Moses Mabhida Stadium to undergo major refurbishment over the next 30 months
Image: Doctor Ngcobo / Independent Newspapers
The refurbishment of Moses Mabhida Stadium (MMS) in Durban is expected to be completed in another 30 months, costing an estimated R284 million.
The request for the extension of the contract to conduct emergency remedial work on the concrete and roof structure for MMS was noted at the Community Services Committee (CSC) on July 17.
The refurbishment of the MMS started on March 28, 2024, and is due to end on September 28, 2025.
However, the municipality stated that some projects were delayed as priority was provided to foundation packages that are the backbone, while the remaining packages envisaged for completion in 2025/2026 and 2026/ 2027 financial years.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Next
Stay
Close ✕
On May 31, 2025, the city aimed to extend the contract for 30 months due to the identified structural complications and risks.
According to the CSC report, the extension of the current scope to complete the original work packages, but focusing on lists that were subject to further testing and were dependent on completion of the foundation packages, is:
PROPOSED BUDGETS
Civil: MMS structural steel painting - R19 million
Electrical: sky car upgrade - R25 million
Civil: infrastructure upgrade, expansion joints - R35 million
Civil: infrastructure upgrade cables and canvas roof system - R135 million
Lighting: upgrade - floodlight to LED - R55 million
Civil: replacement of arch cladding MMS - R2 million
Upgrade of audio visual system - R6 million
Big swing upgrade, zipline, and adventure walk - R4 million
Viewing platform - R2 million
In a statement earlier this month, the municipality stated that the refurbishment project at the MMS is progressing well. The upgrades to the iconic stadium, which has been in operation for 15 years, have been strategically phased to minimise disruptions to scheduled activities and public access.
The committee acknowledged the importance of completing the remaining work within the revised timeline and emphasised the need for close monitoring to ensure that the project meets both quality and compliance standards.
The renovation will also see the introduction of the following new features to ensure the stadium remains a premier tourist destination:
New Viewing Platform with 60% increase in floor area featuring a cantilevered glass floor for an 'Air Walk' experience.
New Sky Car with increased travel time, which will be accessible to people with disabilities.
New Big Swing with improved access to the launch platform.
New Zip Line, which ends at the People's Park.
Compression Ring Walk, which provides panoramic views with a sea-facing bungee jump option.
The municipality stated that the refurbishment not only secures MMS as a premier venue for sports, concerts, and cultural events but also contributes to local job creation, skills development, and small business support through the procurement of services from local contractors.
Despite the renovations, the stadium has successfully hosted several high-profile events, including the 2025 Nedbank Cup Final and the Toyota Cup between Kaizer Chiefs and Asante Kotoko on July 26, 2025.
zainul.dawood@inl.co.za
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

IOL News
7 minutes ago
- IOL News
Women's rugby is booming, but safety relies on borrowed assumptions from the men's game
The Springbok women's rugby squad on Table Moountain before their departure for Rugby's Women's World Cup this month. Image: Henk Kruger Independent Newspapers Kathryn Dane, Isla Shill and Stephen West Rugby union, commonly known as just rugby, is a fast-paced and physical team sport. More girls and women around the world are playing it now than ever before. As of 2021, women's rugby reached a record 2.7 million players globally, a 25 per cent increase over four years, and by 2023, women's rugby participation was growing at a rate of 38 per cent year-over-year. Countries including Australia, England, Ireland and the United States offer professional contracts for women's teams. While these remain modest compared to the men's game, they still represent a clear step forward. Canada's senior women's XVs team is currently ranked second in the world and heading into the 2025 Rugby World Cup, which kicks off on Aug. 22 in England. The national sevens team also captured silver at the 2024 Paris Olympics — further evidence of the game's growing competitiveness in Canada. However, many systems, including coaching and medical support, have not kept pace with the demands of elite competition. With visibility increasing ahead of the 2025 World Cup, stronger institutional support is needed to match the sports' growing professionalism and popularity. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading These concerns are especially urgent as the women's game becomes more physical and professionalized, and players are hit harder and more often. Unlike men's rugby, women's teams often operate with fewer medical or coaching support resources, which can lead to inconsistent or absent injury prevention programs. Compounding the risk is the fact that many women also come to rugby later in life, often with less experience in contact sports. This delayed exposure restricts proper tackle skill development and player confidence in contact. This means safe tackling is even more important. Without proper supports, the physical risks of the game may outweigh its benefits. United States' Alex Sedrick is stopped by Canada's Carissa Norton during Vancouver Sevens women's rugby action, in Vancouver this year. Image: THE CANADIAN PRESS/Ethan Cairns Science is still playing catch-up While women's rugby is growing rapidly, the science behind it is has not kept pace. Most of what we know about rugby safety — how to tackle, how much to train or when it's safe to return to play after injury — largely comes from research on men. Decisions around coaching and player welfare have been based on male data, leaving female players under-served and potentially at greater risk. While these foundations may well apply to girls and women, the problem is we don't yet know for sure. Only four per cent of rugby tackle research has focused on women. Much of the early evidence on girls rugby comes from Canada, underscoring the country's leadership in this space. Still, most coaches and clinicians rely on a 'one-size-fits-all' approach that may not account for menstrual cycles, pregnancy, different injury profiles or later sport entry. The differences matter because strength, speed and injury risk all vary. Women are 2.6 times more likely than men to sustain a concussion. Gender also shapes access to training, care and facilities, often limiting opportunities for women to develop safe tackling skills, receive adequate support and train in safe, well-resourced environments, factors that impact both performance and safety. Even safety tools reflect this gap. World Rugby's Tackle Ready and contact load guidelines were designed around male athletes. While well-intentioned, we know little about how they work for girls and women. Instead of discarding these tools, we need to adapt and evaluate them in female contexts to ensure they support injury prevention and provide equal protection. Results of a PubMed search of peer-reviewed literature on girls' and women's rugby since 2015, showing year-on-year increases in publications. Image: Author provided Women's rugby needs better data Change is underway. More research and tools are being designed specifically for girls and women. A search of PubMed, a database of published biomedical research, reveals a steep rise in studies on women's rugby over the past decade, especially in injury surveillance, injury prevention, performance, physiology and sociocultural contexts. New rule trials, such as testing lower tackle heights, are being evaluated on women athletes. New technologies like instrumented mouthguards and video analysis are also helping researchers understand how girls and women tackle, how head impacts happen and how they can be prevented. Much of this new research is led by our team at the Sport Injury Prevention Research Centre, a pan-Canadian, multidisciplinary group focused on moving upstream to prevent concussions in adolescent girls' rugby. The women's game is also driving its own innovations. Resources like World Rugby's Contact Confident help girls and women safely build tackle skills, particularly those new to contact sport. Researchers are analyzing injury patterns, interviewing players and coaches and studying return-to-play pathways that reflect girls' and women's physiology and life stages. The scope of research is also expanding to pelvic health, breast protection and more tailored injury prevention. Global collaboration is making this work more inclusive, spanning different countries, skill levels and age groups, not just elite competitions. But this is just the start. A golden opportunity lies ahead Girls' and women's rugby is experiencing unprecedented growth. Rising participation, media attention and new sponsorships are fuelling momentum. It's a golden opportunity to build strong, sustainable foundations. Gold-standard support requires focused, ongoing research and a commitment to sharing that evidence with players, coaches, health-care providers and policymakers. It's time to build systems for women's rugby based on women's data, not borrowed assumptions from the men's game. But challenges remain. Some national teams still have to raise funds to attend World Cups. Others train without consistent access to medical or performance staff — clear signs that the women's game is still catching up. To sustain and accelerate the growth of girls' and women's rugby, the sport deserves more resources and research tailored specifically to participants. A 'one-size-fits-all' model no longer works. By investing in systems that are safer, focused on prevention, more inclusive and grounded in evidence, we can build a thriving future for women's rugby that lasts for generations to come. Kathryn Dane is a postdoctoral associate, University of Calgary, Isla Shill a p ostdoctoral research fellow in Injury and Illness Epidemiology in Sport, University of Edinburgh and Stephen West is a p ostdoctoral research associate, Kinesiology, University of Calgary

IOL News
17 hours ago
- IOL News
Major refurbishment set to last 30 months on the cards for Moses Mabhida Stadium
The Moses Mabhida Stadium in Durban is set for a comprehensive refurbishment costing R284 million, with an expected completion date in 2027. Image: Doctor Ngcobo / Independent Newspapers The further refurbishment of Moses Mabhida Stadium (MMS) in Durban could be completed in 30 months, at an estimated R284 million, if a tabled proposal from an eThekwini Municipality's sub-committee is approved. The request for the extension of the contract to conduct emergency remedial work on the concrete and roof structure for MMS was noted at the Community Services Committee (CSC) on July 17. The CSC is a sub-committee of the city's executive committee. The refurbishment of the MMS started on March 28, 2024, and was due to end on September 28, 2025. However, the municipality stated that some projects were delayed as priority was provided to foundation packages that were the backbone, while the remaining packages envisaged for completion in 2025/2026 and 2026/ 2027 financial years. On May 31, 2025, the city aimed to extend the contract for 30 months due to the identified structural complications and risks. According to the CSC report, the extension of the current scope to complete the original work packages, but focusing on lists that were subject to further testing and were dependent on completion of the foundation packages, are: PROPOSED BUDGETS Civil: MMS structural steel painting - R19 million Electrical: sky car upgrade - R25 million Civil: infrastructure upgrade, expansion joints - R35 million Civil: infrastructure upgrade cables and canvas roof system - R135 million Lighting: upgrade - floodlight to LED - R55 million Civil: replacement of arch cladding MMS - R2 million Upgrade of audio visual system - R6 million Big swing upgrade, zipline, and adventure walk - R4 million Viewing platform - R2 million In a statement earlier this month, the municipality indicated that the refurbishment project at the MMS is progressing well. The upgrades to the stadium, which has been in operation for 15 years, have been strategically phased to minimise disruptions to scheduled activities and public access. The committee acknowledged the importance of completing the remaining work within the revised timeline and emphasised the need for close monitoring to ensure that the project meets both quality and compliance standards. The renovation will also see the introduction of the following new features to ensure the stadium remains a premier tourist destination: New Viewing Platform with 60% increase in floor area featuring a cantilevered glass floor for an 'Air Walk' experience. New Sky Car with increased travel time, which will be accessible to people with disabilities. New Big Swing with improved access to the launch platform. New Zip Line, which ends at the People's Park. Compression Ring Walk, which provides panoramic views with a sea-facing bungee jump option. The municipality stated that the refurbishment not only secured MMS as a premier venue for sports, concerts, and cultural events but also contributed to local job creation, skills development, and small business support through the procurement of services from local contractors. Despite the renovations, the stadium has successfully hosted several high-profile events, including the 2025 Nedbank Cup Final and the Toyota Cup match between Kaizer Chiefs and Asante Kotoko on July 26.

IOL News
21 hours ago
- IOL News
Moses Mabhida Stadium to undergo major refurbishment over the next 30 months
The Moses Mabhida Stadium in Durban is set for a comprehensive refurbishment costing R284 million, with an expected completion date in 2027. Image: Doctor Ngcobo / Independent Newspapers The refurbishment of Moses Mabhida Stadium (MMS) in Durban is expected to be completed in another 30 months, costing an estimated R284 million. The request for the extension of the contract to conduct emergency remedial work on the concrete and roof structure for MMS was noted at the Community Services Committee (CSC) on July 17. The refurbishment of the MMS started on March 28, 2024, and is due to end on September 28, 2025. However, the municipality stated that some projects were delayed as priority was provided to foundation packages that are the backbone, while the remaining packages envisaged for completion in 2025/2026 and 2026/ 2027 financial years. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ On May 31, 2025, the city aimed to extend the contract for 30 months due to the identified structural complications and risks. According to the CSC report, the extension of the current scope to complete the original work packages, but focusing on lists that were subject to further testing and were dependent on completion of the foundation packages, is: PROPOSED BUDGETS Civil: MMS structural steel painting - R19 million Electrical: sky car upgrade - R25 million Civil: infrastructure upgrade, expansion joints - R35 million Civil: infrastructure upgrade cables and canvas roof system - R135 million Lighting: upgrade - floodlight to LED - R55 million Civil: replacement of arch cladding MMS - R2 million Upgrade of audio visual system - R6 million Big swing upgrade, zipline, and adventure walk - R4 million Viewing platform - R2 million In a statement earlier this month, the municipality stated that the refurbishment project at the MMS is progressing well. The upgrades to the iconic stadium, which has been in operation for 15 years, have been strategically phased to minimise disruptions to scheduled activities and public access. The committee acknowledged the importance of completing the remaining work within the revised timeline and emphasised the need for close monitoring to ensure that the project meets both quality and compliance standards. The renovation will also see the introduction of the following new features to ensure the stadium remains a premier tourist destination: New Viewing Platform with 60% increase in floor area featuring a cantilevered glass floor for an 'Air Walk' experience. New Sky Car with increased travel time, which will be accessible to people with disabilities. New Big Swing with improved access to the launch platform. New Zip Line, which ends at the People's Park. Compression Ring Walk, which provides panoramic views with a sea-facing bungee jump option. The municipality stated that the refurbishment not only secures MMS as a premier venue for sports, concerts, and cultural events but also contributes to local job creation, skills development, and small business support through the procurement of services from local contractors. Despite the renovations, the stadium has successfully hosted several high-profile events, including the 2025 Nedbank Cup Final and the Toyota Cup between Kaizer Chiefs and Asante Kotoko on July 26, 2025.