added to connect the Gurugram railway station with the Sector 5 metro station, the proposal said.


Time of India
a day ago
- Time of India
Telangana asks Centre to reject AP's Godavari link project
Hyderabad: Irrigation minister N Uttam Kumar Reddy has urged the Centre to immediately reject the pre-feasibility report (PFR) of the Godavari–Banakacherla link project proposed by the Andhra Pradesh govt. He also demanded the stoppage of the detailed project report (DPR) and a halt to any tendering process related to the scheme. In a letter to Union jal shakti minister CR Patil, Uttam asserted that the Centre's move to entertain AP's DPR violates the Godavari Water Disputes Tribunal (GWDT) Award of 1980 and the AP Reorganisation Act, 2014, and endangers Telangana's rightful share of river waters. "The project is a direct assault on Telangana's legal entitlements and violates interstate water-sharing protocols. Allowing such a project would undermine the equitable and judicious management of interstate river waters and sets a dangerous precedent against the principles of equity and natural justice," Uttam said. He flagged developments from a June 2 meeting chaired by Union finance ministry official Sajjan Yadav, where the AP govt was reportedly asked to submit the DPR. "This implies that the project is deemed approved. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với sàn môi giới tin cậy IC Markets Tìm hiểu thêm Undo But how can the Centre ask for a DPR without first approving the PFR?" he questioned. He argued that any such move would be procedurally flawed, as DPRs must follow a PFR vetted by the Central Water Commission. Skipping this step would undermine the regulatory framework governing inter-state river projects, he said. He also dismissed criticism that the Congress govt in Telangana had been slow to respond. "When the AP chief minister sought funds from the Centre, I formally objected on Jan 22. Again on June 13, I reiterated our opposition to the PFR, DPR, and tender process. Telangana Congress acted from day one," he said. Follow more information on Air India plane crash in Ahmedabad here . Get real-time live updates on rescue operations and check full list of passengers onboard AI 171 .