Groundwork of Swargate-Katraj underground Metro line yet to begin nearly one year after approval
2
3
Pune: Actual groundwork on the 5.5-km-long Swargate-Katraj Metro line has remained a non-starter almost a year after it was approved in Aug 2024. The addition of two stations on the stretch as an afterthought necessitated re-tendering for the entire project.
The plan was initially sanctioned with three stations. Later, two more Metro stations were included at Balajinagar and Market Yard, taking the total to five stations on the route.
Updating TOI about the most recent status of the line, Maharashtra Metro Rail Corporation Limited (Maha Metro) officials said they are in the process of finishing the re-tendering work and appointing agencies to execute the project in the next two months.
However, work is likely to begin only after the monsoon in Oct 2025.
You Can Also Check:
Pune AQI
|
Weather in Pune
|
Bank Holidays in Pune
|
Public Holidays in Pune
The Swargate-Katraj Metro line is an extension of the PCMC-Swargate corridor, which has been functional since last year. Once completed, it will connect Pune's southern end to Pimpri Chinchwad.
Prime Minister Narendra Modi laid the foundation of the Swargate-Katraj stretch in Sept 2024. Since then, authorities have just been engaged in completing formalities required to start actual work.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Is it legal? How to get Internet without paying a subscription?
Techno Mag
Learn More
Undo
Commuters have long been awaiting the beginning of this line. Many Metro users from Satara Road in particular are hoping for the Katraj extension to become functional at the earliest. "We are looking ahead to the Metro run getting extended till Katraj, but work has not even started yet. There should be some timeline followed by authorities," said Ashok Marathe, a resident of the Padmavati area.
As per the plan, the work is expected to be completed in four years after it starts.
Opposition parties claimed that state govt is planning the launch of this pending groundwork with an eye on the upcoming civic polls. A Congress functionary from the Pune unit pointed out that although the project's foundation was laid "hurriedly" at the hands of the PM, work has failed to take off for a year. "Civic polls are around the corner; state govt will attempt to push ahead with the project in the next couple of months," he claimed.
The addition of three stations has also escalated the project cost to Rs3,637.6 crore from Rs2,954.5 crore — an increase of Rs683 crore. The cost of this additional expense is expected to be shared by the Centre, state, and Pune Municipal Corporation (PMC).
Maha Metro officials said details of the finances were being worked out, including the share of govt and assistance from financial institutions.
A functionary from Shiv Sena (UBT) said that the BJP-led govt has failed to push ahead with several major projects in Pune, including Metro extensions.
"People are struggling to deal with increasing traffic in the city, but govt has ignored these issues. Why can't projects like the Metro be expedited to avoid delays?" he said.
Pune: Actual groundwork on the 5.5-km-long Swargate-Katraj Metro line has remained a non-starter almost a year after it was approved in Aug 2024. The addition of two stations on the stretch as an afterthought necessitated re-tendering for the entire project.
The plan was initially sanctioned with three stations. Later, two more Metro stations were included at Balajinagar and Market Yard, taking the total to five stations on the route.
Updating TOI about the most recent status of the line, Maharashtra Metro Rail Corporation Limited (Maha Metro) officials said they are in the process of finishing the re-tendering work and appointing agencies to execute the project in the next two months.
However, work is likely to begin only after the monsoon in Oct 2025.
The Swargate-Katraj Metro line is an extension of the PCMC-Swargate corridor, which has been functional since last year. Once completed, it will connect Pune's southern end to Pimpri Chinchwad.
Prime Minister Narendra Modi laid the foundation of the Swargate-Katraj stretch in Sept 2024. Since then, authorities have just been engaged in completing formalities required to start actual work.
Commuters have long been awaiting the beginning of this line. Many Metro users from Satara Road in particular are hoping for the Katraj extension to become functional at the earliest. "We are looking ahead to the Metro run getting extended till Katraj, but work has not even started yet. There should be some timeline followed by authorities," said Ashok Marathe, a resident of the Padmavati area.
As per the plan, the work is expected to be completed in four years after it starts.
Opposition parties claimed that state govt is planning the launch of this pending groundwork with an eye on the upcoming civic polls. A Congress functionary from the Pune unit pointed out that although the project's foundation was laid "hurriedly" at the hands of the PM, work has failed to take off for a year. "Civic polls are around the corner; state govt will attempt to push ahead with the project in the next couple of months," he claimed.
The addition of three stations has also escalated the project cost to Rs3,637.6 crore from Rs2,954.5 crore — an increase of Rs683 crore. The cost of this additional expense is expected to be shared by the Centre, state, and Pune Municipal Corporation (PMC).
Maha Metro officials said details of the finances were being worked out, including the share of govt and assistance from financial institutions.
A functionary from Shiv Sena (UBT) said that the BJP-led govt has failed to push ahead with several major projects in Pune, including Metro extensions. "People are struggling to deal with increasing traffic in the city, but govt has ignored these issues. Why can't projects like the Metro be expedited to avoid delays?" he said.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
&w=3840&q=100)

Business Standard
6 minutes ago
- Business Standard
Govt starts work on Auto Mission Plan to make India global industry leader
The government has initiated the formulation of the Automotive Mission Plan 2047 (AMP 2047), a strategic road map aligned with the 'Viksit Bharat @2047' vision to establish India as a global automotive leader, focusing on innovation and sustainability, the Ministry of Heavy Industries said on Thursday. Sub-committees for AMP 2047 have held a meeting to outline objectives and framework and targets for sectoral growth, exports and industry advancement, to help increase India's share in global automotive trade. Seven sub-committees, comprising experts from government, industry, and academia, will guide the development of a comprehensive plan targeting milestones for 2030, 2037, and 2047. "The vision for 2047 is not an aspiration but a strategic road map backed by concrete targets for sector growth, exports, and industry advancement. We must think beyond specific technologies or companies and focus on India's global standing in 2047, aiming to increase our share in global automotive trade through innovation and quality," Additional Secretary in the Heavy Industries Ministry Hanif Qureshi said. The initiative involves various ministries, industry bodies (SIAM, ACMA, CII), academia, and testing agencies for an industry-led effort. "The Ministry of Heavy Industries, Government of India, under the visionary leadership of Prime Minister Narendra Modi, and with the guidance of Minister for Heavy Industries and Steel H D Kumaraswamy has initiated the formulation of the Automotive Mission Plan 2047 (AMP 2047), a strategic roadmap aligned with the 'Viksit Bharat @2047' vision. The inaugural meeting of the AMP 2047 Sub-Committees was held to outline the objectives and framework," an official statement said. AMP 2047 seeks to integrate the collective vision of stake-holders, including Original Equipment Manufacturers (OEMs), auto component manufacturers, policy-makers, academia and end users, to address challenges like technological advancements and charging infrastructure, the Heavy Industries Ministry stated. The meeting was attended by representatives from various ministries, including the Ministry of Power, Ministry of Road Transport and Highways, Ministry of Commerce, Ministry of Petroleum and Natural Gas, DPIIT, Ministry of Environment Forest and Climate Change and industry bodies such as SIAM, ACMA, and CII, FICCI, academic institutions, research think tanks and testing agencies. The AMP 2016-2026 (AMP 2026) is aimed at bringing the Indian Automotive Industry among the top three of the world in engineering, manufacture and exports of vehicles & components; growing in value to over 12 per cent of India's GDP and generating an additional 65 million jobs.


Time of India
18 minutes ago
- Time of India
PM Modi to visit Bihar on Friday, projects worth over Rs 7,000 crore to be launched
PATNA: Prime Minister Narendra Modi will be in Bihar on Friday when he is scheduled to address a public rally in East Champaran district, besides launching development projects worth over Rs 7,000 crore. Tight security measures are in place at Gandhi Maidan in Motihari town, the district headquarters, where Modi is expected to reach in the forenoon and share the stage with Governor Arif Mohammed Khan, Chief Minister Nitish Kumar and a number of Union ministers. Corner Modi Over Trump's Claim, Pahalgam and Bihar Voter List Row: Cong's Monsoon Session Strategy "All arrangements have been made for the public at the venue of the rally, which is expected to attract around five lakh people," East Champaran District Magistrate Saurabh Jorwal said. "People are likely to come from far-off places. As such, parking arrangements have been made for as many as 10,000 buses. The public will be allowed entry into the gigantic canopy through 12 gates, two of which are specially for women," the DM added. Superintendent of Police Swarn Prabhat said that more than 10,000 police personnel have been deployed in the town. They will ensure proper law and order and traffic, under the supervision of 10 IPS officers and 50 officials of the Deputy SP rank, he said. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Villas For Sale in Dubai Might Surprise You Dubai villas | search ads Get Deals Undo "The entry into the canopy will be allowed from 6 am, and all entry points will be sealed after 9 am, over an hour in advance of the PM's scheduled time of arrival," he said. State BJP president Dilip Jaiswal said this will be the PM's 53rd visit to the state, "which shows that Bihar is high on Modi's list of priorities". The development projects launched by him will give a boost to NDA ahead of assembly polls due in just a few months, he said. Of the development projects to be launched, those relating to Railways would be worth Rs 5,385 crore. According to a statement issued by the Railways, these include doubling of the 256-km Darbhanga-Narkatiaganj at Rs 4,079 crore, and Darbhanga-Thalwara and Samastipur-Rambhadrapur lines at Rs 585 crore. Four Amrit Bharat Express trains, all passing through the state and two connecting Bihar with Delhi, will also be flagged by the Prime Minister on the occasion. In addition, road and highways projects worth Rs 1,173 crore will be launched by Modi, who will also give away Rs 162 crore to 40,000 beneficiaries of the PM Awas Yojana (Gramin) and extend "Rs 400 crore community funding" for 61,500 self-help groups. Meanwhile, Leader of the Opposition in the state assembly Tejashwi Yadav, said, "Tomorrow, when the PM will be in Bihar, we hope he will have a few words for soaring crime rate in the state." "In every rally on Bihar's soil, Modi makes it a point to cry hoarse about return of 'jungle raj' if the RJD-led coalition comes to power. He should acknowledge that 'jungle raj' has already arrived. In fact, it has been there during the 20 years the state has been under NDA rule," Yadav alleged. Congress spokesperson Ragini Nayak said that the people of Bihar have been fed up with the "antics of the Prime Minister" during his innumerable visits. "They still remember the rhetorical flourish with which he had pledged Rs 1.25 lakh crore assistance to the state way back in 2015. Nothing came of it," he added. "We would also like to remind the PM of his promise to the people of Motihari, in 2014, that upon assuming power, he would get the area's sick sugar mills revived and enjoy tea sweetened with local produce. The people of Motihari will serve him tea tomorrow, but it will be bland, like his own unfulfilled promises," the Congress leader said. Nayak also alleged that "booth capturing" has given way to "voters' list capturing" as the special intensive revision was being undertaken in the state by the Election Commission "to steal the assembly polls in favour of the BJP".


Time of India
32 minutes ago
- Time of India
India-Nepal border sealed ahead of PM's rally in Motihari today
Motihari: A day ahead of Prime Minister Narendra Modi's rally at Motihari in East Champaran on July 18, the porous India-Nepal border, especially at Raxaul in the district, was sealed on Thursday evening, with the deployment of Anti-terrorism Squad and special branch police personnel. The border will be opened on Friday after the rally of PM Modi. The police have been conducting a massive checking drive at different places on the border, with frisking of all people crossing the border to and from Nepal. The SSB jawans have also launched a day-and-night patrolling. Nishit Kumar, the SSB IG, said that surveillance cameras were installed at several places on the border to check infiltration. East Champaran district magistrate (DM) Saurabh Jorwal said that the Special Protection Group (SPG) of the PM took charge of the meeting venue, Gandhi Maidan, besides deployment of 16 IPS officers around the venue and two helipads, constructed for the occasion. The PM will land on the police line campus helipad, and CM Nitish Kumar and governor Arif Mohammed Khan will land near the firing range helipad. East Champaran superintendent of police (SP) Swarn Prabhat said that 10 companies of police force, including paramilitary, were deployed in the district to maintain law and order, and to keep a close watch on bad elements. Chairman of Railway Board, Satish Kumar; general manager of ECR, Kshtrashal Singh; and other top officials will participate in the PM's meeting, when he will lay foundation stones for rail projects worth Rs 5,398 crores and virtually flag off three Amrit Bharat Express trains. Special trains from Narkatiyaganj, Raxaul and Mehasi to Motihari station will also run on Friday for the convenience of passengers who would attend the PM's meeting scheduled to start around 11am. Local MP Radha Mohan Singh said on Thursday that apart from the three Amrit Bharat trains, two bi-weekly Amrit Bharat Express trains will also run from Motihari to Anand Bihar.