After A Year's Wait, Rs20cr Approved For MahaMetro's Nag River Widening, Work Completed Now
Tired of too many ads? go ad free now
While the official approval came only this week, MahaMetro already initiated and completed the work, ensuring that flood mitigation measures were not delayed. The intervention was part of broader efforts to improve Nag River's flood-carrying capacity and strengthen the city's resilience during the monsoon following the 9/23 havoc that caused heavy floods in the city in 2023.
The project aimed at widening a 450-metre stretch of Nag River to meet flood flow requirements identified by the irrigation department.
The department flagged the original width was inadequate to carry 140 cumecs of water, making it a priority section to be addressed ahead of monsoon. In response, MahaMetro took up the work using its own resources, without waiting for formal fund release. MahaMetro officials also confirmed that the entire work of the Nag River bed widening was completed with only minor work remaining in some places.
The work began around October last year with desilting and excavation.
Originally scheduled for completion in nine months by June 2025, the project got completed by the end of May—one month ahead of the deadline. The riverbed has now been widened to the required 18 metres, with desilting, embankment support, and other key components already completed. Only minor finishing work remains and is expected to be wrapped up shortly.
The Rs19.84 crore has now been cleared under the State Disaster Mitigation Fund, as per a GR issued on June 23. The amount comes from the 15th Finance Commission's provision for disaster management and will cover the expenses MahaMetro already incurred on the project. MahaMetro officials and senior officials from the divisional commissionerate also confirmed the funds will be transferred to MahaMetro following its receival.
Civic officials noted this stretch is crucial given its urban location and past vulnerability to heavy rains. The completion of the work ahead of the monsoon season is expected to ease pressure on the city's drainage network.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
a day ago
- Time of India
Nagpur Metro Phase 3: New Sitabuldi-Koradi corridor announced with future expansion plans
Advt Even as works under Metro Phase 2 continue at a rapid pace across the city and it's outskirts, Nagpurkars can look forward to the next big leap, which is 'Metro Phase 3'.A new metro corridor between Sitabuldi and Koradi has been finalised as part of the recently presented Comprehensive Mobility Plan (CMP), confirmed senior MahaMetro officials after a high-level stakeholder meeting held on Sunday in the presence of chief minister Devendra Fadnavis and Union minister Nitin Gadkari among CMP, prepared by MahaMetro in collaboration with RITES, outlines the development of mass rapid transit corridors in the Nagpur Metropolitan Region based on traffic density , projected ridership, and future mobility is also a proposal for a Metro Phase IV, though the route has not been revealed yet. Among the key proposals in CMP Phase 1 are two High Capacity MRTS Corridors - the 11.5 km Sitabuldi-Koradi corridor and the 25km Mankapur Chowk-Rachana Junction stretch on the Inner Ring Road. Together, they are estimated to cost 8,625 the two, the Sitabuldi-Koradi line was prioritised for development of the metro route. "We have finalised the Sitabuldi-Koradi corridor based on Peak Hour Peak Direction Traffic (PHPDT) assessments. The ridership projections and traffic volumes make it feasible for metro operations," said a senior MahaMetro proposed corridor is expected to cater to a daily ridership of 1.47 lakh commuters by 2054.


Time of India
a day ago
- Time of India
Rs25,567Cr Mobility Plan To Ease Nagpur Gridlock
Nagpur: After months of deliberation and consultations with stakeholders, the much-anticipated ₹25,567-crore Comprehensive Mobility Plan (CMP) for the Nagpur Metropolitan Region (NMR) has entered its final stage before implementation. The latest and most detailed version of the plan was presented on Sunday to chief minister Devendra Fadnavis, Union minister Nitin Gadkari, Nagpur guardian minister Chandrashekhar Bawankule, and representatives from 16 departments during the third and concluding stakeholder meeting. Officials from Nagpur Municipal Corporation (NMC), MahaMetro, Nagpur Improvement Trust (NIT), traffic police, and the district collectorate were present at the meeting held at Metro Bhawan. The CMP, jointly prepared by MahaMetro and RITES, aims to streamline mobility, reduce congestion, and build long-term transport infrastructure for the region, which spans 3,780 sq. km and has a population of over 43.7 lakh. The final version of the plan reflects a significant budget hike of nearly ₹7,000 crore compared to the previous draft, indicating the inclusion of several new infrastructure components and upgrades pegged at ₹18,585 crore. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like 10 Signs Your Dog Loves You More Than Anything Liseer Read More Undo Divided into three phases, the CMP allocates ₹13,927 crore for Phase 1, ₹10,774 crore for Phase 2, and ₹865 crore for Phase 3. A major addition in the latest draft is the proposed 148-km six-lane peripheral ring road, estimated at ₹3,700 crore. This key project, forming part of Phase 2, will act as a regional bypass connecting major highways including NH-44, NH-47, NH-353, NH-53, and the Samruddhi Mahamarg, thereby diverting heavy traffic away from the city core. "Urbanisation is increasing rapidly, especially in areas like the Mihan and Koradi-Kamptee belt. The road and transport infrastructure must be upgraded accordingly. All agencies must act swiftly on the final plan," said Gadkari. The plan focuses heavily on five core areas — non-motorised transport (NMT) facilities, mobility management, public transport, freight infrastructure, and road upgrades. These areas encompass 20 specific sectors, such as electric buses, intelligent traffic systems, flyovers, underpasses, off-street parking, and pedestrian-friendly pathways. The CMP also proposes restrictions on the movement of long-distance commercial vehicles within city limits from 7am to 9pm, relocation of godowns from the core city area, and promotion of smaller, low-emission cargo vehicles in inner zones. Four freight terminals are planned: Automotive Chowk and Kapsi in Phase 1, Gumgaon in Phase 2, and Gondkhairi in Phase 3 — each estimated at ₹20 crore. "To shape the growing expansion of the Nagpur metropolis, we will implement the mobility plan in three phases. I appeal to citizens and public representatives to share their suggestions, so the plan becomes more people-oriented," Fadnavis said during the meeting. Officials confirmed that a 15-day window has been opened for final suggestions or modifications from participating departments. The DPR, once ready, will be submitted to the state and then to the central government for final approval, after which it will be implemented on the ground. The first mobility plan for Nagpur city was prepared in 2013 by the Nagpur Improvement Trust (NIT). It was revised by MahaMetro in July 2018 and updated again with wider inputs through meetings chaired by the divisional commissioner. Infographics: Cost (₹ Cr) NMT Facility Improvement Plan Footpath (1.5–2 m wide)...................Km.........................156.................................131 NMV Lane (2–2.3 m wide)..................Km.........................139.5..............................116.9 At Grade Pedestrian Grade Separated Mobility Management Measures Automatic Off-Street Intelligent Traffic Mgmt Public Bicycle Sharing (PBS)...............Location..................120..................................24 Intersection Public Transport Improvement Plan High Capacity Medium Capacity Electric Bus Terminal New Bus Railway Station Freight Infrastructure Improvement Freight Road Improvement Projects Road Widening (2/4 lanes)..................Km.......................137.1...............................393.5 New Roads (4-lane C/W)....................Km.........................15.6................................89.5 Rail Over Bridges (4-lane)...................Nos............................7..................................200 Flyovers / Peripheral Ring Road (6-lane).............Km.........................148...............................3,700 Total……………………………………………………………………………………….25,567


Time of India
a day ago
- Time of India
Metro Phase 3: Sitabuldi to Koradi Corridor Finalised in Rs8,625-Cr CMP Expansion
1 2 Nagpur: Even as works under Metro Phase 2 continue at a rapid pace across the city and it's outskirts, Nagpurkars can look forward to the next big leap, which is 'Metro Phase 3'. A new metro corridor between Sitabuldi and Koradi has been finalised as part of the recently presented Comprehensive Mobility Plan (CMP), confirmed senior MahaMetro officials after a high-level stakeholder meeting held on Sunday in the presence of chief minister Devendra Fadnavis and Union minister Nitin Gadkari among others. The CMP, prepared by MahaMetro in collaboration with RITES, outlines the development of mass rapid transit corridors in the Nagpur Metropolitan Region based on traffic density, projected ridership, and future mobility needs. There is also a proposal for a Metro Phase IV, though the route has not been revealed yet. Among the key proposals in CMP Phase 1 are two High Capacity MRTS Corridors — the 11.5 km Sitabuldi–Koradi corridor and the 25km Mankapur Chowk–Rachana Junction stretch on the Inner Ring Road. Together, they are estimated to cost Rs8,625 crore. Of the two, the Sitabuldi–Koradi line was prioritised for development of the metro route. "We have finalised the Sitabuldi–Koradi corridor based on Peak Hour Peak Direction Traffic (PHPDT) assessments. The ridership projections and traffic volumes make it feasible for metro operations," said a senior MahaMetro official. The proposed corridor is expected to cater to a daily ridership of 1.47 lakh commuters by 2054. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Why Are Houses In Dubai So Cheap? Villas In Dubai | Search Ads Undo The Sitabuldi-Koradi metro line will diverge from the Kasturchand Park station, and will comprise underground sections also. While details such as the number of stations, alignment, and exact route are yet to be finalised, officials said that once the ongoing 15-day window for suggestions from all concerned departments ends, work on preparing the Detailed Project Report (DPR) will begin. Tenders will be floated subsequently based on the DPR findings. On the other hand, the 25km Mankapur Chowk–Rachana Junction corridor was also identified as a potential high-capacity transit corridor. However, instead of immediately extending metro services, the plan currently involves deploying articulated buses along this route. "We will study the performance of bus operations on this corridor. Based on the data collected and demand observed, necessary modifications in the mobility plan will be made in future phases," the official added. The CMP was designed keeping the horizon year 2030 in mind and includes projections extending up to 2054. It aims to create a sustainable and integrated transport network to support the region's rapid urban expansion. The inclusion of the Sitabuldi–Koradi line is a response to the growing residential and institutional developments towards Koradi, along with the high commuting demand. Another MahaMetro official also confirmed that during the meeting, CM Fadnavis asked officials to begin work on developing a financial model for the CMP. "Fadnavis pointed out that while the vision is clear, the financing and revenue generation model should also be added in the CMP. He has directed us to prepare a model outlining funding sources, investment recovery strategies, and ways to ensure long-term sustainability of the proposed infrastructure," the official said. With Metro Phase 3 taking shape and CMP inching closer to final approval, Nagpur is on track to emerge as a model city for multi-modal urban mobility.