Pasir Gudang Highway: Phased road opening expected soon
Johor Public Works, Transport, Infrastructure and Communications Committee chairman Mohamad Fazli Mohamad Salleh said the road opening would be carried out in stages involving several sections along the five-kilometre work area, depending on the level of readiness and current safety aspects.
"This will allow the completed sections to be opened earlier so that the public can begin using them and enjoy the benefits.
"If we want to expedite the project, we would have to open only one lane while work is ongoing. However, that would cause traffic disruptions. So, we need to strike a balance...it cannot be reduced to fewer than the two lanes currently in use," said the Bukit Pasir Assemblyman, who visited the site to see the work progress of the project last night.
Commenting on the latest development at the project site, Mohamad Fazli said his primary focus was on two key locations - at CH1170 (in front of Petron) and CH4200 (near the Wau replica roundabout), as these areas were riddled with potholes, poorly lit and had uneven road surfaces.
He said that works such as road surfacing and lighting installation were being actively carried out, with over 467 patching works completed since January.
The contractor, he said, had also given an assurance that the installation of 197 streetlights along the five-kilometre route would be completed by July 11, complemented by additional spotlights and warning blinkers at blind spots to enhance road user safety.
Meanwhile, Mohamad Fazli said motorists whose vehicles were damaged due to potholes along the project route could file a compensation claim to the contractor or concessionaire.
"This provision is part of the contract between the Public Works Department (PWD) and the concessionaire. The road must be maintained in a safe condition at all times. If damage or an accident occurs due to unsafe infrastructure, road users can lodge a police report and submit a claim with photographic evidence of the incident location," he said.
The Pasir Gudang Highway serves as the main route to Pasir Gudang, the largest industrial area in the country, which is home to more than 5,000 factories across various industries. It also connects two major ports — Johor Port and Tanjung Langsat Port (PTL).
Menteri Besar Datuk Onn Hafiz Ghazi announced last February that the Pasir Gudang Highway upgrading project (Phase 3), involving the stretch from the Perling Elevated Interchange to the North-South Expressway On-ramp, would see the highway expanded from four lanes to six lanes at a cost of RM301.5 million.
The project is expected to be completed by June 2028.
Meanwhile, the project to upgrade the Pasir Gudang Highway (Phase 2B), covering the stretch from the Bandar Seri Alam/Taman Rinting Interchange to Pasir Gudang, will also be widened from four lanes to six lanes at a cost of RM78 million. It is scheduled for completion by Feb 2026. — BERNAMA
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Sun
2 hours ago
- The Sun
Solar street lights installed on Gerik-Jeli highway, motorists thankful
'THE solar lights are already street is let the light pole get hit (for the area) to become dark again.' That was among the reactions from excited members of the public when solar-powered street lights were installed along the East-West Highway (JRTB) Gerik-Jeli route. In fact, through the comments section on aTikTok video post by @Muhammad Asyraaf, most users were also excited as they frequently use the route, besides praising the Public Works Department (JKR). TikTok user catalognonaa said: 'Alhamdulillah after this, (I won't) be afraid to return from the kampung to the university. The road is always dark and dangerous (to travel) as well. 'Great, they've installed the lights. Don't forget to do maintenance ya,' reminded @Jai. 'It's really good to install solar lights. No need to go through the trouble of laying cables. Not to mention cables getting stolen,' said another user. Earlier, Kosmo reported that Perak JKR would install 385 solar-type street lights on the JRTB Gerik-Jeli route this month. Perak JKR director, Zamri Mat Kasim reportedly said the installation of solar-type street lights was made at the accident location involving a bus carrying 42 Universiti Pendididkan Sultan Idris (UPSI) students with a Proton Alza last month.


Free Malaysia Today
21 hours ago
- Free Malaysia Today
E-hailing firms Maxim, InDrive risk losing licences, says Loke
Transport minister Loke Siew Fook said both inDrive and Maxim had started making improvements. (Bernama pic) PETALING JAYA : Russian-founded e-hailing firms inDrive and Maxim risk having their licences revoked if they fail to ensure their drivers comply with key requirements, including obtaining e-hailing vehicle permits. Transport minister Loke Siew Fook said both companies were found to have allowed their drivers to operate without an EVP, a key condition under their operating licence, Bernama reported. Loke acknowledged that while the Land Public Transport Agency (Apad) had recommended revoking the companies' licences in April for allowing their drivers to operate without EVPs, doing so could burden drivers and passengers who relied on the platforms. Both operators had appealed and the ministry granted a three-month monitoring period starting July 24. 'We've outlined the steps they must take, and they've started making improvements,' Loke said after launching the Kota Setar service in Alor Setar today. 'As this is their first offence, we are giving them the opportunity to rectify the issues. 'However, if they continue to violate (e-hailing) conditions, their licences may be suspended or cancelled.' In September 2022, the road transport department had raided inDrive's Malaysian office and discovered that the firm was operating with an expired licence. In 2023, Maxim was also raided by Apad officers for allowing vehicles to operate without a valid permit.

Malay Mail
a day ago
- Malay Mail
First offence: Loke says Maxim, InDrive given chance to fix compliance issues
ALOR SETAR, July 28 — The Ministry of Transport (MOT) has issued a stern warning to e-hailing operators, Aist Malaysia Sdn Bhd (Maxim) and ID Applications Sdn Bhd (InDrive), to comply with all service requirements to operate in the country, including the mandatory E-Hailing Vehicle Permit (EVP), or risk having their licences suspended or revoked. Minister Anthony Loke said both companies are currently under a three-month monitoring period, during which they are expected to demonstrate full compliance. 'Any operator facing enforcement action has the right to appeal to the MOT, and both companies have done so. 'We've outlined the corrective actions they must take, and we've observed that they've begun making improvements. As this is their first offence, we are giving them the opportunity to rectify the issues. 'However, if they continue to violate the conditions, their licences may be suspended or cancelled,' he told reporters after launching the Kota Setar service in Kota Setar today. Loke acknowledged that the offences committed by the two companies, primarily operating without EVP compliance, were serious. However, he said the ministry also took into account the potential impact on drivers and passengers who rely on both platforms. 'If we were to shut them down immediately without giving a chance for improvement, we'd be facing backlash from affected users. As with any decision, there will always be differing opinions,' he added. On April 24, the Land Public Transport Agency (APAD) issued a Notice of Licence Revocation to both Maxim and InDrive, with effect from July 24, after an audit revealed major compliance failures, particularly related to EVP requirements. Following this, both companies submitted appeals to the MOT, which accepted and granted them a three-month probationary period starting July 24 to fully adhere to service conditions, failing which would result in regulatory action, with no further leniency. — Bernama