KCR acted not as govt head but as administrative executive: Panel report on Kaleshwaram project

KCR acted not as govt head but as administrative executive: Panel report on Kaleshwaram project

The Print2 days ago
While the Bharatiya Janata Party (BJP) and the Congress, then in opposition, have been accusing KCR and his family of using the project 'as their personal ATM to plunder the people of Telangana,' the Medigadda barrage developed cracks and six piers sank within four years of the project's inauguration and only weeks ahead of the November 2023 assembly polls.
The three barrages under inquiry were Medigadda, Sundilla and Annaram, the first of which became a symbol of the alleged mis-execution of Rs 1 lakh crore Kaleshwaram Lift Irrigation Project on Godavari river during the previous Bharat Rashtra Samithi (BRS) regime.
Hyderabad: The judicial commission of inquiry on Kaleshwaram has held former Telangana chief minister K.Chandrasekhar Rao 'directly and also vicariously accountable for the irregularities and the illegalities in planning, construction, completion, operation and maintenance of the three barrages,' under the mega irrigation project.
KCR had inaugurated the BRS government's mega showpiece Kaleshwaram Lift Irrigation Project (KLIP) at Medigadda in June 2019, i.e., in the first year of his second term.
'It can be categorically held that there is rank irregularity from the stage of conceptualization of Kaleshwaram project till the issuance of administrative approvals on 1.3.2016 for construction of the three barrages. This is not the decision of the government but of individuals,' said the Pinaki Chandra Ghose commission.
Sticking to its election promise, the Revanth Reddy-led Congress government, in March 2024, appointed Pinaki Chandra Ghose, a former judge of the Supreme Court, to conduct judicial Inquiry on allegations of irregularities, corrupt practices and embezzlement of public funds via the project.
The commission submitted its report last week and the contents were revealed by irrigation minister Uttam Kumar Reddy, in presence of the CM and other ministers after the Telangana cabinet reviewed the report on Monday.
'The then chief minister is pre-determined and bent upon to construct barrage at Medigadda at his free choice and the authorities associated with the decision making facilitated them,' said the report.
The commission noted that the reason given—non-availability of water at Tummadihetti, the original site—for shifting the barrage location to Medigadda 'does not appear to be sincere and honest.'
'The decision of construction of barrage at Medigadda and also at Annaram and Sundilla is solely of the then chief minister,' the commission said, noting that an expert committee had earlier concluded Medigadda site as 'not advisable and also not economical.'
The commission 'conclusively held that the issuance of government orders according administrative approval of Rs 2591 crore for construction of Medigadda project is not placed before the cabinet and is issued pursuant to the orders of the minister (irrigation) and the chief minister.'
The consequential failure of the barrage, the report said, is on account of impounding of water, among other reasons.
'It has categorically been observed and held that the then chief minister has directed the authorities to store water in the barrages to their full capacity for the purpose of lifting water through pump houses. Therefore, the then chief minister acted against the interests of the state and had no sincere, honest and conscientious mind to protect and safeguard the three barrages constructed at huge cost of thousands of crores of public money.'
'The chief minister acted not as the head of the government but as the administrative executive himself.'
KCR, then irrigation minister Harish Rao had appeared before the commission earlier this year.
Presenting the findings of the report, irrigation minister Uttam said the 'irrigation project described as the life line of Telangana has collapsed, after incurring huge expenditure and pushing the state into huge debts.'
Later, CM Reddy said that his government 'will table the report in the assembly for a thorough discussion and to decide on course of action based on the recommendations.'
The report also blamed former chief secretary S.K.Joshi, engineer in chief C.Muralidhar and others of suppressing an expert committee report with malicious intention to enable the then minister for irrigation and the then chief minister to go ahead with their intention to construct the barrage at Medigadda.
'Thus, by suppressing the report, they facilitated to construct barrage at Medigadda and they indulged in this malicious act at the cost of huge public money and putting the economy of the state at stake (sic),' it added.
The report is expected to be presented in the Telangana legislature during the ensuing Monsoon session.
(Edited by Tony Rai)
Also Read: The rise of PV Krishna Reddy & MEIL — 2nd largest electoral bonds donor that worked on Kaleshwaram
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Speak less, fill vacant cabinet berths, says Raj Gopal to Revanth
Speak less, fill vacant cabinet berths, says Raj Gopal to Revanth

Time of India

timean hour ago

  • Time of India

Speak less, fill vacant cabinet berths, says Raj Gopal to Revanth

Hyderabad: Congress MLA Komatireddy Raj Gopal Reddy on Wednesday said his suggestion to chief minister A Revanth Reddy is to control his language, speak less, fill the three vacant cabinet berths, and focus more on the development of Telangana. Of late, Raj Gopal has been making statements against Revanth, which has been termed as "pressure tactics" by Congress seniors, to secure a cabinet berth for himself. Raj Gopal, who has openly expressed that he is upset with the party for not fulfilling its promise of allotting him a cabinet berth, met Karnataka deputy chief minister DK Shivakumar at a hotel in Hyderabad and termed it a courtesy call. Shivakumar was in the city on a personal visit. You Can Also Check: Hyderabad AQI | Weather in Hyderabad | Bank Holidays in Hyderabad | Public Holidays in Hyderabad Speaking to media persons after the meeting, Raj Gopal said Revanth should focus more on explaining to the people what the Congress govt was doing for their welfare, instead of going after the opposition. "The Congress leadership had promised me a cabinet berth. Revanth will continue to be the CM for another three-and-a-half years. Thereafter, the party high command will decide based on the public mandate in the next elections. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Daughter thought she had saved 'cute bunnies.' The vet pales when he realizes what they really are Interesticle Undo Revanth's comments on social media journalists were not fair," he said. He also questioned the lack of action by Revanth against Andhra Pradesh-based contractors involved in the Kaleshwaram project. "Several Andhra contractors looted public money, but Revanth has been delaying taking action against them on the pretext of investigations and inquiry commissions. Over 20 Andhra-based contractors were looting Telangana's resources. I will expose them soon," he said, vowing to speak out against anyone looting the state's wealth — be it in the form of land, sand, or contracts, irrespective of party affiliations. Responding to Raj Gopal's comments, TPCC disciplinary action committee chairman and MP Mallu Ravi said they will speak to him in a day or two. "Based on his version, we will decide our future course of action. We were busy making arrangements for the dharna at Jantar Mantar in New Delhi. But I want to make it clear that indiscipline will not be tolerated, irrespective of the leader's stature. Everyone has to follow the party's discipline," he said, when asked whether disciplinary action would be taken against the MLA.

Tewari raises railway station work, govt says no fixed timeline can be given for completion
Tewari raises railway station work, govt says no fixed timeline can be given for completion

Indian Express

timean hour ago

  • Indian Express

Tewari raises railway station work, govt says no fixed timeline can be given for completion

The long-promised redevelopment of the Chandigarh Railway Station under the Amrit Bharat Station (ABS) Scheme remains mired in delays and uncertainty, with the Ministry of Railways admitting in Parliament that no fixed timeline can be provided for its completion. This comes in a response, given to a question raised by MP Manish Tewari in the Lok Sabha on August 6. Speaking on the matter, Chandigarh MP Tewari expressed his disappointment, stating, 'It is unfortunate that rather than recognising the utter chaos, anarchy and mayhem that prevails at the railway station, the ministry's response avoids accountability. The answer gives no timeline for when the renovation will finally be over and fails to offer any solution to the persistent parking mess. In all, the reply betrays the total inefficiency of the Railway Ministry.' Meanwhile, in its written reply, the ministry confirmed that Chandigarh Railway Station is being redeveloped under the ABS scheme with a sanctioned cost of Rs 436.29 crore. While structural works on the Panchkula and Chandigarh sides have been completed — including platform upgradation, foot overbridges, parking areas, and new building finishes — the ministry admitted that no definite completion date can be given due to numerous on-ground challenges. These include statutory clearances (fire, heritage, airport), shifting of utilities (water, sewage, power, optical fibre), ongoing train operations, and speed restrictions due to nearby high-voltage lines. All these factors, the ministry claimed, are affecting progress, and thus no timeline can be committed at this stage. The station's inclusion in the national ABS scheme is part of a broader plan to modernise 1,337 stations across the country, out of which work at 105 has already been completed. However, work at Chandigarh railway station is still not complete. The ministry stated that routine inspections are being conducted and cleanliness is being maintained, but passengers and local residents continue to face overcrowding and inadequate amenities. Chandigarh falls under Northern Railway, which has been allocated Rs 2,216 crore under Plan Head-53 for customer amenities for the financial year 2025–26, mentioned the ministry in its response to Tewari's question.

Disclose solar power price supplied to other states, HC tells SECI
Disclose solar power price supplied to other states, HC tells SECI

Time of India

timean hour ago

  • Time of India

Disclose solar power price supplied to other states, HC tells SECI

Vijayawada: The high court on Wednesday directed Solar Energy Corporation of India (SECI) to disclose the price of solar power at which it was supplying to other states, at the time it entered into an agreement to supply power to Andhra Pradesh at Rs 2.49 per unit. The court also directed to place the orders of Andhra Pradesh Electricity Regulatory Commission (APERC) approving the unit price quoted by SECI. CPI state secretary K Ramakrishna and then TDP MLA and present finance minister Payyavula Keshav filed separate PILs in the high court challenging the agreement made by the then YSRCP govt with SECI for supply of 7,000 MW of solar power at Rs 2.49 per unit. The counsel for the petitioner argued that SECI made an agreement to supply solar power at Rs 2.49 per unit with AP, but the same SECI made an agreement with Gujarat govt for supply of solar power at Rs 1.99 per unit. The counsel further said that the power purchase price should be derived through tender route according to the Electricity Act but it was not followed while entering into an agreement with SECI. Arguing on behalf of the state govt, advocate general Dammalapati Srinivas said the high court has allowed APERC to decide the unit price and it has approved the price quoted by SECI. The petitioners can challenge the decision of APERC if they have any grievances on the same. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like For all your EV needs ScottishPower Learn More Undo The counsel for SECI submitted that the per unit price of solar power used to be anywhere between Rs 2.52 and Rs 2.61 at the time when it entered an agreement with AP. The unit price offered to AP was the lowest at that time when compared to other states, he stated. Considering the arguments, the high court bench headed by Chief Justice Dhiraj Singh Thakur and Justice Ravi Cheemalapati directed SECI to submit an affidavit with details of prices at which it had made agreements with other states at the time of entering into the agreement with AP.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store